BP GoM: A Case Study of a Next Generation Undersea Fiber Optic - - PowerPoint PPT Presentation

bp gom a case study of a next generation undersea fiber
SMART_READER_LITE
LIVE PREVIEW

BP GoM: A Case Study of a Next Generation Undersea Fiber Optic - - PowerPoint PPT Presentation

conference & convention enabling the next generation of networks & services BP GoM: A Case Study of a Next Generation Undersea Fiber Optic System for Oil and Gas Applications Rob Munier Jeremiah Mendez Derek Buffitt Tyco Electronics


slide-1
SLIDE 1 enabling the next generation of networks & services

conference & convention

BP GoM: A Case Study of a Next Generation Undersea Fiber Optic System for Oil and Gas Applications

Rob Munier Jeremiah Mendez Derek Buffitt Tyco Electronics Subsea Communications

slide-2
SLIDE 2 enabling the next generation of networks & services

conference & convention

Presenter Profile

Marsha has over 25 years of experience in the submarine telecommunications industry, beginning at Bell Laboratories, holding positions in R&D, engineering, sales, and project management. Marsha is currently an R&D Director responsible for fiber and cable design, as well as planning and engineering for special projects, including oil and gas

  • pportunities. Marsha received her BS

Mechanical Engineering from California State University Fresno and her MS Mechanical Engineering from Stanford University. Marsha Spalding Director, Cable & Offshore Planning & Engineering Email: marshaspalding@subcom.com Tel: +1-732-578-7154

slide-3
SLIDE 3 enabling the next generation of networks & services

conference & convention

Outline

  • Background
  • Design
  • Implementation
  • Key Project Enablers
  • Results & Conclusions
slide-4
SLIDE 4 enabling the next generation of networks & services

conference & convention

Background

  • Offshore Oil & Gas Fields are Expensive to

Develop

A typical field in the US GOM costs between US$2-4 Billion

  • High Tech Systems Require More Reliable

Bandwidth

  • Safety, hurricane resilience, managing day-to-day
  • perations, active monitoring systems, quality of life
  • Facilities are Becoming More Automated
  • Remote operations and minimal crew sizes are possible

Major production platforms require secure, stable and expandable communications that are only available through fiber:

slide-5
SLIDE 5 enabling the next generation of networks & services

conference & convention

Traditional Connectivity Approaches

Satellite and Microwave Can Isolate Expensive Deep Water Platforms Following Storm Events

  • Antenna Failures
  • Cascaded Connectivity Relies on Shallow Water Facilities

Facility Isolated Deep Water Shore Station

X

Deep Water Shore Station Shallow Water Facility Isolated

X X X

slide-6
SLIDE 6 enabling the next generation of networks & services

conference & convention

Deep Water Shore Station

The Goal of the BP GoM Fiber Solution

Direct “Virtual” Com m unication Path to Each Platform

Shallow Water Facility Remains Connected

“Disaster Proof” Netw ork

X X X

slide-7
SLIDE 7 enabling the next generation of networks & services

conference & convention

BP GoM Fiber Solution: Overarching Objectives

  • Secure, Highly Reliable Communications
  • Communications Unaffected by Significant Weather

Events – Dedicated Communications Path from Rig to Shore with No Shallow Water Platform Dependencies – Rapid Re-Manning after Storm Activity

  • Sufficient Bandwidth for Current & Future

Needs

  • Audio Telecon Service
  • Video Conferencing
  • Remote Troubleshooting
  • Data Transmission from Down-Hole Monitoring or

Seismic Sensors

  • Flexible
  • Easily Expandable
  • Upgradeable
  • Implementable &Cost Effective
  • Modest Construction & Technology Risk
slide-8
SLIDE 8 enabling the next generation of networks & services

conference & convention Freeport Pascagoula Marlin Horn Mt. Nakika Thunder Horse Atlantis Mad Dog Holstein

  • 19 OADM BUs: 7 Initial Platform Connections; 12 Future Expansion Stubs
  • Both East & West Communications for Redundancy from Each Platform
  • Second Fiber Pair for Expansion

