SLIDE 1
Big Swamp Rehabilitation Project: Hydrologic Study
Will Glamore, PhD
Water Research Laboratory, School of Civil and Environmental Engineering University of New South Wales
SLIDE 2 Introduction
Definitions:
- Big Swamp
- Pipeclay Canal
- Cattai Creek
Technical Terms:
- Hydrology
- Hydrodynamics
- Groundwater
- Hydraulic Head
- Acidity (pH)
- Modelling
SLIDE 3
SLIDE 4
Introduction
SLIDE 5 Logic of Study and Report
SLIDE 6 Conceptual Understanding
is 8,420 km2
catchment is 113 km2 or ~1% of total.
- Average annual rainfall at
Moorland gauge is 1,436 mm but seasonal.
AHD (mean sea tide)
SLIDE 7
Conceptual Understanding
SLIDE 8
SLIDE 9
Conceptual Understanding
SLIDE 10 Conceptual Understanding
Drainage History
Scheme Approved
- 1905 completed
- Designed to pass upland
catchment directly to Cattai Creek
secondary issue
- Expanded in 1960s and 90s.
SLIDE 11
SLIDE 12
Conceptual Understanding
SLIDE 13
SLIDE 14
Tide, Drains and Acid Sulfate Soils
SLIDE 15
DRY Conditions
SLIDE 16
Flood Conditions
SLIDE 17
Draining Conditions
SLIDE 18
Conceptual into Actual What happens at Big Swamp?
SLIDE 19
Field Data Collection
June Sept Feb
SLIDE 20
Field Data Collection Program
SLIDE 21
Field Data Collection Program
SLIDE 22
Elevation Data Check
SLIDE 23 Cross-Sections and Culverts
from upstream of Pipeclay canal to bridge near Harrington.
culvert/structure
- All based on high precision
RTK-GPS positioning.
SLIDE 24
Field Data Collection Program
SLIDE 25
New Instruments Installed
SLIDE 26
Cattai Creek Logger
SLIDE 27
Upper Pipeclay Canal Logger
SLIDE 28
RESULTS: Dry Conditions
SLIDE 29
SLIDE 30 Wet Conditions- Flooding on Big Swamp
- Levee Bank at 1.8m AHD
- 1% ARI = 3.1 m AHD
- A 100 year event is
required to flood Big Swamp over the levee banks from local catchment runoff
back-flooding of Manning River at ~10 yr event.
SLIDE 31
Flooding
SLIDE 32 Flood Event: March 1978 (1.3% AEP)
2000 4000 6000 8000 10000 12000 10 20 30 40 50 60 70 80 Flow (m3/s) Time (hrs) Killawarra Hydrograph: March 1978 Flood Pipeclay Creek Hydrograph: March 1978 Flood
SLIDE 33 Flood Event: May 1977 (15% AEP)
1000 2000 3000 4000 5000 6000 20 40 60 80 100 120 Flow (m3/s) Time (hrs) Killawarra Hydrograph: May 1977 Flood Pipeclay Creek Hydrograph: May 1977 Flood
SLIDE 34
>200 mm of rainfall was recorded at the site in 3 days in late Jan 2013
SLIDE 35
Wet Conditions: Jan-Feb 2013
SLIDE 36
SLIDE 37
SLIDE 38
SLIDE 39
SLIDE 40
SLIDE 41
SLIDE 42
SLIDE 43
SLIDE 44
SLIDE 45
SLIDE 46
On-ground Impacts
SLIDE 47
Remediation Options What can we do?
SLIDE 48 Priority Assessment
determine which areas are highest priority and should be remediated.
- Based on:
- Groundwater/Soil
- Acidity
- Surface water
- Total discharge
- Areas 1/7 and 0/6 were
highest priority
SLIDE 49
SLIDE 50 Restoration Options
- Objective is to remediate
acid problem by:
- Dilution
- Neutralisation
- Reduction
- Aim is to:
- Improve water quality
- Reduce acid ponding
- Improve ecology
- Decrease acid discharges
from soil
- On-ground works:
- Encourage neutralisation at
source by removing floodgates and levee sections
- Prevent further acid creation
by infilling drains and keeping wet
removing floodgates and filling drains
existing acid
- Ensure no impact to flooding
and limit stagnant water.
SLIDE 51 Computer Model
developed using the field data to:
- Assess conceptual model
- Simulate existing scenaro
- Modify model to test:
- No floodgates anywhere
- Selected restoration
- ptions
- Dry versus wet scenarios
- Plan for on-ground works
SLIDE 52
Computer Model
SLIDE 53
Model Results
SLIDE 54
Existing Site Drainage
SLIDE 55
Scenario: No Floodgates
SLIDE 56
S-W Remediation Options
SLIDE 57
S-E Remediation Option
SLIDE 58
Restoration Options
SLIDE 59
SLIDE 60 Summary
areas will remove large high priority acid zones.
fully restored as it still requires drainage.
- The remediation works will
not impact flooding elsewhere.
will be shallow and intermittent.
SLIDE 61 Recommendations
- On-ground works
- Floodgates
- Levees
- Drain modification and
construction
- Land grading
- Future Monitoring
- Continuous sampling
- Before-After sampling
- Photo points
- Proceed with Additional
Restoration Sites
Management
SLIDE 62 Acknowledgments
- Greater Taree City Council
- Mr Dave Hopper
- Various field support staff
- Wetland Care Australia
- Various stakeholders and
volunteers
- Landholders for Access to
Monitoring Stations