Bush River 115kV Crossing Rebuild
Tiffany Matthe thews-La Lay & Kevin n Elvet eton
- n
Projec ject Managem gemen ent
Bush River 115kV Crossing Rebuild Tiffany Matthe thews-La Lay - - PowerPoint PPT Presentation
Bush River 115kV Crossing Rebuild Tiffany Matthe thews-La Lay & Kevin n Elvet eton on Projec ject Managem gemen ent Agenda Team Introduction Project Overview Project Necessity Route Determination Existing Line
Projec ject Managem gemen ent
2
Agenda
Bush River Crossing
3
Project Team
Bush River Crossing
4
Proposed Bush River Project
and foundations
Bush River Crossing
5
Necessity
1951 and has experienced substantial reliability and risk problems
inspection in 1991
6
Structural Reliability and Safety
inspected and severe degradation was discovered
new steel and grout
inspection of the steel piles
year life span for the repairs – currently in year 29
7
Boat Safety
contacts
from its mooring and contacted the lines, causing an outage and the total loss of the vessel (no one was on board)
drifted into the lines
8
Avian Challenges
all 9 occurred within the Bush River Crossing
debris
discovery of a LARGE colony of cormorants
insulators, conductors, tower steel, and foundations
no totally effective ways to keep the cormorants from inhabiting the tower
9
Avian Challenges (cont.)
was also found on tower 56 (Perryman side)
shields” were installed, but due to the liquid state of the contaminant and the steady wind, the shields were not entirely effective
accessing a severely “contaminated” tower, maneuvering around mildly aggressive birds, and maintaining insulators and conductors that will continue to become contaminated
10
Route Determination
11
Existing Edgewood to Perryman Transmission Lines
crossing
(horizontally-configured) lattice towers
River
12
Proposed Solution
Removal
towers (one on each shore and
frames (two on each side of the river)
total)
N
Install
bank,
Bush River on pile foundation
existing line to minimize outage impacts
vessel height)
13
Proposed Solution – Each Bank
Install
bank
nesting on structures Removal
towers (one on each shore and
frames (two on each side of the river)
total)
14
Renderings
15
Renderings
16
Proposed Solution
17
Environmental Mitigation
Department of Environment and Department of Natural Resources and will address:
activities
18
Project Schedule
Second Quarter, 2021
Third Quarter, 2021
Fourth Quarter, 2021
April 2022 - May 2022
September 2022 - November 2022
19
Project Summary
20
Questions
Questions from the Public Open Discussion