at barseb ck 1 and 2
play

at Barsebck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS - PowerPoint PPT Presentation

Dismantling of the RPV and Internals at Barsebck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS Seminar 2010 Studsvik 14 September 1 Agenda Introduction Background Segmentation Waste management Time schedule


  1. Dismantling of the RPV and Internals at Barsebäck 1 and 2 Niklas Bergh Westinghouse Electric Sweden NKS Seminar 2010 Studsvik 14 September 1

  2. Agenda  Introduction  Background  Segmentation  Waste management  Time schedule  Staffing  Conclusions 2

  3. Introduction  Barsebäck 1 and 2 (B1 & B2)  ASEA-Atom BWR:s  Electrical effect 620 MW  B1 closed 1999  B2 closed 2005 Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 3

  4. Background  Basis for strategic decision: Handling of RPV and Internals • One-piece removal • Segmentation  Determine volumes for the expansion of SFR  Define year for placement of segmentation contract Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 4

  5. Segmentation methods  Thermal techniques • Plasma Arc Cutting • Oxy-fuel Cutting • MDM  Mechanical techniques • Shearing • Band sawing • Circular sawing  Other • Abrasive Water Jet Cutting Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 5

  6. Segmentation methods – pros and cons  Thermal techniques • Fast • Costly • Radiation and visibility issues  Mechanical techniques • Minor secondary waste • Easy to install • Reliable • Limited cutting thicknesses Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 6

  7. Internals segmentation  Mechanical cutting program recommended due to extensive Westinghouse experiences  Wet segmentation in internal parts pool using band saw, shear, tube cutter and circular saw  Waste packed in the pool  Done in parallel for B1 and B2 Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 7

  8. RPV segmentation Head 1,4 m 1  A combination of dry thermal and 2,0 m 2 wet mechanical cutting 1,8 m 3  Bottom modified for filling/draining 2,0 m 4  Auxiliary support systems installed 2,0 m 5  PAC used to cut annular pieces from the RPV 2,0 m 6  Height of annular pieces < 2 m, 1,6 m 7 avoiding nozzles 2,0 m 8 Bottom Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 8

  9. RPV segmentation  Holes made with MDM/drill for lifting of the rings  Annular pieces moved to internal parts pool  Further segmented with band saw and packed into containers  Done in series for B1 and B2 to utilise lessons learned Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 9

  10. Packing  Goal: Achieve optimal packing of containers to reduce costs  Previous Westinghouse experience: • Internals • 0.4-1.1 ton/m 3 • RPV • 1.0 ton/m 3 Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 10

  11. Activity contents  Long-lived to SFL: • Core grid • Core shroud • Core shroud cover • Core spray • Part of control rod guide tubes  The rest to SFR Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 11

  12. Containers  BFA-tank • 1.3 x 2.3 x 3.3 m • For long-lived LILW  Large Steel Box • 1.2 x 2.4 x 2.4 m • For short-lived ILW  ISO Container • 6.1 x 2.4 x 1.3 m • For short-lived LLW Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 12

  13. Time schedule  Prerequisites: 3 shifts 24 hours per day  Internals segmentation done in parallel for B1 and B2  RPV segmentation done in series for B1 and B2  Design & manufacturing phase 2 years  Segmentation campaign 2.5 years Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 13

  14. Staffing  Manpower on site during the different phases: • Crew of 11 during the internals segmentation • Crew of 14 during the RPV segmentation  Functions: • Project management • Engineers (Installation, quality and technical lead) • Operators (Tools and crane) • Decontamination • Health physics • Supervision Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 14

  15. Conclusions  Proven technology available for segmentation of RPV and Internals  The contract for segmentation should be placed no later than 2017 in order to start establishment on site 2020  Total waste amounts: • 220 m 3 in SFL • 1 360 m 3 in SFR Waste Introduction Background Segmentation Time schedule Staffing Conclusions management 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend