BENESCH
Richard D. Kalson, Esq. rkalson@beneschlaw.com 614.223.5380 (W) 412.417.4209 (C)
Recovering for Unforeseen Conditions May 20, 2016 ADSC West Coast Chapter Annual Meeting
BENESCH ADSC West Coast Chapter Annual Meeting Recovering for - - PowerPoint PPT Presentation
BENESCH ADSC West Coast Chapter Annual Meeting Recovering for Unforeseen Conditions May 20, 2016 Richard D. Kalson, Esq. rkalson@beneschlaw.com 614.223.5380 (W) 412.417.4209 (C) Field Changes Things to Consider: Understand what your soil
Richard D. Kalson, Esq. rkalson@beneschlaw.com 614.223.5380 (W) 412.417.4209 (C)
Recovering for Unforeseen Conditions May 20, 2016 ADSC West Coast Chapter Annual Meeting
Things to Consider:
– How do you know if you have a change of ground conditions? – Everyone on team must know expected conditions AND notice
geotechnical information with consistent and correct Drill Logs and Daily Diaries.
ground conditions.
and daily diaries.
condition.
Daily Journals
– Sexually explicit, racially offensive comments – Foul language – Personal information – Admissions of liability – Opinions
– Easier review – Easier maintenance – Location/Retention issues – Easier to complete daily
needed
when previously excluded by subcontract (your proposal is critical)
precedence, especially as concerns scope of work.
Owner Disclosures
Driller’s Definition: When subsurface conditions are materially different than as advertised in the contract documents.
encountered during performance of the work differ materially from the conditions described in the contract documents.
unusual and unforeseen, and differ from conditions usually encountered in the type of work specified in that area.
Determination of fault is not a requirement.
upon by owners and contractors.
while courts in other states find exceptions to the general rule that contract provisions requiring written notice of a claim will not be strictly enforced if some other notice is provided.
differing site condition claims.
review and negotiation of your contract.
in contract documents.
boulders than indicated in the contract documents, perhaps at unexpected elevations.
than indicated in the contract documents.
documents or knowledge from prospective bidders and such information would have educated a contractor regarding an existing underground condition, a contractor may recover additional costs as a result of the condition.
required to establish such recovery.
waive claim.
formal notice requirements in some states where there is constructive notice, a waiver of notice provisions, a lack of prejudice despite the lack of formal written notice, contractor may not be immediately aware of the scope of the differing site condition.
not to waive the claim by executing a serious of unambiguous releases barring suits or causes of action arising on or prior to date of execution, released claims for extra work where subcontractor did not show on releases that extra additional amounts were owed to it. Must reserve claim on lien waivers.
– The owner had nonotice of the contractor's additional work until it was already completed.The owner did not have an opportunity to investigate the differing site conditionsand make a determination of how to accommodate them. – Rather,the contractor went ahead and completed the work and then presented the bill. – The contract notice provisions had not been met or waived
impliedly warrant the adequacy of their plans and specifications.
specifications to receive Spearin protection.
specifications.
for local public entity projects: “material that is hazardous
classes of] disposal site. . .” This third type ensures that the owner takes responsibility for the proper disposal of hazardous wastes.
in 2006 to define a type 1 differing site condition as: “Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids”.
– “Since the disclaimers wholly denied responsibility for the subsurface conditions indicated, in violation of [the statute mandating the differing site conditions clause], they were properly excluded from jury consideration. . . . [¶] . . . . [E]ven under the law preceding [that statute], a general disclaimer could not overcome positive assertions of fact regarding subsurface conditions upon which the contractor was entitled to rely. (See E. H. Morrill Co. v. State of California, 65 Cal.2d at 793.) Adjusting the Morrill analysis to substitute the required statutory standard of “indicated” for positive assertions of fact, the disclaimer in this case is precisely the kind of general disclaimer condemned in the Morrill case.”). – California courts have rejected efforts to circumvent the differing site conditions clause with disclaimers – The contractor must prove (1) a subsurface or latent physical condition at the site, (2) differing materially (3) from what was indicated in the bidding information. What was “indicated” can be either a positive statement about the condition in the bidding information, or an inference about the condition arising from that information – “Determining whether the contract and related documents indicated the subsurface conditions at the jobsite . . . is a matter of contract interpretation . . .”
