Centinela Valley Union High Centinela Valley Union High School - - PowerPoint PPT Presentation
Centinela Valley Union High Centinela Valley Union High School - - PowerPoint PPT Presentation
Centinela Valley Union High Centinela Valley Union High School District Measure CV Program Update March 11, 2013 Site Construction Progress Site Updates Hawthorne High School Lawndale High School Leuzinger High School 2 TELACU
Site Construction Progress Site Updates
Hawthorne High School Lawndale High School Leuzinger High School
TELACU Construction Management
2
Hawthorne High School Site Aerial
Aerial January 2013
TELACU Construction Management
Aerial January 2013
3
Hawthorne High School
Building A & B – Rendering of Counseling and Student Services & Media Center
Building A Building B TELACU Construction Management
4
Hawthorne High School
Building A - Counseling & Student Services
The Counseling & Student Services building is on schedule for a summer completion. Since
- ur last update steel has been erected, underground utilities installed and the slab-on-grade
February 2013
TELACU Construction Management
- ur last update steel has been erected, underground utilities installed and the slab-on-grade
has been placed. Steel stud framing and mechanical, electrical and plumbing rough-ins are proceeding.
5
Hawthorne High School
Building B - Media Center
February 2013
TELACU Construction Management The Media Center has the grade beam excavated and the footings concrete
- poured. Building B will start being erected after Building C.
6
Hawthorne High School
Building C - Sciences Building
10 Biology Classrooms 3 Chemistry Labs 1 Physics Classroom Workrooms
Rendered view from the corner of El Segundo and Inglewood intersection
Workrooms TELACU Construction Management
Rendering of courtyard view
7
Hawthorne High School
Science Building
The Science Building has the grade beam excavated with the formwork in place
February 2013
TELACU Construction Management The Science Building has the grade beam excavated with the formwork in place and the footings concrete poured.
8
Lawndale High School Site Aerial
COSTCO STRIP/ PARKING SOMMERVILLE/ UTILITIES OUTDOOR QUAD STUDENT STUDENT SERVICES BUILDING TELACU Construction Management
9
Lawndale High School
Student Services Building Student Services Building
Construction for the Phase 1 Student Services Building started in October 2012. The Building Building started in October 2012. The Building will be complete by June 2014 with the outdoor Quad area developed in the Summer 2014. Building will be ready for the 2014-15 school year. Administration, Library and Campus Security Administration, Library and Campus Security spaces including 42 teaching stations. TELACU Construction Management
10
Lawndale High School
Student Services Building Costco Strip/ Parking
Work on the ‘Costco’ strip is being expedited in order to provide the District with much needed added to provide the District with much needed added parking immediately. 75% of the new storm drain line is installed. Paving, Landscaping and fencing to be complete by March end TELACU Construction Management
11
Lawndale High School
Student Services Building Footing Excavation
At the last update, excavation and backfill the building pad was nearly completed. Trenching for building pad was nearly completed. Trenching for foundations began in January 2013 TELACU Construction Management
12
Lawndale High School
Student Services Building Rebar placement
Excavate for foundations began in January 2013 followed by rebar placement and concrete formwork, followed by rebar placement and concrete formwork, an immense amount of craftsmanship, labor, and coordination is required during this phase. TELACU Construction Management
13
Lawndale High School
Student Services Building Concrete placement Student Services Building Concrete placement
Concrete foundations are being poured in sections and every week in order to meet the mid -March steel erection start date. mid -March steel erection start date. TELACU Construction Management
14
Leuzinger High School Site Aerial
TELACU Construction Management
15
Leuzinger High School Phase II
2 Story Classroom & Dining Facility
Segment “A”: Surveying and Grading Excavation of grade beams footings Excavation of grade beams footings Concrete pour at grade beams Forming of Slab (Concrete pour 2/25/23) Storm drain, sewer, water, grease interceptor, and electrical conduit. Segment “B”: Surveying and Grading Excavation of grade beam footings Concrete pour at grade beams Forming of Slab Storm drain, sewer, water, grease Storm drain, sewer, water, grease interceptor, and electrical conduit/pull box’s Structural Steel HSS columns Segment “C”: Surveying and Grading Excavation of grade beam footings Excavation of grade beam footings Concrete pour at grade beams (forthcoming) Rat slabs poured at grade beam footings Storm drain, sewer, water, grease interceptor, and electrical conduit
TELACU Construction Management
16
Leuzinger High School Phase II
2 Story Classroom & Dining Facility
Abandoned 6" and 10" Exxon lines running East-West along lines running East-West along 145th Street, through site, were discovered to be in conflict with multiple project elements, such as:
Bridge column footing.
Electrical high voltage Storm drain laterals Removal of 6” & 10” Idle Exxon Mobile pipeline were removed late February at no cost to the District. TELACU Construction Management
17
Leuzinger High School Phase II
2 Story Classroom & Dining Facility 2 Story Classroom & Dining Facility
TELACU Construction Management