Anchorage Port Modernization Project
Project Management Institute Alaska Chapter February 2016 Dinner Meeting
Presented by: Lon Elledge, P.E. Program Manager CH2M February 10, 2016
Anchorage Port Modernization Project Project Management Institute - - PowerPoint PPT Presentation
February 10, 2016 Anchorage Port Modernization Project Project Management Institute Alaska Chapter February 2016 Dinner Meeting Presented by: Lon Elledge, P.E. Program Manager CH2M ANCHORAGE PORT MODERNIZATION PROJECT Briefing Agenda Port
Project Management Institute Alaska Chapter February 2016 Dinner Meeting
Presented by: Lon Elledge, P.E. Program Manager CH2M February 10, 2016
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
Terminal/POL Age (years) Min. Thickness Observed Percent Loss Terminal 1 54 0.15” 67% POL Terminal 1 50 0.15” 67% Terminal 2 46 (avg) 0.20” 55% Terminal 3 40 (avg) 0.18” 59% POL Terminal 2 20 0.13” 71%
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
– Geotechnical Advisory Commission (GAC)
Kirby
Association
Alaska District (USACE)
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
Develop Concepts Charrette with follow on development of 3 Concept Plans Completed Select Concept Municipality selects the concept and initiates the project Completed Preliminary Engineering Concept refinement, develop permitting strategy, refine procurement strategies. Collect survey, aerial mapping, geotechnical, environmental, ship operations, hydrological, hydro‐acoustical and pile driving data for use by future Designers of Record On‐going Permitting Engage in the APMP Permitting process Initiating Design Procure Designer(s) of Record Contracts through the Municipality and prosecute designs Not Started Construct Procure Construction Contracts through the Municipality and prosecute construction efforts Not Started
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
Phase Task Cost Funds Required Proposed Fund Source Construction 1 ½ North Extension Stabilization and Replace POL 1 (fuel and cement) $127 M $0 In hand 2017‐2018 2 Replace Terminal 2 and Terminal 3 $298 M $298 M Statewide GO Bond 2018‐2022 3 Replace POL 2 $35 M $35 M Various 2019 or later Subtotal $460 M $333 M 4 Complete North Extension Stabilization $88 M $88 M Various 2019 or later 5 Terminal 3 Demolition $8 M $8 M Various 2022 or later Total $556 M $429 M
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
28
ANCHORAGE PORT MODERNIZATION PROJECT
29
ANCHORAGE PORT MODERNIZATION PROJECT
30
ANCHORAGE PORT MODERNIZATION PROJECT
32
ANCHORAGE PORT MODERNIZATION PROJECT
Source: Alaska Business Monthly
ANCHORAGE PORT MODERNIZATION PROJECT
Source: Alaska Business Monthly
ANCHORAGE PORT MODERNIZATION PROJECT
35
Anchorage Port Modernization Project
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT
38
ANCHORAGE PORT MODERNIZATION PROJECT
ANCHORAGE PORT MODERNIZATION PROJECT