bailey cr creek e k estates tentative m e map ap
play

BAILEY CR CREEK E K ESTATES TENTATIVE M E MAP AP WASHOE COUNTY - PowerPoint PPT Presentation

BAILEY CR CREEK E K ESTATES TENTATIVE M E MAP AP WASHOE COUNTY PLANNING COMMISSION| FEBRUARY 7, 2017 28.76 acre undeveloped site Located south Reno east of Geiger Grade/Toll Road intersection Proj ojec ect A Area ea Bound


  1. BAILEY CR CREEK E K ESTATES TENTATIVE M E MAP AP WASHOE COUNTY PLANNING COMMISSION| FEBRUARY 7, 2017

  2. • 28.76 acre undeveloped site • Located south Reno  east of Geiger Grade/Toll Road intersection Proj ojec ect A Area ea

  3. • Bound by  Geiger Grade (north)  Toll Road (west)  Kivett Drive (east) • Surrounding uses:  Single Family (north)  Single Family/Vacant/Commercial (east)  Common area/Single Family (south)  Single Family (west) Proj ojec ect A Area ea

  4. • County Land Use Designation  Southeast Truckee Meadows Area Plan • General Rural (GR) = 0.90 ac • Medium Density Suburban (MDS) = 27.815 ac • Restricts density to 2 dwelling units/acre • Surrounding Land Use Designations:  North – MDS  East – GC & MDS  South – GR & MDS  West - MDS Proj ojec ect A Area ea

  5. • Comstock Estates North (TM6- 11-94) – Expired • Cottonwood Creek (TM03-012)  Approved December 2003  2 8.66 ± acres  57 lots (2 du/acre)  Lots ranged from 9,988 – 32,302 sqft  Access via Shadow Hills Drive and Moon Lane • Tentative Map expired before built out Background und

  6. Tentative Map for 56 lots • 1.95 du/ac (2 du/ac allowed)  Lot sizes range from 0.33 to 0.81 • 0.50 ac min along Geiger • 0.33 ac min along Creek  Average lot size = 0.41 ac  0.75 acre of common area for detention and drainage • FEMA Flood zones  Shaded Zone X (500-year)  AE – Bailey Creek  A – north of site Proj ojec ect R Reques est

  7. Drainage • Onsite drainage directed to detention basins or Bailey Creek via underground storm drain pipes • V-ditches will be provided along the project eastern boundary • All runoff from adjacent properties and developed portions of the project site will be directed into detention basins. • Impacts mitigated per Truckee Meadows Drainage Manual and WC Code. Proj ojec ect S Spec ecif ifics

  8. Access & Traffic • Primary access from Geiger Grade  Secondary, gated emergency access, at Moon Lane.  Required for secondary fire access if main entrance is blocked. • Traffic Analysis  ADT = 533  PM Peak Hour = 56 (below threshold for Traffic Study)  Right turn eastbound deceleration lane on Geiger Grade Proj ojec ect S Spec ecif ifics

  9. • Drainage • Utility Availability • Schools • Views & Open Space • Horse Migration • Access & Traffic Key P ey Poi oints

  10. Stacie Huggins Associate shuggins@woodrodgers.com 775.823.5258 – direct 775.250.8213 – mobile

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.