The BP GoM Network

slide-9
SLIDE 9 enabling the next generation of networks & services

conference & convention

BP GoM: Design Requirements

– Bandwidth

  • Provide initial 1 x GigE to

7 primary platforms

  • Upgradeable to 64 X

10Gb/s ultimate capacity

– Configuration

  • Self healing “wet’ ring

between landings

  • 2 fiber pairs
  • 19 primary branches

– Technology

  • Powered trunk,

repeaterless branches

  • Wet-mate subsea

connections

  • Dynamic Riser Cables
  • Compact Terminal Eqt

– Expansion

  • Branches up to 100 km
  • Trunk extendable an

additional 300 km

  • Sea floor terminations to

subtend secondary platforms or sensors

– High Reliability

Dynamic Riser Riser Cable Termination FDC OADM BU

Sensor

slide-10
SLIDE 10 enabling the next generation of networks & services

conference & convention

  • SL17 Submarine Cable
  • Millennia Joints
  • Optically Amplified Repeaters
  • Standard BU Bodies

BP GoM Backbone Implemented with Standard Telecom Hardware

slide-11
SLIDE 11 enabling the next generation of networks & services

conference & convention

Platform Connection Hardware

Adapt Proven & Qualified Technologies and Products for O&G Functionality Fiber Distribution Canister & Deployment Pallet Based on Industry Standard Wet-Mates within SubCom Repeater Body & Couplings Riser Cable Termination & Fusible Link Based on Millennia Joints OADM BUs Incorporation of OADM Functionality in Standard BUs

slide-12
SLIDE 12 enabling the next generation of networks & services

conference & convention

BP GoM Platform Connection Types

Dynamic Riser Cable with Fiber Distribution Canister for 4 Platforms Subsea Wet-Mate in Deployment Pallet for 3 Platforms Two Methods of Platform Connection

slide-13
SLIDE 13 enabling the next generation of networks & services

conference & convention

  • 3. The main lay vessel overboards the Dynamic Riser Cable (DRC) and

associated equipment

Dynamic Riser Connection Installation

  • 1. A pull-in system (winch skid) is installed on the platform
  • 2. Support ROV attaches a messenger to the pulling wire
  • 4. The DRC is secured topside; the bend limiter connector is secured by

the ROV

  • 5. The Main Lay Vessel lays the DRC creating the catenary, followed by

the FDC & branch leg, while the support ROV performs touchdown monitoring

  • 6. The Main Lay Vessel lays the final bight, completing the connection
slide-14
SLIDE 14 enabling the next generation of networks & services

conference & convention

Subsea Wet-Mate Connection Installation

  • 1. The support vessel ROV performs an inspection of the

UTA and seabed

  • 2. The Main Lay Vessel deploys the Deployment Pallet to

the seabed

  • 3. The flying lead is deployed to the seabed, support vessel

ROV performs wet-mate connection

  • 4. The Main Lay Vessel completes the branch leg, installs

and lays the final bight, completing the connection

slide-15
SLIDE 15 enabling the next generation of networks & services

conference & convention

  • 62 Pipeline Crossings
  • 19 Branching Units
  • 21 Repeaters
  • ~300 km of Burial
  • ~900 km of Surface Lay
  • 2 Pre-Laid Shore Ends
  • 2 Un-manned Cable Stations

BP GoM Installation Accomplishments

slide-16
SLIDE 16 enabling the next generation of networks & services

conference & convention

Key Project Enablers

slide-17
SLIDE 17 enabling the next generation of networks & services

conference & convention

Project Success Attributed To:

  • Robust Network & Hardware Designs
  • Adaptation of Existing Technologies
  • Long-term Planning & Detailed Installation Modeling
  • Successful Peer Design Reviews
  • Coordination of all Parties
  • Established Installation Techniques Customized for

