welcome need for proposed improvement
play

Welcome Need for Proposed Improvement Additional River Crossing - PowerPoint PPT Presentation

Caton Farm Bruce Road Phase I Engineering Study Welcome Need for Proposed Improvement Additional River Crossing Des Plaines River is barrier to east-west circulation. IL Route 7 bridge is only crossing for 7 miles. Need


  1. Caton Farm – Bruce Road Phase I Engineering Study Welcome

  2. Need for Proposed Improvement � Additional River Crossing • Des Plaines River is barrier to east-west circulation. • IL Route 7 bridge is only crossing for 7 miles. • Need for additional crossing has been well documented by previous studies.

  3. Need for Proposed Improvement � East-west arterial to enhance regional mobility. � Protect local streets from cut-through arterial traffic.

  4. Study Process � Federal funding. � State & federal regulations. � NEPA/404 Merger Process.

  5. Study Process � Three phase process: • Preliminary Engineering (Phase I) • Design Engineering (Phase II) • Construction (Phase III)

  6. Phase I – Preliminary Engineering � Phase I involves: • Identifying Project Needs. • Developing Alternatives. • Regulatory Agency Coordination. • Environmental Documentation. • Obtaining Public Input. • Selecting Preferred Alternative.

  7. Purpose of Today’s Meeting � To present improvement alternatives and impacts. � To obtain public input.

  8. Project Purpose � Satisfy year 2030 projected travel demand within a regional corridor between Caton Farm Road at U.S. Route 30 and IL Route 7 at Cedar Road. � Address capacity, operational, and safety deficiencies.

  9. Project Needs � Accommodate Population and Employment Growth. � Improve Roadway Network with new Des Plaines River Bridge. � Accommodate Projected Transportation demand. � Optimize intermodal relationships. � Increase travel safety.

  10. River Crossing Alternatives � 8 Historic River Crossings: • 135th Street • 143 rd Street – Taylor Road • 151 st Street – Airport Road • Thornton Street – Renwick Road • IL Route 7 • Stateville Road – Division Street • Caton Farm Road – Bruce Road • Theodore Street – Rosalind Street

  11. Historic River Historic River Crossing Crossing 135 th Street Locations Locations 143 rd Street 151 st Street Renwick Road Thornton Street IL Route 7 Division Street Bruce Road Caton Farm Oak Avenue Theodore Street Rosalind Street

  12. Non-Feasible Non-Feasible River Crossing River Crossing 135 th Street Locations Locations 143 rd Street 151 st Street Airport Road Division Street

  13. Alternatives � Potential for a large number of alternatives. � A representative number covering a full range.

  14. Alternatives Renwick Road Gougar Road Wolf Road Cedar Road IL Route 7 Bruce Road Caton Farm Road Oak Avenue Theodore Street U.S. Route 6

  15. Alternatives � Each alternative generally consists of: • 2 through lanes in each direction. • Median for left turn lanes. • Intersection Improvements. • 150-foot R.O.W. desirable. • Potential for sidewalk & bikepath.

  16. Initial Screening of Alternatives � An alternative was eliminated if it did not satisfy the Purpose & Need.

  17. Initial Screening Alternatives to Be Dropped Existing IL Route 7 Theodore - Rosalind - Wolf

  18. 2 nd Level Screening of Alternatives � 11 alternatives were evaluated for impacts to: • Floodplains • Wetlands • Section 4(f) Land • Historic Structures/Properties • Special Waste Sites • Environmental Justice • Threatened & Endangered Species • Displacements • Right-of-Way Acquisition

  19. Evaluation of Alternatives � Same level of benefits. � Alternatives with greater impacts to the environment were discarded.

  20. Alternatives Dropped � Theodore - Rosalind - Gougar � Caton Farm - Weber - Renwick - Thornton � Caton Farm - Oak - Cedar � Caton Farm - Oak - Bruce - Cedar � Caton Farm - Bruce - Cedar

  21. Alternatives Carried Forward Gougar Road Middle Bruce Road Caton Farm Road Oak Avenue

  22. Alternatives Carried Forward � Details are presented in the adjacent room. � Public input is critical to selecting a Preferred Alternative.

  23. The next steps… � 14-day comment period. � Selection of Preferred Improvement Plan.

  24. Who Decides? � Will County - based upon Public and Local Community input.

  25. Schedule � More detailed studies. � Preliminary Engineering 2008 � Design Engineering � Construction Post 2010

  26. Closing Remarks Thank You

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.