centinela valley union high centinela valley union high
play

Centinela Valley Union High Centinela Valley Union High School - PowerPoint PPT Presentation

Centinela Valley Union High Centinela Valley Union High School District Measure CV Program Update March 11, 2013 Site Construction Progress Site Updates Hawthorne High School Lawndale High School Leuzinger High School 2 TELACU


  1. Centinela Valley Union High Centinela Valley Union High School District Measure CV Program Update March 11, 2013

  2. Site Construction Progress Site Updates � Hawthorne High School � Lawndale High School � Leuzinger High School 2 TELACU Construction Management

  3. Hawthorne High School Site Aerial Aerial January 2013 Aerial January 2013 3 TELACU Construction Management

  4. Hawthorne High School Building A & B – Rendering of Counseling and Student Services & Media Center Building A Building B 4 TELACU Construction Management

  5. Hawthorne High School Building A - Counseling & Student Services February 2013 The Counseling & Student Services building is on schedule for a summer completion. Since our last update steel has been erected, underground utilities installed and the slab-on-grade our last update steel has been erected, underground utilities installed and the slab-on-grade has been placed. Steel stud framing and mechanical, electrical and plumbing rough-ins are proceeding. 5 TELACU Construction Management

  6. Hawthorne High School Building B - Media Center February 2013 The Media Center has the grade beam excavated and the footings concrete poured. Building B will start being erected after Building C. 6 TELACU Construction Management

  7. Hawthorne High School Building C - Sciences Building � 10 Biology Classrooms � 3 Chemistry Labs � 1 Physics Classroom � Workrooms � Workrooms Rendered view from the corner of El Segundo and Inglewood intersection Rendering of courtyard view 7 TELACU Construction Management

  8. Hawthorne High School Science Building February 2013 The Science Building has the grade beam excavated with the formwork in place The Science Building has the grade beam excavated with the formwork in place and the footings concrete poured. 8 TELACU Construction Management

  9. Lawndale High School Site Aerial COSTCO STRIP/ PARKING SOMMERVILLE/ UTILITIES OUTDOOR QUAD STUDENT STUDENT SERVICES BUILDING 9 TELACU Construction Management

  10. Lawndale High School Student Services Building Student Services Building Construction for the Phase 1 Student Services Building started in October 2012. The Building Building started in October 2012. The Building will be complete by June 2014 with the outdoor Quad area developed in the Summer 2014. Building will be ready for the 2014-15 school year. Administration, Library and Campus Security Administration, Library and Campus Security spaces including 42 teaching stations. 10 TELACU Construction Management

  11. Lawndale High School Student Services Building Costco Strip/ Parking Work on the ‘Costco’ strip is being expedited in order to provide the District with much needed added to provide the District with much needed added parking immediately. 75% of the new storm drain line is installed. Paving, Landscaping and fencing to be complete by March end 11 TELACU Construction Management

  12. Lawndale High School Student Services Building Footing Excavation At the last update, excavation and backfill the building pad was nearly completed. Trenching for building pad was nearly completed. Trenching for foundations began in January 2013 12 TELACU Construction Management

  13. Lawndale High School Student Services Building Rebar placement Excavate for foundations began in January 2013 followed by rebar placement and concrete formwork, followed by rebar placement and concrete formwork, an immense amount of craftsmanship, labor, and coordination is required during this phase. 13 TELACU Construction Management

  14. Lawndale High School Student Services Building Concrete placement Student Services Building Concrete placement Concrete foundations are being poured in sections and every week in order to meet the mid -March steel erection start date. mid -March steel erection start date. 14 TELACU Construction Management

  15. Leuzinger High School Site Aerial 15 TELACU Construction Management

  16. Leuzinger High School Phase II 2 Story Classroom & Dining Facility Segment “A”: � Surveying and Grading � Excavation of grade beams footings � Excavation of grade beams footings � Concrete pour at grade beams � Forming of Slab (Concrete pour 2/25/23) � Storm drain, sewer, water, grease interceptor, and electrical conduit. Segment “B”: � Surveying and Grading � Excavation of grade beam footings � Concrete pour at grade beams � Forming of Slab � Storm drain, sewer, water, grease � Storm drain, sewer, water, grease interceptor, and electrical conduit/pull box’s � Structural Steel HSS columns Segment “C”: � Surveying and Grading � Excavation of grade beam footings � Excavation of grade beam footings � Concrete pour at grade beams (forthcoming) � Rat slabs poured at grade beam footings � Storm drain, sewer, water, grease interceptor, and electrical conduit 16 TELACU Construction Management

  17. Leuzinger High School Phase II 2 Story Classroom & Dining Facility Abandoned 6" and 10" Exxon lines running East-West along lines running East-West along 145th Street, through site, were discovered to be in conflict with multiple project elements, such as: � Bridge column footing. � Electrical high voltage � Storm drain laterals Removal of 6” & 10” Idle Exxon Mobile pipeline were removed late February at no cost to the District. 17 TELACU Construction Management

  18. Leuzinger High School Phase II 2 Story Classroom & Dining Facility 2 Story Classroom & Dining Facility 18 TELACU Construction Management

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend