Athletics Facilities Renovations BOARD OF TRUSTEES MEETING OCTOBER - - PowerPoint PPT Presentation

athletics facilities renovations
SMART_READER_LITE
LIVE PREVIEW

Athletics Facilities Renovations BOARD OF TRUSTEES MEETING OCTOBER - - PowerPoint PPT Presentation

Athletics Facilities Renovations BOARD OF TRUSTEES MEETING OCTOBER 12, 2017 AC ACCOMPLISHM HMENT NTS Board of Trustees tour Track/Football & Gymnasium (new paint & wood floor completed; bleachers being installed) AC ACCOMPLISHM


slide-1
SLIDE 1

Athletics Facilities Renovations

BOARD OF TRUSTEES MEETING OCTOBER 12, 2017

slide-2
SLIDE 2
slide-3
SLIDE 3
slide-4
SLIDE 4

AC ACCOMPLISHM HMENT NTS

Board of Trustees tour Track/Football & Gymnasium (new paint & wood floor completed; bleachers being installed)

slide-5
SLIDE 5

AC ACCOMPLISHM HMENT NTS

Saturday game against Claremont: Eagles 23 – Claremont 20 (Double Overtime) Football team Thursday workout on new field before 1st home game.

slide-6
SLIDE 6

Delayed DSA approval

  • Increment 1: 3/15/17
  • Increment 2: 4/11/17
  • Shortened duration for construction

Athletics and PE Renovation Project

slide-7
SLIDE 7

Audio/Visual added during construction phase

  • Discovery/Design/Cost Proposed
  • Submittals Processed/Approved
  • Conduits approved/installed
  • Added Cost

Gym Lobby Restrooms – DSA Structural Requirements

  • Shoring required due to deteriorated wall conditions

Prime Trade Contractor

  • Football Permeable Base – rejected and reinstalled

Removal of Concrete slab at Locker-room Bldg HazMat Abatement - Unforeseen

  • Asbestos Tile underneath the existing Tile @ Gym Restrooms

(17) Construction Change Directives

  • Each requires DSA submittal, review & approval

Athletics and PE Renovation Project Challenges

slide-8
SLIDE 8
slide-9
SLIDE 9

Construction: Original Board Approved Contracts for Project $9,363,429 Allowances (included above) $335,000 Allowances (change orders): Approved by Board on 9/14/17: (308,191) BEC Electric CO#3 – 10/12/17 BOT: (97,529) Interpipe CO#2– 10/12/17 BOT: (12,673) Projected remaining change orders: (281,114) Net increase to original contracts $364,507 New Construction Contracts Total: $9,727,936

Athletics and PE Renovation Project

slide-10
SLIDE 10

Balfour Beatty $695,680.00 Projected Change Order 148,920.00 New Construction Manager Total: $844,600.00

Athletics and PE Renovation Project

Construction Manager (CM)

slide-11
SLIDE 11

Athletics and PE Renovation Project

Project Assessment (Architect/Engineering, Other) CEQA 4,910.00 Fees 813.00 Soils Testing 14,750.00 Utility Locator Services 6,980.00 Other geotechnical testing 3,600.00 Sub Total: 31,053.00

Site Infrastructure

slide-12
SLIDE 12

Athletics and PE Renovation Project

Architect's Fees 894,335.00 DSA Plan Check 82,178.00 Other Plan check fees (AQMD, City, CO, Other) 130.00 Plan Reproduction 100.00 Bid Advertisement 5,000.00 Sub Total: 981,743.00

Project Development & Plans

slide-13
SLIDE 13

Athletics and PE Renovation Project

Construction Cost per Bids 9,363,429.00 CM Contract 695,680.00 Shade Structure 194,961.00 Gym Bleacher 118,143.00 Fair-Play Scoreboard 51,210.00 Special Equipment Audio Visual 139,000.00 Project Management 228,198.00 Course of Construction Insurance (COC) 6,742.00 Asbestos Abatement 41,155.00 IOR-- Lead 73,500.00 Testing and Inspection 88,350.00 Interim Housing 40,000.00 Fire Watch Services 21,000.00 Construction Sub Total: 11,061,368.00

Construction

slide-14
SLIDE 14

Athletics and PE Renovation Project Summary

Site Infrastructure 31,053.00 Project Development & Plans 981,743.00 Construction Contracts 11,061,368.00 Increase to Project 364,507.00 Increase to CM Contract 148,920.00 Estimated Project Total: 12,587,591.00

slide-15
SLIDE 15

Locker-room Bldg (occupy) 11/14

  • Lockers completed

11/14

Gymnasium (team use) 10/24

  • Lobby/RR

11/20

Baseball Stadium (sod grow-in) 11/2 – 12/15

  • Shade Structures

1/23 (pending shop drawing approval)

Athletics and PE Renovation Project Forecast – Major Completion Milestones

slide-16
SLIDE 16

Questions?

BOARD OF TRUSTEES MEETING OCTOBER 12, 2017