O&G Hardware

Key Project Enablers

slide-18
SLIDE 18 enabling the next generation of networks & services

conference & convention

Engineering, Modeling & Review

slide-19
SLIDE 19 enabling the next generation of networks & services

conference & convention

Engineering, Modeling & Review

  • Extensive Routing & Engineering
  • Modeling & Analysis
  • Design & Peer Reviews
  • Complexity of Seabed Infrastructure
  • Flowlines & umbilicals in the vicinity of facility
  • Drill center infrastructure
  • Lease Block & Pipeline Crossing Requirements
  • Future exploration
  • Pipeline Mattressing
  • Dynamic Riser Cable Catenary
  • Motion characteristics
  • Clashing with existing infrastructure
  • Catenary shape
  • Subsea Equipment (FDC/DP/Fusible Link)
  • Deployment
  • Cathodic protection
  • Riser Equipment
  • Riser Termination/Buoyancy/Centralizers/Uraduct
  • Inclusion of all Design Parameters
  • Robust Network Design
  • Adherence to Safety Protocols
  • Proper Integration into Facility Systems
  • Incident-Free Installation
slide-20
SLIDE 20 enabling the next generation of networks & services

conference & convention

Installation & Coordination

slide-21
SLIDE 21 enabling the next generation of networks & services

conference & convention

Installation & Coordination

  • Adaptation of Existing Equipment
  • Standard Cable Lay Procedures & Equipment
  • Cable Modeling & Sea Trials
  • Topside Coordination
  • Simultaneous Operations
  • Normal Loading & Transportation Techniques
  • No Alteration of Cable Load/Lay Equipment Required
  • Traditional Testing & Power Safety Procedures
  • Foundation of Standard Submarine Cable Product Handling
  • Generate DRC lay procedures
  • Dry run DRC equipment overboarding
  • Verify subsea equipment deployment procedures
  • Practice ROV wetmates, model ROV interventions

Coordination of topside activities required schedule integration early in the process to allow:

  • Topside telecom equipment installations
  • Installation of riser pull-in equipment
  • Network testing

To avoid schedule and POB conflicts with O&G activities which have priority Safety - Safety knowledge & procedures are already ingrained in the existing systems Operational Integrity - Did not require shipboard personnel to learn new lay or testing techniques Schedule - Did not require the generation and review of new procedures by all parties De-conflict installation through constant monitoring of in-field activities such as:

  • Drilling Operations in Vicinity of Subsea Connections
  • Support Activities at Floating Facilities during Riser

Installations

  • Pipe Lays over Cable Route
  • Seismic Surveys through Lease Blocks
slide-22
SLIDE 22 enabling the next generation of networks & services

conference & convention Freeport Pascagoula Marlin Horn Mt. Nakika Thunder Horse Atlantis Mad Dog Holstein

Network Effectiveness: 2008 Hurricanes

GUSTAV IKE

2008 Hurricanes Gustav & Ike proved the value and strength of the network

slide-23
SLIDE 23 enabling the next generation of networks & services

conference & convention

Gulf of Mexico 2008 Hurricane Season

Network Effectiveness

  • Ability to monitor platform motions

and stability through storm events

  • Preliminary assessment of systems

prior to sending crews offshore

  • Undamaged, full-time

communications in place to allow earlier return of facility personnel

  • With earlier deployment of personnel,
  • il production re-started with

substantially less downtime

slide-24
SLIDE 24 enabling the next generation of networks & services

conference & convention Freeport Facility 1 Facility 2 Pascagoula Marlin Horn Mt. Nakika Thunder Horse Atlantis Mad Dog Holstein

  • Network Expansion: 2 Additional Subsea Connections

2009 Network Expansion

slide-25
SLIDE 25 enabling the next generation of networks & services

conference & convention

BP GoM Summary of Success

  • Robust, Highly Reliable Communication Connectivity

Demonstrated during 2008 Hurricane Season

  • Expandability Proven through Additional Platform

Connections in 2009, including Third Party Customers

  • Improved Communications Reliability has become an

Attractive Benefit for Improved Productivity

  • Introduction of OADM BU Technology has been a Benefit

for the Traditional Telecom Market

  • Technology has Potential Application to Scientific

Systems

slide-26
SLIDE 26

2010

Pacifico Convention Plaza Yokohama & InterContinental The Grand Yokohama 11 ~ 14 May 2010 www.suboptic.org

enabling the next generation of networks & services

The 7th International Conference & Convention

  • n Undersea Telecommunications

conference & convention