background
play

Background Colin Taylor - Director 30+ years in Building Services - PowerPoint PPT Presentation

Background Colin Taylor - Director 30+ years in Building Services industry - 10 years design/installation of heat networks Background in BMS & energy networks, ESCos & Facility Management Richard Johnson - Director 25+ years


  1. Background Colin Taylor - Director 30+ years in Building Services industry - 10 years design/installation of heat networks Background in BMS & energy networks, ESCo’s & Facility Management Richard Johnson - Director 25+ years construction & civil engineering industry with major UK contractor 8 years management/design/installation of heat networks Original Objectives in December 2012 Establish credible UK Design and Installation Contractor • • Become a Benchmark for Quality Capitalise on the Opportunity within UK market • • Increase Powerpipe UK Market Share • Offer a non-operator “Turnkey Solution”

  2. Established 1986, Sweden’s largest manufacturer of pre-insulated • pipes • Annual Production of: • 25,000 Pipes – Single & Twin (300Km) • 10,000 Fittings & Joints • Products confirm to BS EN Standards EN BS 253, 489 • Verified by Euroheat & Power 2015 Powerpipe’s UK sales £2M – 30% •

  3. Design/Technical Support High Quality Installation Pipe Supply Business Development Product Risk Management Training UK based operation Sub Suppliers Contractors • Directly employed & highly trained technical installation operatives • Technical and design capability – supported by Powerpipe 13/14 Turnover: £1.6m Design Install 14/15 Turnover: £2.5m Maintain 15/16 Turnover: £3.5m UK District Heating Network Market

  4. Capabilities • Pre-insulated pipe design – routing, expansion, feasibility studies & coordination • Pre-insulated pipe supply, install & commission • Civil engineering works associated with the installation of pre-insulated pipe • Maintenance of pre-insulated pipe heating and cooling networks, including water quality • Energy Services Company (ESCo) consultancy – financial and technical modelling • Stockist

  5. Quality • “Once Only” Policy - Raise the bar in terms of UK DH installation • Employed competent trained and certified staff “Best in Class” installation processes and • procedures developed from Swedish standards • Accurate records and data from installation process - GPS • Accreditations:

  6. Heat Network Design • Heat mapping, high level routing & load assessments • Detailed design to BS EN13941– expansion, maximise temperature differential & heat loss calculations • CIBSE Heat Networks – Code of Practice Network sizing, diversity, form of terminations, heat substations, • future expansion • Service coordination – Ground Penetrating Radar, Trial Pits etc. Accurate utility information, reduces project risk, delays & costs • • Installation depth – cost critical Cap/Op ex Wayleaves, possessions, NRSWA, parking suspensions – optimised • practical routing • Construction phased implementation coordination • Testing allowances – NDT, Air Tightness, Hydraulic • Live before all installed – Temporary Energy Centre • Flushing and testing considerations • Operation, Maintenance & Warranty

  7. DH in the UK - Practicalities • Construction/installation generally not considered – time & cost • National Joint Utilities Group - DH not recognised • Utility/general contractors - life cycle risk and conditions required for install of DH • UK Construction Environment – Adversarial • Contracts – Civils & Mechanical • Health & Safety • Time & Programme Constraints Site Coordination & Logistics – 12m lengths • • Cold Lay “the norm” in the UK • Warranty • Contractors Warranty – 12 months • Product Warranty– 12 months, 5yr, 10yr, more… Specialist Contractor Warranty – contract specific durations •

  8. Heat Network – Costs Civil Work- Excavate and Reinstate Composite Rates Mechanical F&R - • Typical split 50:50 Civils and Mechanical Mechanical Mechanical Supply and Install, Excavation in Soft Excavation in Hard Soft per M Hard per M • Central London 60:40 or even 70:30 Inc. prelims per M Surface per M Surface per M Pipe/Casing • Considerations to factor feasibility rates DN 20/110 £ 268.00 £ 140.00 £ 310.00 £ 408.00 £ 578.00 • Environment DN100/225 £ 392.00 £ 156.00 £ 328.00 £ 548.00 £ 720.00 • Access DN150/280 £ 454.00 £ 164.00 £ 344.00 £ 618.00 £ 798.00 DN300/500 £ 860.00 £ 190.00 £ 478.00 £ 1,050.00 £ 1,338.00 • Programme Note: No Allowance for hand excavation/services • Season/Weather • Services • Excavation – hard/soft • Reinstatement materials Possessions – parking bays, road, network rail • • Contractor Risk • Operational costs also critical in overall commercial model • Eneteq can assist with development of site specific budgets for cap-ex and op-ex

  9. Heat Network - Project Risk Risk Management & Allocation Nr Risk Description Impact High Med Low Control Measure Cost Resultant Risk • Design 1 Desired pipe route obstructed Trench diversion and Hold additional pipe offsite or £6,691.97 by additional unkown services alterations that result in the onsite if space and security (£133,839.35 x 5%) • Routing, Expansion, Heat Loss, Sizing requiement for additional pipe, permits Yes - - Low standard and bespoke fittings, joints and assocaited labour, • Installation plant and prelims Hold additional standard £12,549.43 fittings offsite or onsite if space (£83,662.88 x 15%) Low • Services, Programme (3m day in London), and security permits Hold additional joint casings £62,454.71 Pipe 12m, Delay and foam packs offsite or Based upon an addional 102 Low onsite if space and security joints permits • Operation 2 Excavation/Install rate slower Non-productive working Addional civils labour and plant Increased excavtion labour and • Water Quality, Leak Detection, Annual than anticipated at Tender resulting in increased project to maintain tender programme plant costs to be provided by Yes - - Unknown duration, staff and prelims rates others Cycles costs Additional prelims and labour £26,788.00 costs estimated to be 4-weeks or £8,188.00 per week Medium • Controls in duration 3 Logisitcs and materials Unloading area(s) in or around Budget for additional 4-number £5,038.00 • Framework Agreement distribution not as planned Bart's Square not available, HIAB days and associated or £1,259.50 per day resulting in increased time for labour Shared Risk Register • deliveries and/or additional Yes - - Low HIAB days to bring pipe and • Documented Test & Inspection Processes materials from the offsite compound. • Quality Procedures Items not onsite or at the Hold additional materials offsite As detailed above offsite compound will result in - Yes - Low increased programme periods, • As Installed Drawings & Records - GPS prelims etc. • Turnkey Solutions – Supply & Install • Defects Liability & Warranty

  10. Leak Detection What is it? • A pair of wires embedded in throughout the pipe insulation during manufacture • Alarm, Surveillance & Fault Location • Passive or Active Systems Available • Monitors Water Egress & Ingress What does it Cost? • Typically <3% of Contract Value What does it Offer? • Long term monitoring, performance analysis • Early fault location – (1mtr in 1,000mtr) • Minimise & reduce cost of repairs • Reduce OPEX

  11. Heat Loss Conditions • Ground/Ambient Temperature – 10DegC • Conductivity – 1.5W/mK • Cover - 600mm Flow Return Differential Series-1 Series-2 Series-3 Series-4 Unit 95 75 20 352.8 295.8 257.5 226.9 W/mK 75 45 30 235.2 197.2 171.7 151.3 W/mK Reduction in Losses 117.6 98.6 85.8 75.6 W/mK Reduction from Series-1 n/a 155.6 181.1 201.5 W/mK

  12. Innovation Hybrid Systems • Main Transition Mains - Pre-insulated Steel • House/Plot Connections – Flexible Pipes • PEX-A 85DegC 6bar (Higher temps & pressure reduce life expectancy) • Alu-PEX 95DegC 10bar • CuFlex 95DegC+ 16bar • Single, Double & different sizes • High levels of insulation – 0.0216W/mK • Press fittings Steel Press Fitting • HAELOK AG – Swiss manufacturer • Steel Pipe sizes - 6mm – 168mm (6”) • High Temperature, High Pressure no welding • Being assessed by the Danish District Heating Association

  13. Summary Good Design • Compliant with EN13941, CIBSE Code of Practice • Correctly sized carrier pipe, diversified to meet the predicted load • Shortest route, considers construction & site constraints • Maximum differential temperature, minimum heat loss • Active leak detection Good Implementation & Maintenance • Quality Installation that provides accurate records (GPS) Leak detection & System monitoring • • Water quality, “steady” operating conditions Minimises Total Cost of Ownership • CAPEX & OPEX

  14. Case Study: Bristol City Council • Initial appointment for detail design, supply and installation of preinsulated pipe suspended below a new bridge crossing the River Avon • Appointed under a framework agreement for design and procurement of City wide DH network including GPR Surveys, Civils & Supply and Installation • Current Contract Value circa £750k (anticipated £4-5M over 5-years)

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend