art and science of nus data centres building
play

Art and Science of NUS Data Centres Building D ATA C ENTRE @ NUS - PDF document

Art and Science of NUS Data Centres Building D ATA C ENTRE @ NUS Contents I . Nostalgia I I . Science of Elements in a Data Centre I I I . NUS DC Live Migration the Art and Challenges I V. Milestones in Pictures V. Whats next


  1. Art and Science of NUS Data Centres Building

  2. D ATA C ENTRE @ NUS Contents I . Nostalgia I I . Science of Elements in a Data Centre I I I . NUS DC Live Migration – the Art and Challenges I V. Milestones in Pictures V. What’s next

  3. Nostalgia... Part I D ATA C ENTRE @ NUS

  4. D ATA C ENTRE @ NUS • Electrical System

  5. D ATA C ENTRE @ NUS • Raised Floor Cablings

  6. D ATA C ENTRE @ NUS • Air Conditioning System

  7. D ATA C ENTRE @ NUS • UPS System

  8. D ATA C ENTRE @ NUS • Layout and Space Utilization

  9. D ATA C ENTRE @ NUS • Tape Library

  10. D ATA C ENTRE @ NUS • Secure Printing of SmartCards

  11. D ATA C ENTRE @ NUS • Emergency Exits

  12. D ATA C ENTRE @ NUS • Surveillence Cameras

  13. D ATA C ENTRE @ NUS • Signages

  14. D ATA C ENTRE @ NUS Part I I Science of Elements in a Data Centre

  15. Critical Elements in a DataCentre • Tiering of Data Centre • IT Area Versus Non-IT area • Ceiling Height and Raised Floor System • Power Design (Supply + cabling) • HVAC units (Temperature and Humidity) • Fire Detection and Suppression • Environmental Monitoring System • Structural Loading • Physical Security • Structured Cabling • Network Considerations

  16. Tiering of Data Centre •Defining the Tiers. Tier I Tier I is composed of a single path for power and cooling distribution, without redundant components, providing 99.671% availability. Tier II Tier II is composed of a single path for power and cooling distribution, with redundant components, providing 99.741% availability. Tier III Tier III is composed of multiple active power and cooling distribution paths, but only one path active, has redundant components, and is concurrently maintainable, providing 99.982% availability. Tier IV Tier IV is composed of multiple active power and cooling distribution paths, has redundant components, and is fault tolerant, providing 99.995% availability

  17. This chart illustrates tier requirements:

  18. This chart illlustrates the tier attributes of the sites from which the actual availability numbers were drawn:

  19. [HP]

  20. Part I I I NUS DC Live Migration – the Art and Challenges

  21. Key Considerations and Difficulties Encountered • The datacentre must have minimal downtime as it is running live. • Renovated DC must be able to cater for DC operation till year 2010. • Deciding DC tier level. • Maximising IT Area. • Identifying possible/planned hot spot/area. • Non-standard air flow racks/equipments. • Inter-racks dependencies. • Control/minimising dust in operating IT area during the renovation. • Racks with weight overloading floor structural design. • Air flow issues within a rack. • Standardising racks design. • Linkage of M&E vendors and IT vendors during renovation and IT migration in this live DC.

  22. D ATA C ENTRE @ NUS OLD DC OLD DC • Single incoming power source (electrical to IT) • Standalone UPSes; not all equipment on UPS • Equipments mostly on single UPS supply • Insufficient cooling with no humidity control • Generator does not meet existing IT load requirement • No environmental monitoring system • Building smoke detectors and I nergen gas system at selected areas • Un-structured cablings

  23. New DC • Two different incoming power source to • Dedicated N+ 1 Crac units with humidity control , backup by a dedicated DC (electrical for IT) generator • Centralized 2N UPS with individual • New generator for IT electrical supply isolation transformer supplying power to all IT equipments in DC • EMS (temperature, humidity, water detection, PDU incoming and outgoing, • Dual power source for all IT racks crac units, FM200, etc) • 400mm Raised Floor System • Fire detection and protection systems - FM200 and building smoke detectors • Structured Cabling • Hot & Cold aisles with ducted return • Fire rated perimeters • Stand alone earthing system • CCTV Monitoring • Contactless Door Access System

  24. D ATA C ENTRE @ NUS I nteresting Facts... • Renovation Duration : 1 Year • DC NFA : 720 sqm • 60% attained IT Area

  25. Data Centre Highlights... Part I I I

  26. Security Contactless Card Access >> 0 >> 1 >> 2 >> 3 >> 4 >>

  27. Security Cameras >> 0 >> 1 >> 2 >> 3 >> 4 >>

  28. Two different incoming power source to DC >> 0 >> 1 >> 2 >> 3 >> 4 >>

  29. Centralized UPS for all IT equipment in DC >> 0 >> 1 >> 2 >> 3 >> 4 >>

  30. Dual power source for all IT racks >> 0 >> 1 >> 2 >> 3 >> 4 >>

  31. Dedicated A/C with humidity control (backup by generator) >> 0 >> 1 >> 2 >> 3 >> 4 >>

  32. New generator for project IT electrical requirement >> 0 >> 1 >> 2 >> 3 >> 4 >>

  33. EMS (temperature, humidity, liquid detection, etc) >> 0 >> 1 >> 2 >> 3 >> 4 >>

  34. FM200 Gas Cylinders >> 0 >> 1 >> 2 >> 3 >> 4 >>

  35. FM200 Pipings above Ceiling Boards >> 0 >> 1 >> 2 >> 3 >> 4 >>

  36. FM200 System >> 0 >> 1 >> 2 >> 3 >> 4 >>

  37. FM200 Release Nozzle on Ceiling Board >> 0 >> 1 >> 2 >> 3 >> 4 >>

  38. Water Detection Cable >> 0 >> 1 >> 2 >> 3 >> 4 >>

  39. Structured cabling below raised floor >> 0 >> 1 >> 2 >> 3 >> 4 >>

  40. Network Cablings >> 0 >> 1 >> 2 >> 3 >> 4 >>

  41. Earth Cablings >> 0 >> 1 >> 2 >> 3 >> 4 >>

  42. Return Air Duct for CRAC >> 0 >> 1 >> 2 >> 3 >> 4 >>

  43. Internal View of a Typical PDU >> 0 >> 1 >> 2 >> 3 >> 4 >>

  44. Milestones in Pictures... Part I V

  45. Installation of compressors for CRAC units >> 0 >> 1 >> 2 >> 3 >> 4 >>

  46. Installation of compressors for CRAC units >> 0 >> 1 >> 2 >> 3 >> 4 >>

  47. Installation of compressors for CRAC units >> 0 >> 1 >> 2 >> 3 >> 4 >>

  48. Installation of compressors for CRAC units >> 0 >> 1 >> 2 >> 3 >> 4 >>

  49. Delivery of CRAC units >> 0 >> 1 >> 2 >> 3 >> 4 >>

  50. Phase-3 >> 0 >> 1 >> 2 >> 3 >> 4 >>

  51. Phase-4 >> 0 >> 1 >> 2 >> 3 >> 4 >>

  52. Media Room Entrance >> 0 >> 1 >> 2 >> 3 >> 4 >>

  53. Media Room >> 0 >> 1 >> 2 >> 3 >> 4 >>

  54. Network Room Entrance >> 0 >> 1 >> 2 >> 3 >> 4 >>

  55. Network Room >> 0 >> 1 >> 2 >> 3 >> 4 >>

  56. UPS Room >> 0 >> 1 >> 2 >> 3 >> 4 >>

  57. What’s next... Part V D ATA C ENTRE @ NUS

  58. D ATA C ENTRE @ NUS DC @ NUS High School (NUSHS) • � Disaster Recovery Site outside Kent Ridge Campus � Construction Duration: Jun – Oct’ 05 (4 mth) � NFA = 800 sqm � Operational in Nov / Dec 2005 Primary Data Centre • � Able to cater to Computer Centre’s 10-year I T plans � Proposed NFA = 2,000 sqm � Coming soon...

  59. D ATA C ENTRE @ NUS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend