brick township flooding solutions
play

BRICK TOWNSHIP FLOODING SOLUTIONS Presented to the Residents of - PowerPoint PPT Presentation

BRICK TOWNSHIP FLOODING SOLUTIONS Presented to the Residents of Shore Acres and Seawood Harbor Mayor John G. Ducey and Township Council June 8, 2020 ACT ENGINEERS, INC. TEAM Eric Rosina Robert Korkuch, PE, PP, CME Vice President President


  1. BRICK TOWNSHIP FLOODING SOLUTIONS Presented to the Residents of Shore Acres and Seawood Harbor Mayor John G. Ducey and Township Council June 8, 2020

  2. ACT ENGINEERS, INC. TEAM Eric Rosina Robert Korkuch, PE, PP, CME Vice President President Principal, Environmental Services Jeff Richter, PE, PP Junetta Dix Carol Beske Director, Engineering Director, Environmental Services Director, Community Outreach

  3. ACT ENGINEERS’ INITIAL SCOPE OF WORK • Review previous & on-going studies • Identify flood elevations and establish solutions by elevation • Prepare mapping of existing conditions (topography, storm sewer, roadway, bulkhead, key/vulnerable infrastructure, etc.) for 13 identified neighborhoods • 13 neighborhoods – this meeting focuses on Shore Acres and Seawood Harbor (including Snake Road); additional meetings for other neighborhoods • Recommend conceptual engineering design solutions specific to each neighborhood

  4. 13 STUDY AREAS 1) Shore Acres 2) Seawood Harbor (Including Snake Road) 3) Normandy Beach 4) Beaver Dam Creek Watershed a. Bay Harbor b. Baywood c. Harbor Place d. Island Drive / Island Court e. Vannote / Glenwood Place f. Swan Point g. Sandy Point h. Tunes Brook i. Princeton Ave (Bayfront) 5) Cherry Quay (Seagoin Road)

  5. COMMUNITY FLOODING IMPACT ASSESSMENT Impacted < 2.0’ Flood Elevation Impacted > 2.0’ – 3.4’ Flood Elevation (Short Term Design Approaches) (Long Term Design Approaches) # DWELLINGS W/ # DWELLINGS W/ SITE NAME COMPROMISED SITE NAME COMPROMISED ACCESS ACCESS Shore Acres 345 Shore Acres 167 1 1 Normandy Beach 198 153 2 Normandy Beach 2 Seawood Harbor Seawood Harbor 136 3 136 3 (Including Snake Road) (Including Snake Road) Princeton Ave (Bayfront) 134 4 Island Drive/Island Court 46 4 Baywood 67 5 Baywood 38 5 Sandy Point 55 6 Sandy Point 29 6 Island Drive/Island Court 46 7 Princeton Ave (Bayfront) 16 7 Swan Point 37 8 Tunes Brook 12 8 Tunes Brook 30 9 Swan Point 8 9 Cherry Quay (Seagoin Rd) 23 10 Bay Harbor 8 10 Bay Harbor 11 11 Cherry Quay (Seagoin Rd) 2 11 Harbor Place 10 12 Vannote / Glenwood Pl. 2 12 7 Vannote / Glenwood Pl. 13 Harbor Place 0 13

  6. USGS Barnegat Bay at Mantoloking Tide Gage (NAVD88) 4 10/31/12 2/7/20 12/21/12 11/1/19 Peak: 2.67’ Peak: 2.60’ Peak: 3.38’ Peak: 2.93’ 3.5 9/2/06 10/12/19 12/27/12 Peak: 2.64’ Peak: 2.74’ Peak: 2.90’ 3/14/10 3 Peak: 2.61’ 4/17/11 4/16/18 Peak: 2.66’ Peak: 2.60’ 2.5 Elevation (NAVD88) 2 Concept Design Elevation 1.4’ - 2.0’ 1.5 * Tide gage data is unpublished 1 during extreme storm events Average Tide Elevation • Irene (8/27 - 28/11) (rising +1.75” per decade) • Sandy (10/29 - 30/12) • Nor’Easter (3/6/ 7/18) 0.5 0

  7. TIDAL RANGE - SHORE ACRES & SEAWOOD HARBOR Seawood Harbor Lowest Road El. = 1.09’ Shore Acres Lowest Road El. = 0.87’

  8. SHORE ACRES & SEAWOOD HARBOR Conceptual Flood Mitigation Design Approaches Short Term Design Approaches Long Term Design Approaches Site Name (To Design Elevation < 2.0’) (>2.0’ Design Elevation) (Floods 1,500± hrs. per year*) (Floods 60± hrs. per year*) Install Check Valves Raise Roads / Properties Shore Acres Raise Roads Raise Bulkheads Raise Critical Bulkheads Install Pump Stations Seawood Harbor Raise Roads Raise Roads / Properties (Including Snake Road) Raise Critical Bulkheads Raise Bulkheads *USGS Mantoloking Tide Gage Raise Roadways Raise Bulkhead Heights Install Check Valves

  9. RAISE ROADWAYS TO MITIGATE TIDAL FLOODING Proposed Raised Road Elevation Existing Road Elevation • Improves vehicular access during normal tide events • May require driveway / sidewalks / yard improvements • Stormwater impacts/mitigation addressed with final design • Need for neighborhood ‘buy in’

  10. RAISE ROADWAYS TO MITIGATE TIDAL FLOODING

  11. INSTALL CHECK VALVES Ground Level Inlets at Gutter Bulkhead Check Valve

  12. RAISE / STABLIZE SHORELINES Examples: Bulkheads; living shorelines; rock revetments; etc.

  13. SHORE ACRES AND SEAWOOD HARBOR ONGOING AND NEXT STEPS • Update topographic mapping • Identify and pursue funding sources: USACE; FEMA; NJOEM; NJDOT • Secure funding • Identify and recommend Township Ordinance revisions for future design standards (i.e., minimum height of new bulkheads) • Develop a strategy, allocate funding, and implement

  14. QUESTIONS / DISCUSSION brickflooding@actengineers.com Presentation will be available at www.bricktownship.net/floodplaininformation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend