Enabling Works Update Area North Fusion Carley Richards Southam and Windmill Hill : Archaeology update In late March, Fusion the HS2 Area Central Enabling Works Contractor, will start the archaeological investigation work. This will


slide-1
SLIDE 1

Enabling Works Update Area North – Fusion Carley Richards

slide-2
SLIDE 2

Southam and Windmill Hill : Archaeology update

  • In late March, Fusion the HS2 Area Central Enabling Works Contractor, will start the archaeological

investigation work. This will involve excavating trenches and recording any finds

  • The Southam site is located on the south-western outskirts : Access to the site will be along Leamington

Road, Kineton Road and Banbury Road.

  • The Windmill Hill site will be accessed along Windmill Hill.
  • This work will be carried out by Connect, Fusion’s archaeology subcontractor. The investigations will be

done by small teams of archaeologists assisted by an excavator. There will be a maximum of two teams

  • n each site.
  • These works are scheduled to complete by the end of June 2020.
  • An Advanced Works Notice has been issued to the Community with further details for each site
slide-3
SLIDE 3

Archaeological Trial Trench

  • Trial Trenches are undertaken at pre

identified locations

  • Further investigation works are undertaken

within the trial trench at encountered locations of interest

  • Archaeological works are then planned to

investigate the area further based upon initial findings

slide-4
SLIDE 4

Archaeological trial trench areas Southam

slide-5
SLIDE 5

Archaeological trial trench areas – Windmill Hill

slide-6
SLIDE 6

Fencing to the south of the B4451 Kineton Road

  • Works are due to commence in the area

from the start of April 2020 until mid June

  • 8.5km of fencing required
  • A compound will be established utilising

the former Cubbington Saw Mills site at Harp Farm, with direct access to the A423 Banbury Road

  • The fencing to be installed is typically stock

proof fencing with agricultural gates

  • Public Rights of Way are incorporated into

the design

slide-7
SLIDE 7

Fencing to the north of the B4451 to the A425

  • Works are due to commence in this area

from late March to the end of April 2020

  • 2km of fencing required
  • A compound will be established alongside

the A425 Leamington Road. This site access is subject to highway authority approval

  • The fencing to be installed is typically stock

proof fencing with agricultural gates

  • Public Rights of Way are incorporated into

the design

slide-8
SLIDE 8

Enabling Works Update Area North – LM Melanie Ryan Adam Brookes

slide-9
SLIDE 9

Summary of LM current/future works

  • TBM Utilities Works. (Detailed on next

slide)

  • Long Itchington Compound Bellmouth
  • construction. (1)
  • Long Itchington Compound Construction.

(2)

  • Ridgeway Lane Widening. (3)
  • Fosse Way Highway Works & Compound

(4)

  • Vegetation Clearance for access points

and for route of HS2.

  • Community Engagement events including

local drop-ins, forums and parish council meetings

  • Notifications and news updates sent out

via post and also put on to the HS2 commonplace website.

3 4

Fosse Way Welsh Road

2 1

slide-10
SLIDE 10

TBM Utilities Works

  • Installation of ducting along Bascote

Road is ongoing and will be finished mid-March 2020.

  • Cabling works will follow after to duct

installation has been completed.

  • By June 2020
  • Welsh Road will close from mid-

February to mid-March to allow for installation of 11kv cable.

  • Bascote Road will close from mid-

February to mid-April to allow for installation of 11kv cable.

  • The B4452 will close from mid-

March to mid-May to allow for installation of 11kv cable.

slide-11
SLIDE 11

Long Itchington Compound and Ridgeway lane

slide-12
SLIDE 12

Long Itchington Compound

Bellmouth Construction- Completed re-opened dependent on TBM Supply works Spine Road and Compound Construction – Complete by Mar 2020

slide-13
SLIDE 13

Ridgeway Lane Widening

Construct Ridgeway lane widening to facilitate TBM Access – Feb 2020 to June 2020 Construct New Pedestrian Crossing – April 2020

slide-14
SLIDE 14

Fosse Way Highway Works

The Dates shown are subject to the design and coordination development Existing Fosse Way Apr 20 – Sep 20 Construction of the northern roundabout with utility works and tie ins to existing roads. Oct 20 – Mar 21 Construction of the southern roundabout along with utility works and tie ins to existing roads

slide-15
SLIDE 15

Ecological Mitigation

slide-16
SLIDE 16

Cubbington March 19

slide-17
SLIDE 17

Finham June 19

slide-18
SLIDE 18

Hedgerow Planting Hibernacula Basking Banks

slide-19
SLIDE 19

Main Works Update Area North – BBV Andy De Bell Gurcharan Singh

slide-20
SLIDE 20

First main compounds: Long Itchington Wood

  • Occupancy from November 2019
  • Occupancy Date Main Office 11/20(BBV)

Other significant main compounds:

  • Fosse Way
  • A46
  • Occupancy early 2020

Additional compounds will be set up during 2020 Overall, fewer compounds than allowed in the Environmental Statements

Main compounds

What to expect

  • 6-months work to establish the compound
  • We will erect hoardings / fencing around the

Compound to ensure the site is safe and secure.

  • There will be a nominal increase in vehicle

movements during the delivery of equipment, machinery, materials and portacabins.

  • Traffic arrangements to manage flows during

construction and to receive deliveries .

  • Utility works in and around the compound for

the supply of water, electricity and telecommunications.

  • Long Itchington wood: from March 2020 prep

work will start on the north portal tunnel which includes installation of plant equipment , grout and slurry plant.

slide-21
SLIDE 21

Start occupancy from 03/19 Complete main office 11/20 North Portal Office setup

  • Approx. 70 Staff and 170 Workforce

Site Containing: ▪ Site Clearance ▪ Compound Fencing ▪ Access Roads ▪ Cadent Gas protection ▪ Utility supply water - comms - power ▪ Compound at North Portal EWC Scope: ▪ Site Clearance and Compound Fencing ▪ Access Roads ▪ Cadent Gas protection ▪ Utility supply water - comms - power ▪ Compound at North Portal ▪ Installation of balancing pond and

  • utfall

Long Itchington Wood Tunnel Main Compound

slide-22
SLIDE 22

LIWT – North Portal Const. Sequence

slide-23
SLIDE 23

Programme of activity

  • TBM initial delivery at North Portal using the A425 Leamington Road via

the upgraded Ridgeway Lane to the compound.

  • Breakthrough bore 1 at South Portal / Polo Club
  • TBM to be transferred fromSouth Portal to North Portal using the A425 Leamington Road.
  • About 12 week period to transport and reassembly the entireTBM back to launch.
  • Breakthrough bore 2 at South Portal/ Polo Club.
  • First delivery of components for the Tunnel Boring machine(TBM) will be delivered

to the compound from August 2020.

  • TBM ready to bore from December 2020, with approximate one years of tunnelling to

follow .

slide-24
SLIDE 24

Occupancy Date Temporary 04/20 Occupancy Date Main office 09/20

  • Approx. 57 Staff and 155 Workforce

Site Containing:

▪ Main offices (with utilities) ▪ Installation of balancing pond and outfall ▪ Temporary Stockpiles ▪ Storage area ▪ New Roundabout ▪ Temporary Balancing Pond ▪ Sewage plant Early Works Contractor Current Scope: ▪ Site Clearance ▪ Part of the Working platform ▪ Compound Fencing ▪ Access Roads ▪ Utility supply water - comms - power

Sublot 2 – Fosse Way Compound

slide-25
SLIDE 25

Routes to Compound

TBM delivery Operational deliveries

slide-26
SLIDE 26

Routes to South Portal

TBM delivery Operational deliveries

slide-27
SLIDE 27

Ufton Roundabout

Post works View Current View

slide-28
SLIDE 28

A425 Leamington Road

slide-29
SLIDE 29

Mass Haul

Surplus Deficit Surplus Deficits Deficit

slide-30
SLIDE 30

Main Works Update Area Central – EK Chris James

slide-31
SLIDE 31

Heave Trial

3

slide-32
SLIDE 32

Main Works

Main Compound

  • Possession in April
  • 4 months Fusion works
  • Site clearance, drainage

access road,

  • Main compound