Central Kit itchen Upgrade December 17, 2018 Race to the Finish - - PowerPoint PPT Presentation

central kit itchen upgrade
SMART_READER_LITE
LIVE PREVIEW

Central Kit itchen Upgrade December 17, 2018 Race to the Finish - - PowerPoint PPT Presentation

Sequim School Dis istrict - Board Meeting Central Kit itchen Upgrade December 17, 2018 Race to the Finish December 17, 2018 1 Current Configuration / Option 3 Allows for more matching state funds 100% Code compliant


slide-1
SLIDE 1

December 17, 2018

“Race to the Finish”

Sequim School Dis istrict - Board Meeting Central Kit itchen Upgrade

December 17, 2018 1

slide-2
SLIDE 2

Current Configuration / Option 3

➢ Allows for more matching state funds ➢ 100% Code compliant commercial kitchen ➢ Efficient work space ➢ Clears the area for new school ➢ Remains in budget

December 17, 2018

2

slide-3
SLIDE 3

Kitchen Details

➢ 4080 SF ➢ New and modern kitchen equipment ➢ New freezer / cooler space and configuration ➢ New roof structure ➢ Designed for tie-in with future school construction

December 17, 2018

3

slide-4
SLIDE 4

Schedule Overview

SCHEDULE ➢ July / August – New kitchen area abatement and new kitchen construction began ➢ August / September - Full site structure deconstruction commenced ➢ November/December – Deconstruction complete – Site ready for new school structure ➢ January – New Kitchen to be completed

December 17, 2018

4

slide-5
SLIDE 5

Deconstruction Progress….Gone!

December 17, 2018

5

slide-6
SLIDE 6

Construction Progress….Moving Forward!

December 17, 2018

6

slide-7
SLIDE 7

Challenges Overcome

PROJECT CHALLENGES

➢ OPA portable classroom delivery /design / permitting / completion ➢ Wooden roof truss manufacturing backlog / delivery timelines ➢ Material / equipment spec’ing, ordering and delivery in very short timelines ➢ Extensive underground utility tunnels and concrete deconstruction ➢ Concealed asbestos piping

December 17, 2018

7

slide-8
SLIDE 8

Schedule Update/ Status

CURENT HIGHLIGHTS

➢ All abatement complete ➢ Old School 100% deconstructed ➢ New Kitchen is fully enclosed ➢ Interior electrical, mechanical, structural

  • ngoing

➢ Mechanical and Kitchen equipment arriving daily.

December 17, 2018

8

slide-9
SLIDE 9

Wrap Up

➢ OPA portable classrooms occupied.

Final gym/ classroom fire alarm system procurement ongoing. ➢ All kitchen interior work ongoing ➢ Kitchen and mechanical equipment arriving on site ➢ Racing to January 2019 completion…no sacrifice on quality

December 17, 2018

9

slide-10
SLIDE 10

A big Thank You to our Partners

December 17, 2018

10