at Barsebck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS - - PowerPoint PPT Presentation

at barseb ck 1 and 2
SMART_READER_LITE
LIVE PREVIEW

at Barsebck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS - - PowerPoint PPT Presentation

Dismantling of the RPV and Internals at Barsebck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS Seminar 2010 Studsvik 14 September 1 Agenda Introduction Background Segmentation Waste management Time schedule


slide-1
SLIDE 1

1

Dismantling of the RPV and Internals at Barsebäck 1 and 2

Niklas Bergh Westinghouse Electric Sweden

NKS Seminar 2010 Studsvik 14 September

slide-2
SLIDE 2

2

Agenda

  • Introduction
  • Background
  • Segmentation
  • Waste management
  • Time schedule
  • Staffing
  • Conclusions
slide-3
SLIDE 3

3

Introduction

  • Barsebäck 1 and 2

(B1 & B2)

  • ASEA-Atom BWR:s
  • Electrical effect

620 MW

  • B1 closed 1999
  • B2 closed 2005

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-4
SLIDE 4

4

Background

  • Basis for strategic decision:

Handling of RPV and Internals

  • One-piece removal
  • Segmentation
  • Determine volumes for the expansion
  • f SFR
  • Define year for placement of

segmentation contract

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-5
SLIDE 5

5

Segmentation methods

  • Thermal techniques
  • Plasma Arc Cutting
  • Oxy-fuel Cutting
  • MDM
  • Mechanical techniques
  • Shearing
  • Band sawing
  • Circular sawing
  • Other
  • Abrasive Water Jet Cutting

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-6
SLIDE 6

6

Segmentation methods – pros and cons

  • Thermal techniques
  • Fast
  • Costly
  • Radiation and visibility issues
  • Mechanical techniques
  • Minor secondary waste
  • Easy to install
  • Reliable
  • Limited cutting thicknesses

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-7
SLIDE 7

7

Internals segmentation

  • Mechanical cutting program

recommended due to extensive Westinghouse experiences

  • Wet segmentation in internal

parts pool using band saw, shear, tube cutter and circular saw

  • Waste packed in the pool
  • Done in parallel for B1 and B2

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-8
SLIDE 8

8

RPV segmentation

  • A combination of dry thermal and

wet mechanical cutting

  • Bottom modified for filling/draining
  • Auxiliary support systems installed
  • PAC used to cut annular pieces

from the RPV

  • Height of annular pieces < 2 m,

avoiding nozzles

1 2 3 5 4 6 7 8 Bottom Head 1,4 m 2,0 m 1,8 m 2,0 m 2,0 m 2,0 m 1,6 m 2,0 m

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-9
SLIDE 9

9

RPV segmentation

  • Holes made with MDM/drill

for lifting of the rings

  • Annular pieces moved to internal

parts pool

  • Further segmented with band saw

and packed into containers

  • Done in series for B1 and B2

to utilise lessons learned

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-10
SLIDE 10

10

Packing

  • Goal: Achieve optimal packing
  • f containers to reduce costs
  • Previous Westinghouse

experience:

  • Internals
  • 0.4-1.1 ton/m3
  • RPV
  • 1.0 ton/m3

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-11
SLIDE 11

11

Activity contents

  • Long-lived to SFL:
  • Core grid
  • Core shroud
  • Core shroud cover
  • Core spray
  • Part of control rod guide tubes
  • The rest to SFR

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-12
SLIDE 12

12

Containers

  • BFA-tank
  • 1.3 x 2.3 x 3.3 m
  • For long-lived LILW
  • Large Steel Box
  • 1.2 x 2.4 x 2.4 m
  • For short-lived ILW
  • ISO Container
  • 6.1 x 2.4 x 1.3 m
  • For short-lived LLW

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-13
SLIDE 13

13

Time schedule

  • Prerequisites: 3 shifts 24 hours per day
  • Internals segmentation done in parallel for B1 and B2
  • RPV segmentation done in series for B1 and B2
  • Design & manufacturing phase 2 years
  • Segmentation campaign 2.5 years

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-14
SLIDE 14

14

Staffing

  • Manpower on site during the different phases:
  • Crew of 11 during the internals segmentation
  • Crew of 14 during the RPV segmentation
  • Functions:
  • Project management
  • Engineers (Installation, quality and technical lead)
  • Operators (Tools and crane)
  • Decontamination
  • Health physics
  • Supervision

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions

slide-15
SLIDE 15

15

Conclusions

  • Proven technology available for segmentation of RPV

and Internals

  • The contract for segmentation should be placed no later

than 2017 in order to start establishment on site 2020

  • Total waste amounts:
  • 220 m3 in SFL
  • 1 360 m3 in SFR

Introduction Background Segmentation Waste management Time schedule Staffing Conclusions