PUBLIC SCHOOLS Project Cost Overview by School Brick Township High - - PowerPoint PPT Presentation
PUBLIC SCHOOLS Project Cost Overview by School Brick Township High - - PowerPoint PPT Presentation
BRICK TOWNSHIP PUBLIC SCHOOLS Project Cost Overview by School Brick Township High School $ 1,182,000 Brick Memorial High School $ 1,162,000 Lake Riviera Middle School $ 1,092,000 Veterans Memorial Middle School $ 2,230,000
- Brick Township High School
$ 1,182,000
- Brick Memorial High School
$ 1,162,000
- Lake Riviera Middle School
$ 1,092,000
- Veterans Memorial Middle School
$ 2,230,000
- Drum Point Elementary School
$ 1,512,000
- Emma Havens Young Elementary School
$ 415,000
- Herbertsville Elementary School
$ 653,000
- Lanes Mill Elementary School
$ 1,512,000
- Midstreams Elementary School
$ 341,000
- Osbornville Elementary School
$ 1,179,000
- Veterans Memorial Elementary School
$ 1,037,000
- Warren H. Wolf Elementary School
$ 265,000 Total Pr tal Project Cost
- ject Cost
$ $ 12,580,000 12,580,000
Project Cost Overview by School
- Building Renovations
$ 8,206,415
- Upgrade of existing Video Surveillance System
$ 1,880,969
- New Situational Awareness System (CLASS lockdown)
$ 2,346,540
- New Visitor Management System (Hall Pass)
$ 146,076 Total Pr tal Project Cost
- ject Cost
$ $ 12,580,000 12,580,000
Project Cost Overview by Type
Video Surveillance System
- Upgrade of existing Video Surveillance System in 12 schools
- New interior and exterior high-def vandal resistant Network IR Dome Cameras
- Motion detection, tampering, defocus detection, hallway view support
- New Video Management System with 30 day storage
Situational Awareness System (Sielox CLASS)
Crisis Lockdown Alert Status System
- New interior and exterior integrated electronic lockdown door hardware in 12 schools
- Integrated alerts to police, fire, first responders, etc.
- Customizable alerts and status
- Panic buttons and strobe lights
- Browser based accessible from anywhere
- Interface to paging and mass notification system
Visitor Management System (Hall Pass)
- Visitor management System installed at Main Entrance at 12 schools
- Scan Visitors government issued ID – checked against national registry lists
- Records credentials and maintains records
- Identifies teachers, staff, substitutes, visitors, contractors, etc.
- “No-ink” thermal badge printer
Brick Township Public Schools Project Design/Construction Schedule (Tentative)
- November 6, 2018…………………..Referendum
- Nov. 2018 – Feb 2019……………..Architectural / Engineering Design
- March – April 2019………………….Bidding / Contract Award
- May – August 2019………………….Construction Activities
Brick Township Public Schools Referendum Funding Schedule (Tentative)