big swamp rehabilitation project
play

Big Swamp Rehabilitation Project: Hydrologic Study Will Glamore, PhD - PowerPoint PPT Presentation

Big Swamp Rehabilitation Project: Hydrologic Study Will Glamore, PhD Water Research Laboratory, School of Civil and Environmental Engineering University of New South Wales Introduction Definitions: Big Swamp Pipeclay Canal


  1. Big Swamp Rehabilitation Project: Hydrologic Study Will Glamore, PhD Water Research Laboratory, School of Civil and Environmental Engineering University of New South Wales

  2. Introduction Definitions: • Big Swamp • Pipeclay Canal • Cattai Creek Technical Terms: • Hydrology • Hydrodynamics • Groundwater • Hydraulic Head • Acidity (pH) • Modelling

  3. Introduction

  4. Logic of Study and Report 1. How did we get here?

  5. Conceptual Understanding • Manning River catchment • Average annual rainfall at is 8,420 km 2 Moorland gauge is 1,436 mm but seasonal. • Big Swamp-Pipeclay catchment is 113 km 2 or • ~2000 hectares below 0 m ~1% of total. AHD (mean sea tide)

  6. Conceptual Understanding

  7. Conceptual Understanding

  8. Conceptual Understanding Drainage History • 1899 Big Swamp Drainage Scheme Approved • 1905 completed • Designed to pass upland catchment directly to Cattai Creek • Big Swamp drainage was secondary issue • Expanded in 1960s and 90s.

  9. Conceptual Understanding

  10. Tide, Drains and Acid Sulfate Soils

  11. DRY Conditions

  12. Flood Conditions

  13. Draining Conditions

  14. Conceptual into Actual What happens at Big Swamp?

  15. Field Data Collection Feb June Sept

  16. Field Data Collection Program

  17. Field Data Collection Program

  18. Elevation Data Check

  19. Cross-Sections and Culverts • 33 Cross-sections taken from upstream of Pipeclay canal to bridge near Harrington. • Plus every known culvert/structure • All based on high precision RTK-GPS positioning.

  20. Field Data Collection Program

  21. New Instruments Installed

  22. Cattai Creek Logger

  23. Upper Pipeclay Canal Logger

  24. RESULTS: Dry Conditions

  25. Wet Conditions- Flooding on Big Swamp • Levee Bank at 1.8m AHD • 1% ARI = 3.1 m AHD • A 100 year event is required to flood Big Swamp over the levee banks from local catchment runoff • Levee banks overtop from back-flooding of Manning River at ~10 yr event.

  26. Flooding

  27. Flood Event: March 1978 (1.3% AEP) 12000 Killawarra Hydrograph: March 1978 Flood Pipeclay Creek Hydrograph: March 1978 Flood 10000 8000 Flow (m3/s) 6000 4000 2000 0 0 10 20 30 40 50 60 70 80 Time (hrs)

  28. Flood Event: May 1977 (15% AEP) 6000 Killawarra Hydrograph: May 1977 Flood Pipeclay Creek Hydrograph: May 1977 Flood 5000 4000 Flow (m3/s) 3000 2000 1000 0 0 20 40 60 80 100 120 Time (hrs)

  29. >200 mm of rainfall was recorded at the site in 3 days in late Jan 2013

  30. Wet Conditions: Jan-Feb 2013

  31. On-ground Impacts

  32. Remediation Options What can we do?

  33. Priority Assessment • Developed Method to determine which areas are highest priority and should be remediated. • Based on: Groundwater/Soil • Acidity • Surface water • Total discharge • • Areas 1/7 and 0/6 were highest priority

  34. Restoration Options • Objective is to remediate • On-ground works: acid problem by: Encourage neutralisation at • source by removing Dilution • floodgates and levee sections Neutralisation • Prevent further acid creation • Reduction • by infilling drains and keeping wet • Aim is to: Reduce acid transport by • Improve water quality • removing floodgates and filling drains Reduce acid ponding • Encourage reduction of Improve ecology • • existing acid Decrease acid discharges • Ensure no impact to flooding from soil • and limit stagnant water.

  35. Computer Model • Computer model developed using the field data to: Assess conceptual model • Simulate existing scenaro • Modify model to test: • • No floodgates anywhere • Selected restoration options • Dry versus wet scenarios • Plan for on-ground works

  36. Computer Model

  37. Model Results

  38. Existing Site Drainage

  39. Scenario: No Floodgates

  40. S-W Remediation Options

  41. S-E Remediation Option

  42. Restoration Options

  43. Summary • Restoring S-W and S-E areas will remove large high priority acid zones. • The S-E zone will not be fully restored as it still requires drainage. • The remediation works will not impact flooding elsewhere. • Any overland inundation will be shallow and intermittent.

  44. Recommendations • On-ground works Floodgates • Levees • Drain modification and • construction Land grading • • Future Monitoring Continuous sampling • Before-After sampling • Photo points • • Proceed with Additional Restoration Sites • Proceed with Plan of Management

  45. Acknowledgments • Greater Taree City Council Mr Dave Hopper • Various field support staff • • Wetland Care Australia • Various stakeholders and volunteers • Landholders for Access to Monitoring Stations

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend