Carl Dominguez Director Department of Public Works Paving the Way - - PowerPoint PPT Presentation

carl dominguez
SMART_READER_LITE
LIVE PREVIEW

Carl Dominguez Director Department of Public Works Paving the Way - - PowerPoint PPT Presentation

Carl Dominguez Director Department of Public Works Paving the Way for Economic Opportunities and Investment Paving the Way for Economic Opportunities and Investment The Department of Public Works understands the importance of sound


slide-1
SLIDE 1

Carl Dominguez

Director Department of Public Works

slide-2
SLIDE 2
slide-3
SLIDE 3

Paving the Way for Economic Opportunities and Investment

slide-4
SLIDE 4

Paving the Way for Economic Opportunities and Investment

  • The Department of Public Works understands

the importance of sound infrastructure to Guam’s future

– Public sector investments build private sector investor confidence – Mobility is crucial to economic growth potential

  • Efficient delivery of goods and services
  • Safe and efficient access for workers customers
slide-5
SLIDE 5

Paving the Way for Economic Opportunities and Investment

  • Department of Public Works has launched a

massive effort to improve Guam’s existing public roadways

– Rehabilitation – Resurfacing – Reconstruction

  • Effort has been carefully programmed and has been

driven by the 2030 Guam Transportation Plan

slide-6
SLIDE 6

2030 Guam Transportation Plan

  • The 2030 Guam Transportation Plan represents the

largest public investment in roadway improvements in Guam’s history

  • Outlines Guam’s road improvement needs over the

next 20 years

– Based on organic growth – Includes projected needs to meet military buildup requirements – Fosters mobility, safety and economic expansion

slide-7
SLIDE 7

2030 Guam Transportation Plan

  • Plan was developed in partnership between the

Federal Highway Administration (FHWA), DoD and the Guam Department of Public Works

  • Current improvement program covers approx. 186

miles of routed primary roads and bridges throughout the island

  • Identifies and prioritizes projects and funding

requirements

slide-8
SLIDE 8

2030 Guam Transportation Plan

  • Improved inspection standards
  • Higher accountability of Contractors &

Construction Management Firms

  • Continual Audits of Projects
  • On–Going Training for consistency

– Workforce Safety Training Program

  • Over 100 representatives from contractors
  • Mayors, Law Enforcement Agencies & Utilities
  • Focus on MUTCD Standards and Enforcement
slide-9
SLIDE 9

2030 Guam Transportation Plan

  • Plan includes a compendium of supportive

initiatives:

– Rights of Way Manual – Village Streets Master Plan – Storm Water Master Plan – Asset Management Information System – Guam Transportation Training Initiative – Bridge Inspection and Rating Program – Environmental Procedures Guide

slide-10
SLIDE 10
slide-11
SLIDE 11

1

ONGOING PROJECTS

September 2014

Route 1/8 Intersection Improvements and Agana Bridge Replacement (Design Build) Project Start: September 2011 Completion: April 2015 Scope: Road improvements and Bridges Replacement Cost: $16.4M Contractor: Core Tech International

  • Est. Progress: 80%

Route 4, Agfayan Bridge Replacement Project Start: August 2013 Completion: December 2014 Scope: Bridge Replacement Cost: $4.6M Contractor: Black Construction Corporation

  • Est. Progress: 40%

Asan & Aguada Bridges Rehabilitation Project Start: January 2014 Completion: November 2014 Scope: Rehabilitation for two bridges Cost: $1.1M Contractor: Maeda Pacific Corporation

  • Est. Progress: 30%

Route 4, Togcha to Ipan Beach Park Project Start: February 2014 Completion: July 2014 Scope: Roadway and Safety Improvements Cost: $700,000 Contractor: Nippo Corporation

  • Est. Progress: 90%

1 3

2 Route 17 Rehabilitation and Widening, Phase 2A Project Start: March 2014 Completion: March 2015 Scope: Drainage Improvements and Spot Repair Cost: $2.5M Contractor: Nippo Corporation

  • Est. Progress: 25%

Route 20, Maga Haga Highway, Phase 1 Project Start: April 2014 Completion: March 2015 Scope: New Arterial Parkway Cost: $7.3M Contractor: IMCO General Construction

  • Est. Progress: 40%

Route 25/26 Intersection Improvement Project Start: June 2014 Completion: February 2015 Scope: Intersection Improvement Cost: $2.5M Contractor: Korando Corporation

  • Est. Progress: 40%

Inarajan North Leg (As Misa) Project Start: May 2014 Completion: May 2015 Scope: Bridge Rehabilitation Cost: $1.2 Million Contractor: IMCO General Construction

  • Est. Progress: 40%

Bile/Pigua Bridge Replacements Project Start: July 2014 Completion: October 2015 Scope: Replace Two Bridges Cost: $3.7 M Contractor: Korando Corporation

  • Est. Progress: 15%

Replacement of Welded Petroleum Distribution Piping and Appurtenances Project Start: May 2014 Completion: November 2015 Scope: Pipe replacement Cost: $1.5 M Contractor: Rex International

  • Est. Progress: 0%

3 2 5 4 6 5 7 8 6 7 9 8 9 4 10 10

CONSTRUCTION VALUE AT $42M

slide-12
SLIDE 12
slide-13
SLIDE 13

Roadway Improvement Value Summary

Category Construction Value Completed Projects $118 Million Projects Under Construction $42 Million Projects in Planning or Design $141 Million Total Construction Value $301 Million

slide-14
SLIDE 14

Paving the Way for Economic Opportunities and Investment

  • DPW stands ready to assist in creating new

economic opportunities for our island:

– Construction companies, planning and design firms and construction management firms

  • We are prepared to provide potential

investors/developers/builders with assistance:

– Building permitting, inspections and development process guidance

slide-15
SLIDE 15

For More Information visit:

Guam Transportation Program website at: www.guamtransportationprogram.com

  • r

Department of Public Works website at: www.dpw.guam.gov

slide-16
SLIDE 16

Paving the Way for Economic Opportunities and Investment