BROOKLINE HIGH SCHOOL EXPANSION TRANSPORTATION BOARD MEETING October 2, 2019 BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 1 TRANSPORTATION BOARD MEETING AGENDA BHS Expansion Project


slide-1
SLIDE 1

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 1 OCTOBER 2, 2019

TRANSPORTATION BOARD MEETING October 2, 2019

BROOKLINE HIGH SCHOOL EXPANSION

slide-2
SLIDE 2

TRANSPORTATION BOARD MEETING AGENDA BHS Expansion Project Streetscape Improvements

  • Pedestrian
  • Bicycle
  • Vehicular / Parking

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 2 OCTOBER 2, 2019

slide-3
SLIDE 3

BROOKLINE HIGH SCHOOL CAMPUS

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 3 OCTOBER 2, 2019

slide-4
SLIDE 4

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 4 OCTOBER 2, 2019

CAMPUS PLAN

STEM WING CYPRESS BUILDING TAPPAN / KIRRANE UAB BHS

slide-5
SLIDE 5

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 5 OCTOBER 2, 2019

PEDESTRIAN IMPROVEMENTS

KEY IMPROVEMENTS

  • 1. WIDEN TAPPAN STREET SIDEWALK

A major pedestrian sidewalk links the new Cypress Building with the main high school building.

  • 2. RAISE CROSSWALKS ALONG TAPPAN STREET

Raised crosswalks calm traffjc and provide safer crossings at the UAB build- ing and new Cypress Building.

  • 3. DIRECT CONNECTION TO THE MBTA STATION

A direct pedestrian path links Davis Street to the Brookline Hills T statjon.

  • 4. SEATING AND GATHERING ALONG TAPPAN

New seatjng areas at STEM, Tappan/Kirrane, UAB, and the MBTA plaza welcome pedestrians and provide gathering and waitjng areas for stu- dents, stafg, and the community.

  • 5. CURB BULB OUTS ALONG TAPPAN STREET

New curb bulb outs slow traffjc and defjne drop-ofg areas increasing pedes- trian safety.

slide-6
SLIDE 6

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 6

EXISTING CONDITION: AN INCONSISTENT & UNWELCOMING EXPERIENCE

1/64” = 1’-0”

  • Width of sidewalk is inconsistent along Tappan Street
  • Current sidewalk width (6’ wide generally) will not be suffjcient for traffjc fmow to & from new Cypress Building

EXISTING RAISED CROSSING EXISTING CROSSING WIDTH OF SIDEWALK IS INCONSISTENT ALONG TAPPAN STREET SHORTAGE OF BIKE RACKS ON CAMPUS 4’ WALL IN FRONT OF TAPPAN GYM WITH NO GUARDRAIL: NOT TO CODE TRAFFIC WORSENED BY DISORDERLY DROP-OFF AT PEAK HOURS 6’ 7’ 5.5’ 14’ 53 SCHOOL PARKING SPACES 32 SCHOOL SPACES 8 MBTA PARKING SPACES

UAB KIRRANE POOL TAPPAN GYM

slide-7
SLIDE 7

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 7

CREATE A UNIFIED CAMPUS: A TRANSFORMED TAPPAN STREETSCAPE

RAISED CROSSING NEW DESIGNATED DROP-OFF AREA 17 BIKE RACKS + 15 BLUE BIKE SPACES NEW MBTA / CYPRESS BUILDING ENTRY PLAZA WIDENED CROSSWALK TO FACILITATE SAFER STUDENT CROSSING & MBTA ACCESS 2’ SEAT WALL & HANGOUT SPACE IN FRONT OF TAPPAN GYM 2’ SEAT WALL IN FRONT OF NEW CYPRESS BUILDING 11’ 11’ 11’

  • The sidewalk has been increased from 6’ to 11’ wide contjnuously, with an additjonal 4’ of plantjng and seatjng zone
  • New trees along Tappan Street create contjnuity with Greenough facades
  • Benches along Greenough Street popular with students; concept brought to Tappan Street

42 PARKING SPACES 6 SCHOOL SPACES 10 SCHOOL SPACES 8 MBTA SPACES BIKE LANE & “BOX” @ INTERSECTION OF TAPPAN STREET AND CYPRESS STREET NEW CYPRESS BUILDING UNIFIED ARTS BUILDING KIRRANE POOL TAPPAN GYMNASIUM TAPPAN STREET PARKLET SEATING AREA WIDENED SIDEWALK AT CORNER OF TAPPAN AND CYPRESS

slide-8
SLIDE 8

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 8

TAPPAN STREET SECTION AT KIRRANE POOL

1/16” = 1’-0”

EXISTING CONDITION PROPOSED CONDITION

4’ 11’

slide-9
SLIDE 9

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 9

TAPPAN STREET SECTION AT UNIFIED ARTS BUILDING

1/16” = 1’-0”

EXISTING CONDITION PROPOSED CONDITION

4’

slide-10
SLIDE 10

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 10 OCTOBER 2, 2019

CYPRESS STREET SITE PLAN

CYPRESS BUILDING UNIFIED ARTS BUILDING

TAPPAN STREET BRINGTON ROAD

slide-11
SLIDE 11

MBTA / CYPRESS BUILDING ENTRY PLAZA

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 11 OCTOBER 2, 2019

slide-12
SLIDE 12

TEMPORARY FARE COLLECTION HUT

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 12 OCTOBER 2, 2019

slide-13
SLIDE 13

MBTA / CYPRESS BUILDING PLAZA EXISTING CONDITION

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 13 OCTOBER 2, 2019

slide-14
SLIDE 14

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 14 OCTOBER 2, 2019

MBTA / CYPRESS BUILDING PLAZA DESIGN UPDATE

VIEW FROM TAPPAN ST CROSSWALK

slide-15
SLIDE 15

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 15 OCTOBER 2, 2019

MBTA / CYPRESS BUILDING PLAZA DESIGN UPDATE

AERIAL VIEW

slide-16
SLIDE 16

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 16 OCTOBER 2, 2019

MBTA / CYPRESS BUILDING PLAZA DESIGN UPDATE

VIEW FROM BASE OF THE GRAND STAIRCASE

slide-17
SLIDE 17

MBTA PLATFORM IMPROVEMENTS SUMMARY

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 17 OCTOBER 2, 2019

INBOUND PLATFORM WEATHER PROTECTION SF: BENCHES: OUTBOUND PLATFORM WEATHER PROTECTION: BENCHES:

BIKE RACKS 8 BIKES 32 BIKES

*1,225 riders / weekday (2014 MBTA Ridership and Service Statjstjcs - 14th Editjon)

EXISTING CURRENT DESIGN 1,155 sq fu 30 lin fu 1,300 sq fu 25 lin fu 100 sq fu 18 lin fu 180 sq fu 22 lin fu

slide-18
SLIDE 18

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 18 OCTOBER 2, 2019

BRINGTON PATH - MBTA PLATFORM EGRESS

CYPRESS BUILDING GARDEN LEVEL

KEY IMPROVEMENTS

  • 1. STRAIGHTER ROUTE

The accessible pathway has been straightened.

  • 2. LANDSCAPE BUFFER

A landscape bufger provides more privacy for the neighbors to the west.

  • 3. CURB BULB OUT MAINTAINED

Existjng traffjc calming curb profjle relocated on Brington Rd.

  • 4. ANGLED PARKING

Three deeded parking spaces have been angled for easier access.

  • 5. LOW LIGHT LEVELS

The lightjng design meets code required light levels and pro- vides a safe pedestrian environment at night. Lights are aimed away from the adjacent residence.

slide-19
SLIDE 19

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 19 OCTOBER 2, 2019

BRINGTON PATH / MBTA PLATFORM EGRESS - LIGHTING

slide-20
SLIDE 20

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 20 OCTOBER 2, 2019

TAPPAN AND GREENOUGH STREET INTERSECTION STEM WING

5 ACCESSIBLE PARKING SPACES PARKING SPACE REMOVED CURB BULB OUT DEFINES DROP OFF ZONE

1 2 3 4 5

slide-21
SLIDE 21

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 21 OCTOBER 2, 2019

CYCLING IMPROVEMENTS

slide-22
SLIDE 22

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 22 OCTOBER 2, 2019

CYCLING IMPROVEMENTS

KEY IMPROVEMENTS

  • 1. COMPLETE GREEN ROUTES AT BROOKLINE HIGH

Bike lanes on Davis, Greenough, and Tappan link Brookline’s Green Routes around the Cypress Field

  • 2. IMPROVE BIKE SAFETY ON BHS ROADWAYS FOR THE

COMMUNITY

Bike lanes on Davis St, Greenough Street, and Tappan Street improve bicy- cle safety.

  • 3. INCREASE BIKE PARKING CAPACITY BY 67%

89 bike parking spaces have been added to the BHS campus. Cypress Field

slide-23
SLIDE 23

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 23 OCTOBER 2, 2019

CYCLING IMPROVEMENTS

GREEN ROUTES - CURRENT PROPOSED

C Y P R E S S F I E L D CYPRESS FIELD

CONTRAFLOW SHARROWS LANE FUTURE BLUE BIKES BB BB BB

slide-24
SLIDE 24

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 24 OCTOBER 2, 2019

CYCLING IMPROVEMENTS: BIKE LANES

STEM WING CYPRESS BUILDING TAPPAN / KIRRANE UAB

1 2 4 3

slide-25
SLIDE 25

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 25 OCTOBER 2, 2019

  • 1. DAVIS STREET BIKE LANE - TEST FIT

CYPRESS FIELD RESIDENCES

SIDEWALK SIDEWALK BIKE LANE BUFFER VEHICULAR TRAVEL PARKING

slide-26
SLIDE 26

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 26 OCTOBER 2, 2019

  • 2. GREENOUGH STREET CONTRA FLOW BIKE LANE - TEST FIT

GREENOUGH STREET

CYPRESS FIELD HIGH SCHOOL

SIDEWALK SIDEWALK BIKE LANE BUFFER VEHICULAR TRAVEL PARKING

slide-27
SLIDE 27

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 27 OCTOBER 2, 2019

  • 3. TAPPAN STREET BIKE LANE - TEST FIT

TAPPAN STREET

CYPRESS FIELD TAPPAN / UAB

SIDEWALK BUFFER DROP OFF ZONE SIDEWALK VEHICULAR AND BICYCLE TRAVEL (SHARROWS) PARKING

slide-28
SLIDE 28

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 28 OCTOBER 2, 2019

  • 4. TAPPAN STREET / CYPRESS STREET INTERSECTION
slide-29
SLIDE 29

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 29 OCTOBER 2, 2019

EXISTING BIKE PARKING AT BHS / MBTA PLAZA / CYPRESS FIELD

B

BHS KIRRANE UAB

A B C D A C

TAPPAN STREET DAVIS STREET CYPRESS STREET WELLAND ROAD

CYPRESS FIELD TAPPAN 23 BIKES 22 BIKES* 9 BIKES 42 BIKES 21 BIKES 18 BIKES TOTAL BIKE PARKING SPACES:

135**

D E E

*15 BLUE BIKES IN ADDITION TO 22 BIKES IN FRONT OF KIRRANE POOL ** 41% OF BIKE PARKING CAPACITY OBSERVED AT 8:30 AM ON SEPTEMBER 10, 2019 (Locatjon F is ofg-line due to constructjon) 85% OF BIKE PARKING CAPACITY OBSERVED AT 12PM ON SEPTEMBER 18, 2019 (Locatjon F is ofg-line due to constructjon)

F F

slide-30
SLIDE 30

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 30 OCTOBER 2, 2019

B

STEM WING CYPRESS BUILDING TAPPAN / KIRRANE UAB

A D

CYPRESS STREET

23 BIKES 72 BIKES 32 BIKES* 42 BIKES 21 BIKES 18 BIKES 10 BIKES 6 BIKES TOTAL BIKE PARKING SPACES:

224

E

*32 BIKE PARKING SPACES + 15 BLUE BIKES

F B D E F A C C H H G G G

YELLOW + RED SYMBOL INDICATES NEW BIKE PARKING

EXISTING BIKE PARKING AT BHS / MBTA PLAZA / CYPRESS FIELD

slide-31
SLIDE 31

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 31 OCTOBER 2, 2019

BROOKLINE HIGH SCHOOL PARKING

slide-32
SLIDE 32

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 32 OCTOBER 2, 2019

VEHICULAR PARKING AT BHS PRIOR TO CONSTRUCTION

B

BHS KIRRANE UAB

A B C D A C

TAPPAN STREET DAVIS STREET CYPRESS STREET WELLAND ROAD

CYPRESS FIELD TAPPAN 54 CARS 32 CARS* 19 CARS 10 CARS TOTAL PARKING SPACES:

115

D

*8 MBTA PARKING SPACES NOT INCLUDED

slide-33
SLIDE 33

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 33 OCTOBER 2, 2019

STEM WING CYPRESS BUILDING TAPPAN / KIRRANE UAB

PROPOSED VEHICULAR PARKING AT BROOKLINE HIGH SCHOOL

E E A B C A B C D

42 CARS 16 CARS* 19 CARS PARKING LOT REMOVED 2 CARS

*8 MBTA PARKING SPACES NOT INCLUDED

TOTAL PARKING SPACES:

79

slide-34
SLIDE 34

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 34

FUTURE SCHOOL YEAR STAFF AT MAXIMUM CAPACITY

FULL AND PART TIME STAFF: 425* ON CAMPUS PARKING SPACES: 79* NEIGHBORHOOD PARKING SPACES: 160 TOTAL PARKING SPACES: 239 *45 additjonal stafg *36 parking spaces removed

PARKING AUDIT

Based on current data provided by BHS on September 18, 2019:

2018 / 2019 SCHOOL YEAR

FULL AND PART TIME STAFF: 380 ON CAMPUS PARKING SPACES: 115 NEIGHBORHOOD PARKING SPACES: 160 TOTAL PARKING SPACES: 275

BEFORE CONSTRUCTION AFTER CONSTRUCTION

slide-35
SLIDE 35

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. OCTOBER 2, 2019 PAGE 35

PARKING AUDIT STAFF INCREASE

INCREASE IN BHS STAFF: 45 % STAFF REQUIRING PARKING (87%): 40 TDM REDUCTION (-10%): 4 PARKING SPACES NEEDED DUE TO STAFF INCREASE 36

LOSS OF PARKING SPACES

EXISTING # OF PARKING SPACES 115 2021 # OF PARKING SPACES 79 PARKING SPACES LOSS: 36 PARKING SPACES NEEDED DUE TO LOSS OF SPACES 36

TOTAL PARKING SPACES NEEDED: 72

#

slide-36
SLIDE 36

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 36 OCTOBER 2, 2019

END

slide-37
SLIDE 37

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 37 OCTOBER 2, 2019

CYPRESS BUILDING ACCESSIBLITY

OBJECTIVE: EQUITABLE ACCESS TO THE BUILDING AND THE MBTA PLAZA

  • 1. BROOKLINE HIGH SCHOOL

STUDENTS / FACULTY / STAFF / VISITORS

  • 2. MBTA USERS

DRAFT

slide-38
SLIDE 38

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

GREEENOUGH STREET

WEST NORTH SOUTH

MBTA/BHS PLAZA AND PARKING

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 38 OCTOBER 2, 2019

BROOKLINE HIGH SCHOOL USERS

SHORTEST PEDESTRIAN ROUTE FROM THE SOUTH TO FRONT DOOR

DRAFT

slide-39
SLIDE 39

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

GREEENOUGH STREET

WEST NORTH SOUTH

MBTA/BHS PLAZA AND PARKING

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 39 OCTOBER 2, 2019

BROOKLINE HIGH SCHOOL USERS

SHORTEST PEDESTRIAN ROUTE FROM THE NORTH TO FRONT DOOR

DRAFT

slide-40
SLIDE 40

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

GREEENOUGH STREET

WEST NORTH SOUTH

MBTA/BHS PLAZA AND PARKING

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 40 OCTOBER 2, 2019

BROOKLINE HIGH SCHOOL USERS

SHORTEST PEDESTRIAN ROUTE FROM THE WEST TO FRONT DOOR

DRAFT

slide-41
SLIDE 41

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

GREEENOUGH STREET

WEST NORTH SOUTH

MBTA/BHS PLAZA AND PARKING

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

DRAFT

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 41 OCTOBER 2, 2019

MBTA USERS

SHORTEST PEDESTRIAN ROUTE FROM THE SOUTH TO THE BROOKLINE HILLS PLATFORM

slide-42
SLIDE 42

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D MBTA/BHS PLAZA AND PARKING

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

GREEENOUGH STREET

WEST NORTH SOUTH

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

DRAFT

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 42 OCTOBER 2, 2019

MBTA USERS

SHORTEST PEDESTRIAN ROUTE FROM THE NORTH TO THE BROOKLINE HILLS PLATFORM

slide-43
SLIDE 43

CYPRESS FIELD

B R O O K L I N E H I L L S S T A T I O N

TAPPAN STREET DAVIS AVE BOYLSTON ST / ROUTE 9

B R I N G T O N R O A D MBTA PLAZA

WASHINGTON STREET C Y P R E S S S T R E E T

CYPRESS BUILDING

GREEENOUGH STREET

WEST NORTH SOUTH

SHORTEST ROUTE SHORTEST ACCESSIBLE ROUTE

DRAFT

BROOKLINE HIGH SCHOOL EXPANSION WILLIAM RAWN ASSOCIATES | ARCHITECTS, Inc. PAGE 43 OCTOBER 2, 2019

MBTA USERS

SHORTEST PEDESTRIAN ROUTE FROM THE WEST TO THE BROOKLINE HILLS PLATFORM