Centinela Valley Union High Centinela Valley Union High School - - PowerPoint PPT Presentation

centinela valley union high centinela valley union high
SMART_READER_LITE
LIVE PREVIEW

Centinela Valley Union High Centinela Valley Union High School - - PowerPoint PPT Presentation

Centinela Valley Union High Centinela Valley Union High School District Measure CV Program Update March 11, 2013 Site Construction Progress Site Updates Hawthorne High School Lawndale High School Leuzinger High School 2 TELACU


slide-1
SLIDE 1

Centinela Valley Union High Centinela Valley Union High School District

Measure CV Program Update March 11, 2013

slide-2
SLIDE 2

Site Construction Progress Site Updates

Hawthorne High School Lawndale High School Leuzinger High School

TELACU Construction Management

2

slide-3
SLIDE 3

Hawthorne High School Site Aerial

Aerial January 2013

TELACU Construction Management

Aerial January 2013

3

slide-4
SLIDE 4

Hawthorne High School

Building A & B – Rendering of Counseling and Student Services & Media Center

Building A Building B TELACU Construction Management

4

slide-5
SLIDE 5

Hawthorne High School

Building A - Counseling & Student Services

The Counseling & Student Services building is on schedule for a summer completion. Since

  • ur last update steel has been erected, underground utilities installed and the slab-on-grade

February 2013

TELACU Construction Management

  • ur last update steel has been erected, underground utilities installed and the slab-on-grade

has been placed. Steel stud framing and mechanical, electrical and plumbing rough-ins are proceeding.

5

slide-6
SLIDE 6

Hawthorne High School

Building B - Media Center

February 2013

TELACU Construction Management The Media Center has the grade beam excavated and the footings concrete

  • poured. Building B will start being erected after Building C.

6

slide-7
SLIDE 7

Hawthorne High School

Building C - Sciences Building

10 Biology Classrooms 3 Chemistry Labs 1 Physics Classroom Workrooms

Rendered view from the corner of El Segundo and Inglewood intersection

Workrooms TELACU Construction Management

Rendering of courtyard view

7

slide-8
SLIDE 8

Hawthorne High School

Science Building

The Science Building has the grade beam excavated with the formwork in place

February 2013

TELACU Construction Management The Science Building has the grade beam excavated with the formwork in place and the footings concrete poured.

8

slide-9
SLIDE 9

Lawndale High School Site Aerial

COSTCO STRIP/ PARKING SOMMERVILLE/ UTILITIES OUTDOOR QUAD STUDENT STUDENT SERVICES BUILDING TELACU Construction Management

9

slide-10
SLIDE 10

Lawndale High School

Student Services Building Student Services Building

Construction for the Phase 1 Student Services Building started in October 2012. The Building Building started in October 2012. The Building will be complete by June 2014 with the outdoor Quad area developed in the Summer 2014. Building will be ready for the 2014-15 school year. Administration, Library and Campus Security Administration, Library and Campus Security spaces including 42 teaching stations. TELACU Construction Management

10

slide-11
SLIDE 11

Lawndale High School

Student Services Building Costco Strip/ Parking

Work on the ‘Costco’ strip is being expedited in order to provide the District with much needed added to provide the District with much needed added parking immediately. 75% of the new storm drain line is installed. Paving, Landscaping and fencing to be complete by March end TELACU Construction Management

11

slide-12
SLIDE 12

Lawndale High School

Student Services Building Footing Excavation

At the last update, excavation and backfill the building pad was nearly completed. Trenching for building pad was nearly completed. Trenching for foundations began in January 2013 TELACU Construction Management

12

slide-13
SLIDE 13

Lawndale High School

Student Services Building Rebar placement

Excavate for foundations began in January 2013 followed by rebar placement and concrete formwork, followed by rebar placement and concrete formwork, an immense amount of craftsmanship, labor, and coordination is required during this phase. TELACU Construction Management

13

slide-14
SLIDE 14

Lawndale High School

Student Services Building Concrete placement Student Services Building Concrete placement

Concrete foundations are being poured in sections and every week in order to meet the mid -March steel erection start date. mid -March steel erection start date. TELACU Construction Management

14

slide-15
SLIDE 15

Leuzinger High School Site Aerial

TELACU Construction Management

15

slide-16
SLIDE 16

Leuzinger High School Phase II

2 Story Classroom & Dining Facility

Segment “A”: Surveying and Grading Excavation of grade beams footings Excavation of grade beams footings Concrete pour at grade beams Forming of Slab (Concrete pour 2/25/23) Storm drain, sewer, water, grease interceptor, and electrical conduit. Segment “B”: Surveying and Grading Excavation of grade beam footings Concrete pour at grade beams Forming of Slab Storm drain, sewer, water, grease Storm drain, sewer, water, grease interceptor, and electrical conduit/pull box’s Structural Steel HSS columns Segment “C”: Surveying and Grading Excavation of grade beam footings Excavation of grade beam footings Concrete pour at grade beams (forthcoming) Rat slabs poured at grade beam footings Storm drain, sewer, water, grease interceptor, and electrical conduit

TELACU Construction Management

16

slide-17
SLIDE 17

Leuzinger High School Phase II

2 Story Classroom & Dining Facility

Abandoned 6" and 10" Exxon lines running East-West along lines running East-West along 145th Street, through site, were discovered to be in conflict with multiple project elements, such as:

Bridge column footing.

Electrical high voltage Storm drain laterals Removal of 6” & 10” Idle Exxon Mobile pipeline were removed late February at no cost to the District. TELACU Construction Management

17

slide-18
SLIDE 18

Leuzinger High School Phase II

2 Story Classroom & Dining Facility 2 Story Classroom & Dining Facility

TELACU Construction Management

18