Achieving Affordable Programs NRO Cost and Acquisition Assessment Group (CAAG) Support of Cost Driver Identification For ICEAA June 2014 Pat Kielb, Jay Miller, Eileen Devillier, Linda Williams (U) Overview CAAG, Who we are. Cost


  1. Achieving Affordable Programs NRO Cost and Acquisition Assessment Group (CAAG) Support of Cost Driver Identification For ICEAA June 2014 Pat Kielb, Jay Miller, Eileen Devillier, Linda Williams

  2. (U) Overview • CAAG, Who we are…. • Cost Driver Study: Dec 12 • Optimization: On-going CAAG

  3. Cost and Acquisition Assessment Group • Critical Roles: • Acquisition Planning - “How best to accomplish the acquisition?” • Independent Cost Estimates (ICEs) / Agency Cost Positions (ACPs) - “How much will it cost?” • EVM Center of Excellence - “Is the baseline executable and measurable?” • Key Responsibilities: • Provide Independent Cost and Schedule Analyses for program planning, budget, acquisition decisions and design reviews • Support NRO Budget Build – IPBS and Congressional Budget Justification Book (CBJB) • Corporate level Earned Value Management (EVM) – Compliance and surveillance reviews, Integrated Baseline Reviews, program assessments, and Central Repository • Maintain external interfaces with ODNI, DoD and OMB for Major System Acquisitions and Acquisition Policy • Administer Joint Intelligence Acquisition Board (JIAB)/NRO Acquisition Board (NAB); conduct Acquisition Strategy Panels (ASPs) and Quarterly Program Reviews (QPRs) CAAG 3

  4. (U) Enhanced Program Support: More Universal Access and Use of CAAG data, tools, … T he NRO CAAG is uniquely positioned to provide cross-program insight and analysis : • Supports operating as a single integrated entity optimized for Enterprise not individual-level performance • Places renewed emphasis on Enterprise-Level planning and cross-INT integration CAAG Perspective & Value Proposition GED IMINT SIGINT COMM EV Historic Lessons Costs Learned EV Central Program Repository Artifacts CAAG Teammates CAAG Infrastructure  Constantly evolving centralized repositories for  Extensive Knowledge of NRO Corporate History all Cost, Schedule, and Program Artifacts  Unparalleled breadth of Enterprise decisions and consequences across programs over time  Maturing cross-program understanding of lessons learned  Deep Quantitative Skill Set and Knowledge Base IMINT Portfolio COMM Portfolio SIGINT Portfolio GED Portfolio 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Program Milestone Review Program Milestone Review Program Milestone Review Program Milestone Review ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR Performance and Baseline Performance and Baseline Performance and Baseline Performance and Baseline Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Assessment Updates Assessment Updates Assessment Updates Assessment Updates 0 0 0 0 CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Program Milestone Review Program Milestone Review Program Milestone Review Program Milestone Review ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR Performance and Baseline Performance and Baseline Performance and Baseline Performance and Baseline Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Assessment Updates Assessment Updates Assessment Updates Assessment Updates 0 0 0 0 CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Program Milestone Review Program Milestone Review Program Milestone Review Program Milestone Review ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR Performance and Baseline Performance and Baseline Performance and Baseline Performance and Baseline Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Assessment Updates Assessment Updates Assessment Updates Assessment Updates 0 0 0 0 CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 1 2 3 4 5 6 7 Program Milestone Review Program Milestone Review Program Milestone Review Program Milestone Review ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR ICE Budget Source Contract IBR Performance and Baseline Performance and Baseline Performance and Baseline Performance and Baseline Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Development Established Selection Negotiation Conducted Assessment Updates Assessment Updates Assessment Updates Assessment Updates 0 0 0 0 CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAIG Core Infrastructure: People, Processes, Tools, Technology, Data CAAG

  5. (U) Cost: Overview Tracking Our Performance Large / Diverse Database • 13% average underestimate, • 95 government satellites • Track record over 19 years • 75 commercial programs • Continuous improvement • 15 ground programs Key Corporate Initiatives (U) Little use of the “Black - Box” • Standard Reporting SWBS • Custom models • Budget Flexibility - GEAC CAAG Analysts – Not • Detailed analogies • Technical review your typical “Bean Counters” Significant Outreach Integrated Cost & Acquisition Models • Cost IPT 3 times per year • Programmatics Technical Staff • Share models, data • Commercial-like acquisition • Engineers • Industry & Gov’t . • Time phasing and schedules • Physicists • Mathematicians S//TK//NF CAAG 5

  6. Cost Driver Study GOAL : Reduce enterprise costs to posture for potential budget reductions or re- invest into enhancing mission capability CAAG Task: • Identify cost drivers and reasons for cost growth: • Inform Budget Austerity • Identify Unexamined Cost Drivers • Provide Framework for Additional Opportunities Approach: • Assess Cost Drivers and Areas of Cost Growth: • Review of Internal/external cost studies • Perform Data Driven Assessments • Assess NRO processes related to cost control • Budget Analysis: Characterize how the NRO spends it’s money (Trending) • Recommend opportunities to achieve future efficiencies CAAG

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.