SLIDE 27 26
Sensitive but Unclassified. For NASA Internal Use Only
Analyze Optimize Calibrate Analyze Normalize Export Collect Data Estimate
This process depicts how the LPEPM Team believes parametrics should be integrated with programmatics IF the team starts with a mapped WBS
Iteration 1 Iteration 2 Iteration 3
parametric and JCL models
PBS to Project WBS using schedule UIDs to apportion costs
Dashboard Iteration 1
- Refine mapping
- f parametric to
project to normalize scope and assumptions
parametric schedule
Dashboard Iteration 2
parametric schedule per IMS
- Apply parametric
- utputs to JCL
(e.g. TI/TD; uncertainty) as appropriate
Dashboard iteration “Should Cost” “Will Cost” Raw Comparison
discrepancies in:
cost
profiles
- Cost drivers
- Map parametric
PBS to likely Project WBS
estimate in parametric tool
produces initial schedule
Dashboard Iteration 1 Raw Estimate “Will Cost” “Should Cost” Iteration 3 Iteration 2
and cost from parametric tool to scheduling tool
and cost estimate into JCL tool
correlation, uncertainty, phasing, TI/TD from parametric to populate JCL tool
- Scheduler & PM to
- verride cost
- ptimized schedule
with likely sequencing
“realistic” plan
parametric
Dashboard iteration 2
Plan
- Work with PM team:
- Mitigate Risk
- Accelerate work
- Re-sequence
activities To drive cost and risk down
iteration #3