.2d 1034 (Utah Sup.Ct. 1978), at the contractor's request, the county gave the contractor a chart showing the water table of the project area. The contractor argued that the chart was false and misleading because the water was located much closer to the surface than was indicated by the chart. The contractor claimed that the high water table resulted in extra costs. The county claimed that the contractor's negligence and omissions caused the problems with the runway.
there was a fluctuating water table in the project area, and that neither party was aware of such fact.
misrepresentation of factual matters within the state's knowledge or withholding of material information, and when both parties had equal access to information as to the nature of the tests which resulted in the state's findings, a contractor could not claim in the face of a pertinent disclaimer that the state's presentation of the information amounted to a warranty of the conditions that would actually be found.
398 (Nev. 1968), in Nevada a contractor which follows deficient plans and specifications furnished by the owner will not be responsible for any loss or damage that results in absence of any negligence on the part of the contractor or an express warranty.
complete work, liable only for improper workmanship.
1967), an owner’s specification is in nature of warranty, that if complied with will produce a satisfactory result.
Kemper, JV, 191 Wash. App. 142, 364 P.3d 784 (2015)
– The contractor did not establish its claim that the county breached the contract by refusing to grant orders and time extensions for differing site conditionsbecause the contractor failed to satisfy two of the elements for a differing site condition claim – A construction contract does not make any representation that would support a differing subsurface site condition claim if the contract (1) is silent about subsurface conditions or (2) instructs bidders to make their own interpretations or conclusions about subsurface conditions, places on bidders the risk of assumptions that differ from data provided by the project owner, and warns bidders about the scope of the data provided.
awarded a $6.2 million contract to construct two buildings in Hawaii that were 300 yards apart and 700 yards from the ocean.
– The contractor did not visit the site before submitting its bid; rather, it relied upon eight soil borings that were included in the bid package. The contractor presumed that the borings were representative of the site, even though they were all taken by only one of the building sites. – The actual conditions at the other building site were substantially different, resulting in the contractor incurring additional costs for piling, delays and dewatering operations. – The contractor sought an equitable adjustment for a Type I differing site condition. – Ruling in favor of the owner, the court explained that the owner was not required to satisfy a Type I differing site conditions claim because the borings could not reasonably be interpreted as indicating the subsurface condition of a building location 300 yards away in an area that was geologically diverse.
23 (2003)
– There can be no recovery under Hawaii law for extra work if the work is covered by the terms of the construction contract. – In order to prevail on a differing site conditionsclaim under Hawaii law, a contractor must prove that the conditions indicated in the contract differ materially from those encountered during
reasonably unforeseeable based on all of the information available to the contractor at the time of bidding. The contractor also must show that it reasonably relied upon its interpretation of the contract and contract-related documents and that it was damaged as a result
conditions.
Richard D. Kalson, Esq. Benesch Friedlander Coplan & Aronoff LLP 41 South High Street, Suite 2600 Columbus, Ohio 43215-3506 614.223.9380 (W) 412.417.4209 (C) rkalson@beneschlaw.com
Benesch – Cleveland Benesch – Hackensack Benesch - Shanghai 200 Public Square, Suite 2300 411 Hackensack Ave. 3rd Floor Kerry Centre Tower 1, Suite 3002 Cleveland, OH 44114 Hacksensack, NJ 07601 1515 W. Nanjing Road (216) 363-4500 (201) 488-1013 Shanghai 200040 China (86-21-3222-0388) Benesch – Columbus Benesch – Indianapolis Benesch – Wilmington 41 S. High St. Suite 2600 One American Square, Suite 2300 222 Delaware Ave. Suite 801 Columbus, OH 43215 Indianapolis, IN 46282 Wilmington, DE 19801 (614) 223-9300 (317) 632-3232 (302-442-7010) Benesch – Chicago 333 West Wacker Dr. Suite 1900 Chicago, IL 60606 (312-466-7555)