public schools project cost overview by school
play

PUBLIC SCHOOLS Project Cost Overview by School Brick Township High - PowerPoint PPT Presentation

BRICK TOWNSHIP PUBLIC SCHOOLS Project Cost Overview by School Brick Township High School $ 1,182,000 Brick Memorial High School $ 1,162,000 Lake Riviera Middle School $ 1,092,000 Veterans Memorial Middle School $ 2,230,000


  1. BRICK TOWNSHIP PUBLIC SCHOOLS

  2. Project Cost Overview by School ● Brick Township High School $ 1,182,000 ● Brick Memorial High School $ 1,162,000 ● Lake Riviera Middle School $ 1,092,000 ● Veterans Memorial Middle School $ 2,230,000 ● Drum Point Elementary School $ 1,512,000 ● Emma Havens Young Elementary School $ 415,000 ● Herbertsville Elementary School $ 653,000 ● Lanes Mill Elementary School $ 1,512,000 ● Midstreams Elementary School $ 341,000 ● Osbornville Elementary School $ 1,179,000 ● Veterans Memorial Elementary School $ 1,037,000 ● Warren H. Wolf Elementary School $ 265,000 Total Pr tal Project Cost oject Cost $ $ 12,580,000 12,580,000

  3. Project Cost Overview by Type ● Building Renovations $ 8,206,415 ● Upgrade of existing Video Surveillance System $ 1,880,969 ● New Situational Awareness System (CLASS lockdown) $ 2,346,540 ● New Visitor Management System (Hall Pass) $ 146,076 Total Pr tal Project Cost oject Cost $ $ 12,580,000 12,580,000

  4. Video Surveillance System ● Upgrade of existing Video Surveillance System in 12 schools ● New interior and exterior high-def vandal resistant Network IR Dome Cameras ● Motion detection, tampering, defocus detection, hallway view support ● New Video Management System with 30 day storage

  5. Situational Awareness System (Sielox CLASS) Crisis Lockdown Alert Status System ● New interior and exterior integrated electronic lockdown door hardware in 12 schools ● Integrated alerts to police, fire, first responders, etc. ● Customizable alerts and status ● Panic buttons and strobe lights ● Browser based accessible from anywhere ● Interface to paging and mass notification system

  6. Visitor Management System (Hall Pass) ● Visitor management System installed at Main Entrance at 12 schools ● Scan Visitors government issued ID – checked against national registry lists ● Records credentials and maintains records ● Identifies teachers, staff, substitutes, visitors, contractors, etc. ● “No-ink” thermal badge printer

  7. Brick Township Public Schools Project Design/Construction Schedule (Tentative) ● November 6, 2018…………………..Referendum ● Nov. 2018 – Feb 2019……………..Architectural / Engineering Design ● March – April 2019………………….Bidding / Contract Award ● May – August 2019………………….Construction Activities

  8. Brick Township Public Schools Referendum Funding Schedule (Tentative)

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.