analysts investors visit
play

ANALYSTS & INVESTORS VISIT ROSEBEL MINE Management Team Rosebel - PowerPoint PPT Presentation

RGM OPERATIONS PRESENTATIONS ANALYSTS & INVESTORS VISIT ROSEBEL MINE Management Team Rosebel September 12 th , 2017 TSX: IMG NYSE: IAG Cautionary Statement Cautionary Statement All information included in this presentation, including any


  1. 2017 Business Optimization Key Drivers Mill Operations strategy to reduce Cyanide & Grinding Media consumption Parts and Consumables Procurement end-to-end process review and improvement Enhanced Business OPEX Intelligence (BI) Systems Drilling & Blasting accuracy and productivity optimization Production Cost $/Tonne Mined Loading and Hauling efficiency and cost improvement All-In Sustaining Costs (AISC) Sustaining CAPEX Strategic fixed asset management and CAPEX discipline $850-900/oz. CAPEX Tonnes Milled Precrush and liner configuration to increase Mill run rate & capacity Lean Six Gold Produced Ore Quality Improvement of ore fragmentation and reduction of dilution in ore mined Sigma Optimization Projects Optimization of Mill feed blend and CIL configuration Recovery 9

  2. Key Achievements - 2016  Highest tonnes mined on record (> 64 MT)  Highest tonnes Hard rock and Trans rock Milled on record  Lowest $ t/ mined in five years  Lowest G&A costs in five years  Lowest Sustaining Capital in five years  Results in:  AISC well below $1,000/oz, first time in four years 10

  3. RGM Operations Health, Safety & Risk Shalini Kesarsing Health & Safety Supdt. September 12, 2017

  4. Health and Safety Risks and Challenges  Competencies, Certifications and Training  Emergency Readiness  SRCS implementation (i.e. related procedures)  Improving of EHS Management System  Safety Maturity (Behavior Based Safety a. Leading Indicators b. Lagging Indicators 3.50 % completed 120% 3.00 100% 100% 100% 100% 100% 95% 2.50 100% 90% 2.00 80% 1.50 60% 1.00 114% 100% 100% 100% 97% 94% 0.50 85% 40% 0.00 YTD Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 20% 2017 DART Rate 0.71 0.85 0.88 0.90 0.85 0.00 0.96 0.87 0.43 0% TRIR 1.41 1.70 1.76 2.24 0.85 0.00 2.88 1.30 0.87 Safety Planned Planned Timely Bus Medical Exposure to DART Target 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 Meetings Activities Inspections CAPA Inspections Surveillance employees Closure TRIR Target 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 0.46 12

  5. Achievements 2017 Significant Risk Training & Skill Employee Emergency Management Development Engagement Readiness >7500 hours Fall Prevention, Supervisor Safety More mock Confined Space, meetings exercises & drills (site wide) LOTOV & Machine Safeguarding Work Floor Personal Emergency Presences & Leadership – H/S Response Team Stand down personnel meetings Internal & Third Development of Party inspections Contractor Safety improved Safety Upgraded ER and audits meetings & field Induction in equipment interactions progress 13

  6. Some pictures Fall Authorized Training Fire Awareness Training Work floor presences with Mill employees Work floor presences with Mine employees Risk assessment during Mill shutdown H&S Inspection 14

  7. RGM Operations Environment Jerry Finisie Sustainability Manager September 12, 2017

  8. Strategy 2017 • Re-certification new • Detailed 2017 Mine ISO 14001 – 2015 Closure Plan (MCP) Standard • Reclamation • Ensure Legal Research Compliance & Due Diligence SYSTEM CLOSURE MANAGEMENT: PLANNING: WATER EXPLORATION TREATMENT PROJECT: OPTIMIZATION: • ETP Treatability • Baseline studies Study and Sewage completed for Treatment Options Saramacca Project by Golder ESIA SKILL DEVELOPMENT OF STAFF 16

  9. Achievements 2017 System Management: System Management: Legal Compliance & ISO 14001 - 2015 Due Diligence Gap Analysis between ISO 14001 – Environmental Baseline Assessment 2004 and ISO 14001 – 2015. Roma and East Tailings Road (ETR) pits. 3 Workshops for Managers, Superintendents, Coordinators, GF’s EHS Legal Compliance Audit July 2 Training sessions for auditors and OHS and Environmental staff Mindrinetie discharge 100% New HSS Policy English and Dutch compliant . version signed by GM. 17

  10. ISO 14001-2015 Workshops and Training 18

  11. RGM Operations Community Relations Jerry Finisie Sustainability Manager September 12, 2017

  12. Community Relations Social Responsibility Strategy Purpose Enriching the lives of stakeholders through investing in Sustainable development of communities Objective Supporting the business while maintaining the social license to operate Engagement Continuous building and maintaining sustainable relationships based on trust SSM Multi Stakeholder Platform • Risk & Impact Protocols Management Local procurement Centralization of suppliers Local employment Compliance community hiring proc. Catalyze sustainable Structured Partnership Community development Development Strong emphasis on sustainability SIA Extension social Consultations Saramacca license Inclusion traditional requirements Performance Ensure our ability to deliver through talent development and building systems 20

  13. Highlights 2017 initiatives 22

  14. RGM Operations Corporate Affairs & Government Relations Sharmila Jadnanansing Legal and Corporate Affairs Manager September 12, 2017

  15. Government Engagement at the Highest Level Aug. 2016: Saramacca deal Aug. 2015: Inauguration luncheon Aug 11, 2017: Meeting Presidential Palace – meeting July 2016 2013: Signing of Second Amendment 23

  16. Rosebel’s Contribution to Suriname Rep. of Sur. 5% shareholder: at the AGM represented by the Vice President and the Minister of Natural Resources 24

  17. Direct Financial Contribution to the Republic of Suriname 2016 Direct Financial Contribution: $46 M Direct Financial Contribution 2009 - 2016 Income Tax/Stat. & Cons. Fee Payroll Tax $167.4 M 180 $165.1 M $/Millions $8.8 M Income Tax Royalties 160 12.6 M $136.9 M 140 Payroll Tax 120 $107.2 M Dividends $92.1 M 100 80 $53.4 M 60 $46 M $37.4 M Royalties 40 $24.6 M 20 0 2009 2010 2011 2012 2013 2014 2015 2016  2016 Direct Financial Contribution to the Republic of of Suriname: $46 Million  Approx. 23% increase compared to 2015  Excluding dividend: 2016 dividend will be paid in 2017  Due to higher gold production and higher gold prices 1. Amounts are rounded to whole U.S. Dollars. 2. Income Tax includes Statistics & Consent Fee of $300,000. In 2015 there was no Income Tax payment made to the 25 Government. 3. Royalties in-kind are calculated at the market gold price.

  18. Local Content  Total spent in 2016: ~ $265 Suriname Suppliers vs. Non-Suriname million Suppliers 2005 - 2016  Suriname Suppliers: ~ $162 million ~ 250 $/Millions 61% 200  Non-Suriname Suppliers: $103 million ~ 38% 150  100 Local expenditures include power costs 50  Power costs 2016: $24 million (PPA1 0 and PPA2) 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Suriname Suppliers Non-Suriname Suppliers Business with over 350 Local Suppliers 26

  19. Economic Value for Suriname: 2005 – 2016 27

  20. RGM Operations Supply Chain Procurement, Logistics, Warehouse Ritesh Agarwal Supply Chain Manager September 12, 2017

  21. Supply Chain Strategy and Road Map 2020 - Develop Best Skills - Adaptable to changes 2019 - Flexible (internal & external changes) - Develop Sustenance - Deliver world-class - TPM implementation results in cost reduction, - Revisit processes working capital mtg., and 2018 - Look for Innovations product availability - Continuous improvements - Service Levels - Benchmark against / projects best in class - Productivity - Develop Commercial intelligence - Stretch KPIs - Housekeeping – 5s - Enhance market Analysis & Trends 2017 - Improve competency - Apply TCO concepts - Cost optimization - Basics Right - Automation & Digitalization - Restructuring - Communication - Procedures - Simplification - Quick wins 29

  22. Major Categories Sourcing Plan • Renegotiated with existing service providers for food supplies, equipment hire, labor hire, security services and explosives supplies. • Tendered out for employee bussing services and introduced turnkey performance based contract with 25% better rates than existing. Cyanide prices also reduced by 25% for 2018 contract. • Maintain prices in 2018 for OTR tires, Nitric acid and Lime irrespective of raw materials prices. • To initiate tender for fuel and lubricants in Oct 2017. CAT parts supply contract under discussion with CAT dealer. • Total reduction in AISC on negotiated contracts : 28 $/Oz year on year • Negotiations with other suppliers underway. 30

  23. RGM Operations 2017 LOM $1200/Oz Gold Price Base Michel Payeur/Remon van de Paal Technical Services Manager /Finance Controller September 12, 2017

  24. RGM Site Layout 32

  25. Mineral Resource Update June 30th, 2017 Tonnage Grade Contained Metal Category (000 t) (g/t Au) (000 oz Au) Measured 31,402 0.7 676 Indicated 275,710 1.0 8,649 Total M&I 307,112 0.9 9,325 Inferred 84,866 1.0 2,667  Mineral Resources estimated at average cut-off grades between 0.19 g/t Au and 0.50 g/t Au  Mineral Resources estimated using an average long-term gold price of US$1,500 per ounce 33

  26. Resources Waterfall All pits MII – 100% basis 1,500 $/oz; Pit constrained 34

  27. Resource Distribution Pit & Material Types Resource Distribution per Material Type Resource Distribution per Pit 100% 35% 90% 30% 80% % MII Resources % MII Resources 25% 70% 60% 20% 50% 15% 40% 30% 10% 20% 5% 10% 0% 0% Saprolite Transition Hard Rock Material Types Measured & Indicated Resources Inferred Resources Pit/Orebodies Measured & Indicated Resources Inferred Resources 35

  28. 2016-2017 Model Updates Models Type (Flag) Flag 5 => all the rest 36

  29. Resource Models Comparison – Overall Trends Previous estimates using ID3 underestimated tonnage, slightly overestimated grade and underestimate ounces New models using OCK-Luc globally show more tonnage, same grade and more ounces, which matches closer to historical reserve reconciliation Figure Model Comparison Within Same Pit Shells Pits Tonnes Grade Ounces J Zone 37% 1% 38% Pay Caro 10% 4% 15% Mayo 21% -16% 2% Roma East 87% 1% 88% Royal Hill 16% 6% 23% Rosebel 29% 5% 36% Total 18% 1% 19% 37

  30. 2015-2016 Drilling – Included in 2017 Resource Update Main Targets Resources increased by 245 kt @ 0.8 g/t => 6 koz Resources increased by 500 kt @ 0.7 g/t => 13 koz Resources increased by 2.4 Mt @ 0.9 g/t => 68 koz Resources increased by Resources increased by 120 kt @ 0.67 g/t => 3 koz 11.0 Mt @ 1.0 g/t => 362 koz Resources increased by 4.2 kt @ 0.84 g/t => 113 koz Saddles and near-pit Resources 2015 drilling 38 2016 drilling increased by about 565 koz

  31. 2017 Drilling Overview In Progress KoolHoven - Jzone SADDLE => 2,500m Jzone Central - East SADDLE => 3,200m PayCaro WEST SADDLES => 9,900m PayCaro EAST East Extension => 1,200m PayCaro Central - East SADDLE => 1,200m Rosebel – Rosebella Royal Hill SADDLE => 5,600m SADDLE => 4,000m 2015 drilling 2016 drilling 39 2017 drilling

  32. RGM Reserves Update July 27 th Disclosure September 2017 TSX: IMG NYSE: IAG

  33. Mineral Reserve Update June 30th, 2017 Tonnage Grade Contained Metal Category (000 t) (g/t Au) (000 oz Au) Proven 24,356 0.7 516 Probable 90,544 1.1 3,215 Total 114,900 1.0 3,730  Mineral Reserves estimated at average cut-off grades between 0.16 g/t Au and 0.44 g/t Au  Mineral Reserves are estimated using an average long-term gold price of US$1,200 per ounce 41

  34. Reserves Waterfall All pits in production P&P – 100% basis 1,200 $/oz 42

  35. Reserve Distribution Pit & Material Types Reserve Distribution per Material Reserve Distribution per Pit 3 500 1600 1400 3 000 Gold Ounces (koz) Gold Ounces (koz) 1200 2 500 1000 2 000 800 1 500 600 1 000 400 500 200 0 - Saprolite Transition Hard Rock Material Type Pits 43

  36. Major Assumptions Mill Run Rates Material Recoveries Soft 96% Transition 94% Hard 93% Total Mill Throughput as a Function of Hard Rock Feed 14000000 12000000 Mill Throughput (tonnes) 10000000 8000000 6000000 4000000 2000000 0 55% 60% 65% 70% 75% 80% 85% 90% 95% 100% % Hard Rock 44

  37. Mine Schedule Optimization Shell Selection & Phasing Whittle pit optimization used to determine maximum net discounted cash flow Selection methods incorporate phasing into the ultimate pit shell selection to ensure maximum value – This technique is a departure from what was previously applied at RGM A dilution factor of 8% in soft, 10% in trans and 10% in rock was applied to select the optimized pit shells – Resulted in smaller pit shells due to diminished value of the blocks used to determine the optimized pit shell Apex of Worst case line selected – Practically feasible but least optimized pit shell 45

  38. Mine Schedule Optimization (Contd) Shell Selection & Phasing Apex of best case line selected – Not practically feasible but most optimized pit shell Apex of Phased case – Compromise of optimization and practicality 46

  39. Multi-Pit Blending – Money Mining (Cont.) Multi-Pit Blending – Money Mining  Detailed mine designs chosen from selected shells, with extensive use of pit phasing Pits LOM 2016 Phases LOM 2017 Phases Rosebel 2 7 Pay Caro 3 5 J-Zone 2 5 Royal Hill 1 3 Mayo 1 5 Roma West 1 1 0 1 Roma East 1 0 2 Koolhoven 1 Total 11 27 Notes: 1. Roma East not included in 2016 LOM 2. Koolhoven excluded from 2017 LOM, however prior to exclusion, had 4 phases  The mine schedule is then applied, using a multi-pit blending optimizer › The software analyzes thousands of scenarios looking at sequencing and timing of material to mine with the goal of maximizing revenue and minimizing costs › The output of this exercise is a mill feed blend with variable cut-off grades, in order to accommodate the highest value blend through the mill  Inputs include: › Mining & processing limitations (mine equipment, mill throughput, vertical rate of advance, etc.) › Financial assumptions (gold price, discount rate) 47

  40. Cut Off Grades The mine scheduling process applies variable CoG’s CoG’s are developed to allow the most optimal mill feed blend while taking into account location, time, material and mining and milling capacity LOM 2016 LOM 2017 Material CoG’s CoG’s * 0.23 0.16 Soft Transition 0.27 0.20 Hard 0.43 0.44 * Average over LOM 48

  41. Cut Off Grade Trend North Pits Pay Caro J Zone Rosebel 49

  42. Cut Off Grade Trend South Pits Mayo Royal Hill Roma East Roma West 50

  43. Dilution, Mining Loss and Adjustment Factors Dilution factors of 8% in Saprolite and 10% in Transition and Rock applied Dilution estimated at zero grade Adjustment factor of 8% in Saprolite, 10% in Transition and Rock applied to tonnes Aligned with historical reconciliation No mining loss factor applied Material Tonnage Grade Soft 8% -8% Transition 10% -10% Hard 10% -10% *Dilution, Mining Loss and Adjustment Factors result in no change to the in situ ounces 51

  44. Material Mined by Rock Type 52

  45. Production by Pit 53

  46. Mill Feed by Material Type & Ounce Production 54

  47. Mill Feed by Pit 55

  48. Opportunities Waste planning Further optimization of dump plans and schedules Mining costs optimized allocation VRA (Vertical Rate of Advancement) Focus: Dewatering, Blasting, Wall Control and Mining Quality. Further Life-of-fleet optimization and coordination with satellite pit integration 56

  49. LOM 2017 Financials September 2017 TSX: IMG NYSE: IAG

  50. LOM 2017 Financial Key Assumptions Mining costs based on 2017 Budget costs (new CLA & SRD devaluation) EURORESSOURCES Royalty (IMG now has 90% participation) Regional Exploration, Corp Admin and Group Charges not considered ARO estimate for End of Mine disturbance End of Mine redundancy costs included in model Recoveries SR 96%, TR 94%, HR 93% ( previously TR 95%, HR 94% ) Dilution applied, SR 8%, TR 10%, HR 10% 58

  51. Highlights  LOM 2017 = 3.7 Moz Reserve  Compared to like-for-like 2016 2.4 Moz Reserve  LOM 2017 weighted average total Cash cost = $ 707 / oz *  LOM 2017 weighted average total AISC = $ 923 / oz *  Koolhoven pit not included (2.5MT Hard Rock @ 1.3 g/t)  Overman was in (internal) LOM-2016, it is not in LOM-2017  Saramacca has not been considered * as per Technical Report NI 43-101 – September 5, 2017 59

  52. Rosebel’s LOM * vs. Gold Price Assumptions Rosebel’s LOM* vs. Gold Price Assumptions 2030 1450 2028 1400 2026 1350 Ending)* )* S$/oz) LOM (Year Endin 2024 1300 ice (US$ old Pric 2022 1250 Gold 2020 1200 2018 1150 2016 1100 Jan 15, Jun 15, Jan 15, June 15, Jan 15, June 15, Jan 15, June 15, 2014 2014 2015 2015 2016 2016 2017 2017 LOM Gold Price *Internal Life of Mine Plans shown do not necessarily correlate with Reserve and Resource Statements in their coinciding year. 60

  53. Tonnes Mined comparison LOM 2014, LOM2016 (internal) and LOM 2017 Tonnes Mined (millions) 80 70 60 50 40 30 20 10 - 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 LOM-2014 LOM-2016 (internal) LOM-2017 61

  54. Tonnes Milled Comparison LOM 2014, LOM2016 (internal) and LOM 2017 Tonnes Milled (millions) 14 12 10 8 6 4 2 - 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 LOM-2014 LOM-2016 (internal) LOM-2017 62

  55. Ounces Produced comparison LOM 2014, LOM2016 (internal) and LOM 2017 Ounces produced (‘000) 400 350 300 250 200 150 100 50 - 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 LOM-2014 LOM-2016 (internal) LOM-2017 63

  56. RGM Operations Mine Operations Saran Sankar Operations Manager September 12, 2017

  57. Strategy Alignment IAMGOLD Strategy Sustainability Cost Optimization Step change Innovation Productivity Safety 65

  58. 10,000 meters 10.0 12.0 14.0 16.0 18.0 • 2.0 4.0 6.0 8.0 - Meters Drilled & Tonnes Blasted Tonnes Blasted 8% above the forecast 2017. Jan'15 12.6 Feb'15 12.1 Mar'15 13.0 Apr'15 15.2 May'15 12.5 June'15 11.5 July'15 10.5 Aug'15 11.1 Sep'15 12.7 Meters Drilled Oct'15 16.6 Nov'15 14.0 Dec'15 8.8 Jan'16 13.7 Feb'16 12.9 Mar'16 13.1 Apr'16 13.4 May'16 12.3 June'16 11.8 July'16 14.0 Aug'16 13.1 Sep'16 9.7 Oct'16 13.3 Nov'16 11.6 10 20 30 40 50 60 70 - Dec'16 11.2 Jan'17 11.1 Jan'15 37 Feb'17 9.5 Feb'15 38 Mar'17 11.4 Mar'15 43 Apr'17 11.7 Apr'15 44 May'17 10.3 May'15 June'17 9.7 37 June'15 32 • • July'15 28 Aug'15 46 efficiency. 10 by improving drill productivity and equipment Reduced the total operating drill fleets from 13 to Meters drilled 0.2% above the forecast 2017. Sep'15 43 Oct'15 53 Tonnes Blasted Nov'15 53 Dec'15 29 Jan'16 48 Feb'16 45 Mar'16 47 Apr'16 51 May'16 45 June'16 44 July'16 65 Aug'16 53 Sep'16 41 Oct'16 63 Nov'16 53 Dec'16 53 Jan'17 45 Feb'17 42 Mar'17 46 Apr'17 49 66 May'17 43 June'17 36

  59. Mine Productivities • 23.1% Improvement in drill productivity in terms Drill Productivities (EHM/NOH) of Equivalent hard meters/NOH and 6.1% 24 increase in terms of gross meters/NOH 23 compared to 2015. 22 21 • Real time monitoring and reporting of drill 20 parameters to ensure optimum performance. 23 19 23 22 22 22 22 22 22 22 • Multiple trials with various drill consumables to 18 20 20 19 19 19 17 19 19 identify the optimum combinations for higher 19 19 19 19 18 18 18 18 18 18 18 18 17 16 penetration rates and reduced costs. 17 15 • Focus on pattern quality improvements and drainage plans. 6030 Loading Unit Productivities (MT/NOH) • 6.6% improvement in 6030 Loading units 1600 productivity compared to 2015. 1500 • Selective deployment of production shovels 1400 with proper face preparations. • 1567 Improvement in blast fragmentation and muck 1300 1547 1546 1540 1529 1517 1511 1501 1491 1484 1480 1481 1480 1472 1458 1448 1425 1428 1423 profile. 1414 1403 1397 1401 1390 1382 1363 1200 1356 1344 1320 1298 • Pattern specific monitoring and analysis of 1100 average loading time based on blast design parameters. 1000 67

  60. Mine Productivities Tire Life (NOH) 2015 -2017 YTD 5500 • 5% improvement in 777 and 7% improvement in 5000 785 tire life compared to 2015. 4500 4000 • Haul road management and reduced rolling 5297 resistance. 3500 5008 4679 • Optimum strut pressure 3000 4026 • Payload management 3824 3641 • Inflation pressure of tires. 2500 2000 2015 2016 2017 (YTD) 777 785 Linear (777) Linear (785) Hauling Unit Productivities(MT/NOH) 260 • 0.9% Improvement in hauling unit 240 productivities compared to 2015. 220 200 • 180 Truck allocation based on material type. 249 227 228 226 225 225 • 219 216 216 Implementation of side bars in trucks. 160 215 214 213 215 214 215 215 215 214 213 213 211 213 213 205 201 202 201 199 197 • Payload management using Wenco fleet 140 175 management. 120 • Operator training. 100 68

  61. Key Performance Indicators Drill Yield (T/Meter) • Drill Yield 15.2% higher compared to 2015 driven 50 by narrower pit operations in Mayo and Rosebel pits. 45 40 • Conversion to 8/10 meter benches in all the pits. 48 48 46 46 46 35 • Realized 10-15% expansion of drill patterns with 44 44 43 42 42 42 41 40 optimum design parameters. 39 38 37 38 37 37 36 36 36 36 36 30 35 35 • Fragmentation and heave models generated to 33 33 32 31 identify further opportunities with pattern 25 expansion. Jan'15 Feb'15 Mar'15 Apr'15 May'15 June'15 July'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Mar'16 Apr'16 May'16 June'16 July'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 Mar'17 Apr'17 May'17 June'17 Powder Factor (Kg/Tonnes) • 7% reduction in powder factor with 6% reduction 0.350 in explosive consumption compared to Budget 0.330 2017. 0.310 0.290 0.270 0.336 0.250 • 0.333 Design optimization based on blast requirements 0.325 0.322 0.316 0.312 0.313 0.304 0.297 0.230 0.293 0.284 0.284 0.281 0.283 0.282 and efficient charging practices with quality 0.278 0.272 0.272 0.268 0.264 0.263 0.210 0.239 control. 0.229 0.229 0.226 0.224 0.224 0.221 0.190 0.210 0.185 0.170 0.150 Jan'15 Feb'15 Mar'15 Apr'15 May'15 June'15 July'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Mar'16 Apr'16 May'16 June'16 July'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 Mar'17 Apr'17 May'17 June'17 69

  62. Key Performance Indicators Tonnes Moved/Mining Manhour 50 45 40 • Average tonnes moved per man hour in mining is 35 7.2% higher compared to 2015. 30 25 44 20 39 37 37 37 37 37 37 37 35 35 34 34 34 33 34 33 33 32 32 33 33 31 32 32 15 30 30 29 29 • 28 16% reduction in average man-hours in mining 10 compared to 2015. 5 0 Jan'15 Feb'15 Mar'15 Apr'15 May'15 June'15 July'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Mar'16 Apr'16 May'16 June'16 July'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 Mar'17 Apr'17 May'17 June'17 Tonnes Moved/Litre of Fuel 1.80 • 0.9% reduction in tonnes moved per unit fuel consumption driven by 4.8% reduction average 1.60 tonnes moved and 1.4% increase in fuel 1.40 consumption. 1.20 1.66 1.60 1.51 1.37 1.00 1.35 1.33 1.33 1.32 1.30 1.29 1.26 1.27 1.27 1.27 1.24 1.24 1.22 1.22 1.23 1.21 1.22 1.21 1.18 1.16 1.16 1.16 1.17 1.16 • Higher hard rock ore planned from the far pits 1.13 1.08 0.80 including Mayo and Rosebel contributed majorly. • Deeper pits with longer hauls to dumps. 0.60 Jan'15 Feb'15 Mar'15 Apr'15 May'15 June'15 July'15 Aug'15 Sep'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Mar'16 Apr'16 May'16 June'16 July'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 Mar'17 Apr'17 May'17 June'17 70

  63. $10.00 $12.00 • • $2.00 $4.00 $6.00 $8.00 $- Operational Costs – Drilling bulk explosives. with advance initiation system and high energy Selective pattern expansion driven by trials below compared to 2015. Drilling costs on tonnes blasted is 0.003% Jan'15 $5.44 Feb'15 $6.26 Mar'15 $6.36 Apr'15 $5.03 May'15 $5.52 June'15 $6.13 Drilling Costs ($/Meter) July'15 $4.64 Aug'15 $6.57 Sep'15 $4.51 Oct'15 $3.78 Nov'15 $6.09 Dec'15 $3.71 Jan'16 $5.40 Feb'16 $4.36 Mar'16 $4.66 Apr'16 $6.35 May'16 $6.68 June'16 $5.78 July'16 $4.68 Aug'16 $4.34 Sep'16 $8.53 Oct'16 $11.08 $0.05 $0.07 $0.09 $0.11 $0.13 $0.15 $0.17 $0.19 $0.21 $0.23 $0.25 Nov'16 $4.26 Dec'16 $9.51 Jan'17 $5.43 Feb'17 $8.34 Jan'15 $0.19 Mar'17 $6.97 Feb'15 $0.20 Apr'17 $5.37 Mar'15 $0.19 May'17 $7.26 Apr'15 $0.17 June'17 $7.71 May'15 $0.19 June'15 $0.22 July'15 $0.18 • Aug'15 $0.16 Drilling Costs ($/T) Sep'15 $0.13 0.02% below compared to the budget 2017. Unit drilling costs of RGM drills ($/meter) is Oct'15 $0.12 • Nov'15 $0.16 Dec'15 $0.11 fleet in operations to reduce unit costs. Consumable management and optimum Jan'16 $0.16 Feb'16 $0.13 Mar'16 $0.13 Apr'16 $0.17 May'16 $0.18 June'16 $0.15 July'16 $0.10 Aug'16 $0.11 Sep'16 $0.20 Oct'16 $0.23 Nov'16 $0.09 Dec'16 $0.20 Jan'17 $0.14 Feb'17 $0.19 Mar'17 $0.17 Apr'17 $0.13 71 May'17 $0.17 June'17 $0.21

  64. $0.05 $0.10 $0.15 $0.20 $0.25 $0.30 $0.35 $0.40 $- • Operational Costs – Blasting & Tire compared to 2015. Tire Costs ($/tonne moved ) is 12.3% higher Jan'15 $0.36 Feb'15 $0.34 Mar'15 $0.28 Apr'15 $0.32 May'15 $0.31 June'15 $0.37 July'15 $0.34 Aug'15 $0.26 Blasting Costs ($/T) Sep'15 $0.29 Oct'15 $0.27 Nov'15 $0.27 Dec'15 $0.30 Jan'16 $0.30 Feb'16 $0.29 Mar'16 $0.29 Apr'16 $0.27 May'16 $0.24 June'16 $0.24 July'16 $0.21 Aug'16 $0.18 $0.05 $0.10 $0.15 $0.20 $0.25 Sep'16 $0.26 $- Oct'16 $0.16 Nov'16 $0.20 Dec'16 $0.24 Jan'15 $0.20 Jan'17 $0.23 Feb'15 $0.10 Feb'17 $0.23 Mar'15 $0.13 Mar'17 $0.27 Apr'15 $0.12 Apr'17 $0.20 May'15 $0.08 May'17 $0.31 June'15 $0.16 June'17 $0.21 July'15 $0.11 Aug'15 $0.10 • • • • • • Sep'15 $0.06 Quality control and charging accuracy initiatives. Trials with 225g boosters. heave. with aid of blast modelling for fragmentation and Multiple trials with Advance initiation systems ground, for efficient and effective blast designs. Extensive baseline studies on sonic velocities of 10-15% expansion of drill patterns. the budget 2017. compared to 2015 and 14 % below compared to Blasting costs ($/tonne blasted ) is 21.2% below Oct'15 $0.12 Nov'15 $0.06 Tire Costs($/T) Dec'15 $0.14 Jan'16 $0.08 Feb'16 $0.08 Mar'16 $0.10 Apr'16 $0.12 May'16 $0.15 June'16 $0.09 July'16 $0.14 Aug'16 $0.09 Sep'16 $0.09 Oct'16 $0.08 Nov'16 $0.09 Dec'16 $0.05 Jan'17 $0.10 Feb'17 $0.12 Mar'17 $0.08 Apr'17 $0.16 72 May'17 $0.16 June'17 $0.14

  65. $0.10 $0.15 $0.20 $0.25 $0.30 $0.35 $0.40 $0.45 $0.50 $0.55 • Higher productivities (1%) and lower fuel cost • (8.5%) contributed majorly. Operational Costs – Load & Haul 4% reduction in hauling costs compared to 2015. Jan'15 $0.44 Feb'15 $0.34 Mar'15 $0.46 Apr'15 $0.35 May'15 $0.37 June'15 $0.44 July'15 $0.39 Aug'15 $0.32 Loading Costs ($/T) Sep'15 $0.31 Oct'15 $0.38 Nov'15 $0.32 Dec'15 $0.36 Jan'16 $0.26 Feb'16 $0.28 Mar'16 $0.30 Apr'16 $0.33 May'16 $0.35 June'16 $0.32 July'16 $0.38 Aug'16 $0.30 Sep'16 $0.34 Oct'16 $0.30 $0.02 $0.04 $0.06 $0.08 $0.10 $0.12 $0.14 Nov'16 $0.34 $- Dec'16 $0.33 Jan'17 $0.33 Feb'17 $0.33 Jan'15 $0.12 Mar'17 $0.36 Feb'15 $0.07 Apr'17 $0.33 Mar'15 $0.11 May'17 $0.50 Apr'15 $0.09 June'17 $0.30 May'15 $0.10 June'15 $0.11 • Higher productivities (6.6%) and lower fuel cost • 11.9% reduction in loading costs compared to July'15 $0.13 (8.5%) contributed majorly. 2015. Aug'15 $0.11 Hauling Costs ($/T) Sep'15 $0.09 Oct'15 $0.08 Nov'15 $0.08 Dec'15 $0.08 Jan'16 $0.06 Feb'16 $0.06 Mar'16 $0.07 Apr'16 $0.07 May'16 $0.07 June'16 $0.09 July'16 $0.09 Aug'16 $0.07 Sep'16 $0.09 Oct'16 $0.07 Nov'16 $0.09 Dec'16 $0.08 Jan'17 $0.08 Feb'17 $0.08 Mar'17 $0.08 Apr'17 $0.09 73 May'17 $0.04 June'17 $0.13

  66. Mine Maintenance - Strategic Objective Cost – Capital Personal Health & Safety Equipment Development Availability Spares Increase focus on the Refocus on safety with Increase the equipment Extend Engine life & work execution of regular inspection on systems knowledge of Contamination control planned maintenance work areas and the floor personal with through mid life repair improve personal safety and quality control. specialized training awareness through caterpillar.. 74

  67. x 100000 • $10 $15 $20 $25 $30 $35 $40 Maintenance Costs budget 2017. compared to 2015 and 5% below compared to 1.1% higher maintenance costs per tonne moved Jan'15 $34 Feb'15 $32 Mar'15 $30 Apr'15 $30 May'15 $31 Overall Maintenance Costs June'15 $28 July'15 $36 Aug'15 $28 Sep'15 $29 Oct'15 $35 Nov'15 $32 Dec'15 $21 Jan'16 $28 Feb'16 $31 Mar'16 $30 Apr'16 $32 May'16 $34 June'16 $33 July'16 $23 Aug'16 $35 Sep'16 $35 Oct'16 $24 $0.10 $0.20 $0.30 $0.40 $0.50 $0.60 $0.70 $0.80 Nov'16 $29 $- Dec'16 $27 Jan'17 $30 Jan'15 $0.60 Feb'17 $33 Feb'15 $0.56 Mar'17 $25 Mar'15 $0.53 Apr'17 $27 Apr'15 $0.48 May'17 $31 May'15 $0.54 June'17 $30 June'15 $0.55 Maintenance Costs ($/T) July'15 $0.66 • • • Aug'15 $0.45 Sep'15 $0.51 management. maintenance and major component change Quality compared to budget 2017. below compared to 2015 and 4.8% below Overall average maintenance costs is 4% the total mining budget 2017. driver for mine operations contributing 33% of Mine Maintenance is one of the major cost Oct'15 $0.56 Nov'15 $0.55 Dec'15 $0.56 Jan'16 $0.45 Feb'16 $0.61 improvements Mar'16 $0.57 Apr'16 $0.68 May'16 $0.64 June'16 $0.70 July'16 $0.45 Aug'16 $0.61 Sep'16 $0.70 Oct'16 $0.41 Nov'16 $0.50 in Dec'16 $0.45 Jan'17 $0.54 preventive Feb'17 $0.67 Mar'17 $0.43 Apr'17 $0.49 75 May'17 $0.57 June'17 $0.60

  68. RGM Operations Mill Operations John Grignon Operations Manager September 12, 2017

  69. Mill Heat Map 77

  70. 2017 Highlights Operational Total Tonnes Milled YTD 6.4M vs 5.2M B CHALLENGES / FOCUS 1.20  Millions Transition reporting to soft rock feeders 1.00  Increased oversize hard rock  0.80 Limitation to hard rock capacity Tonnes Milled 0.60  Fine fragmentation of transition 0.40  Optimization of secondary crusher CSS and 0.20 Grizzly tine gap width 0.00  Liner design – emphasis on lifters – modify face Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec angle, reduced shell plate height, reduced weight 2016 2017 Forecast Budget Total Ounces Produced 156K VS 159K B FOCUS 40  Thousands Increased run rate 35  Increased HR ratio 30  Optimized gravity operating parameters / grinds 25  Optimize CN control system / pH control 20 Ounces  Optimize elution / acid wash performance – 15 maximize CIL performance 10  Reduced gold inventory 5  Reduced solution losses - Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2016 2017 Forecast Budget 78

  71. Performance Highlights Mill Recovery YTD 93.5 vs 94.5 B CHALLENGES / FOCUS  97% Carbon calcium loadings – impact on carbon 96% activity 95%  Lime – product quality and storage 94% Mill Recovery  93% Comminution grinds / Gravity performance 92% 91%  Optimization of secondary grinding – ES / BM3 90%  Maximize acid wash batches / reduced carbon 89% inventory for quicker turnover 88%  Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Gravity concentrators – optimized operational set 2016 2017 Forecast Budget points – ore source Mill Availability 95.9 vs 94.5 B CHALLENGES / FOCUS 100%  Standard work practices / Equipment availability 90%  Timeline between shutdown – (5) weeks – not all 80% 70% critical path processes make the distance Mill Availability 60% 50%  Continued focus on behavior models, visual 40% 30% boards & short interval controls 20%  Defined roles and responsibilities – RACI 10%  Re-design components for longer run intervals – 0% Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec SAG chute / idler quality 2016 2017 Forecast Budget 79

  72. Cost Highlights Mill Total Costs ($/tonne) CHALLENGES / FOCUS 9.00  Labor costs – utilization of manpower 8.00  Reagents costs – suppliers / negotiated contracts 7.00  Process set point controls – set point stability Costs ($/tonne) 6.00 5.00 4.00  Visual boards, short interval controls and defined 3.00 roles and responsibilities 2.00  Source quality reagent, negotiate best case 1.00 purchase terms 0.00 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec  Loop tuning and plant stability – expert system 2016 2017 Forecast Budget tuning Power Costs ($/tonne milled) 4.40 vs 4.63 B CHALLENGES / FOCUS 4.50  Maximized comminution run rates / hard rock 4.00 ratio 3.50 3.00  Maximized performance of solar plant Costs ($/tonnes) 2.50 2.00  Loop tuning and plant stability – expert system 1.50 1.00 tuning 0.50  Clean and coat solar panels 0.00 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2016 2017 Actual Forecast Budget 80

  73. 2017 Highlights – Grinding Survey - CEET 2 Rosebel LOM - Base Case 2000 100% BASE CASE 1800 90%  1SAG + 3BM – NO PC 1600 80% Plant Throughput (TPH) 1400 70% 1200 60%  100% HR = 5.4Mtpa 1000 50% 800 40% 600 30% CEET2 400 20%  Grinding survey 200 10% completed Feb 2017 0 0% 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 at 75% SAG shell liner life – 30 row Target Capacity (6.8 Mt) 1SAG+3BM Existing PC(3")+1SAG+3BM %Hard Rock  100% HR = 7.8-8.2 Mtpa BASE CASE to CEET2 + Pebble Crusher Upgrade + Powerflex Drive + 30 Row SAG shell SAG Drive Media 5” to 5.5” + SAG Liner + Secondary Crusher Configuration Pebble Secondary CAPEX = <20M$ Crusher Crusher 81

  74. 2017 Highlights – Advanced Process Control (Expert System) SAG power draw at SAG Bearing target (5600 kW) pressure stable Stockpile inventory OK? Stable Yes feeding Stable Controls by Feeders are C.L Expert available? Yes SAG Bearing SAG power draw pressure unstable below target Expert is online? Yes > 90% of time at target Lost HR Unstable C.L feeders 82

  75. 2017 Highlights – Laboratory PAL (pulverize and leach)  PAL  Improved sample representation, 300g vs 30g fire assay  Reduced analytical costs, $1.00/determination vs fire assay $3.00/determination  Single PAL machine 416/ determinations/day with current (2) PAL machines at 832 determinations – (3) Units installed and operational  Estimated direct cost saving of $60k/month Weekly QAQC review – Laboratory & MTS ensure quality performance 83

  76. 2017 High Return Projects – Secondary Crusher  Secondary Crusher  Project start date February 2015  Construction start date June 2016  Commissioning date November 2016 as scheduled.  Budget 14M$ completed at 13.8M$  Secondary Crusher Optimization  Optimized Grizzly tine sizing 62mm  Optimized crusher closed side setting 69mm  SAG hard rock throughput at optimized >45% hard rock at 12.5Mtpa run rate vs pre-secondary crusher at 30% hard rock at 12.5Mtpa run rate  Secondary Crusher Next Steps  Optimized maintenance and operational standards through visual boards and short interval controls – “behavior models”  Internal grinding surveys at various secondary crusher closed side settings / bypass sizing through grizzly 84

  77. 2017 High Return Projects – SAG Liners Design  SAG Grate Design  Increase slot relief from 10.5° to 12° - reduced blinding = reduced pooling  Double wide configuration sees 16 pieces vs 32 = reduced installation time  SAG Shell Design  Increase HR by 1%  At 0.4g/t advantage over soft  Decrease face angle -2.5°  At 12Mtpa  Decrease shell plate 1”  = 1,500 oz/year Decrease set weight 23t  = 1.8M $/year Increase bucket capacity 85

  78. Mill 2017 Opportunities / Innovation  SECONDARY PEBBLE CRUSHING  Pebble crusher optimization – additional grinding surveys with increased and decreased feed size following operation with phase 1 & CEET2 complete to determine:  Maintain current installation Pebble Crush #1 CV6  Increase capacity with single stage crushing  Move to secondary pebble crushing CV4 addition with product transfer to x3 Ball CV8 Mills or BM3 Pebble Crush #2 CV3 PUMP CV2 86

  79. 2017 Mill Opportunities Opportunity Description Potential Impact PSA (pressure swing adsorption) – Oxygen enrichment to leach allowing for Target = 1% recovery / 1 increased recovery of 1.5% cash flow 3.5M$ / year Target = 5% CN savings / Cyanide reduction – point addition strategy / chemistry influence on set point 2 0.6M$ / year Mill Maintenance – standard work practices, “We Tjaring Waka Processes” and Target = 5% maintenance 3 material upgrades including ceramic wear technologies, slurry pump impeller reduction = 1M$ / year design and liner specifications. savings Target = -10% solution Elution Circuit – continued optimization of both elution and acid wash processes 4 losses 1M$ / year CIL – installation of hollow shaft air distribution - minimize agitator breakage – Target = +0.5% recovery / 5 improve air distribution. Cash flow 1.5M$/ year Grind optimization – Increase BM3 capacity +30%, conversion to trommel from Target = +0.5% recovery / 6 static screen / Install gravity tail header for optimized distribution to secondary Cash flow 1.5M$/ year grinding. 87

  80. 2017 Achievements  95.9% overall plant availability  93.5% recovery at high hard rock ratio and increased run rates.  44% hard rock run ratio at 12.7Mtpa run rate  At increased transition ratio (48%) and reduced soft rock ratio (8%)  Expert system control and >90% at full SAG power / maximum bearing pressure with SAG auto speed control  Costs: the Mill has seen forecast cost reductions for 2017 including  Grinding media – $0.6M – continued focus on expert system optimization and secondary grinding operating strategy to maintain maximized circulating loads is seeing advantage which represent a significant portion of the savings  Secondary Crusher operational / optimized for maximized SAG HR capacity 88

  81. RGM Operations Finance Remon van de Paal Finance Controller September 12, 2017

  82. Accomplishments  Reduced like-for-like AISC from > $1,500 to < $1,000/oz  Created foundation for long-term Rosebel future  Productivity improvements through Business Excellence  Significant Workforce rationalization  Immense improvement in Labor relations  No strikes, no indexation to inflation, no guaranteed bonuses, reduced absenteeism, 30% performance-based pay  Substantial plant debottlenecking has greatly improved hard rock throughput  Disciplined Capital Management  58% reduction in Operational Working Capital since December 2013  Acquisition of Saramacca and completion of maiden NI 43-101 Resource  Empowerment and talent development; Strong focus on Nationals 90

  83. Rosebel’s Cost structure Transformation AISC-trend Rosebel Gold Mines N.V. 1,691 1,604 1,525 1,669 1,407 1,338 1,332 1,316 1,411 1,245 1,207 1,200 1,266 1,249 1,250 1,085 1,250 1,250 1,093 1,044 1,185 1,158 968 1,123 1,153 1,070 1,063 1,045 988 975 964 939 934 884 In 2011/2012 Rosebel’s 2013 to 2017 projected AISCs were expected Gold average to increase to over $1,600/oz ( red line - consensus estimates for gold Budget AISC 2013-2017 (undiluted) spot prices were approximately $2,000/oz). Starting in 2013, significant measures were implemented aimed at Budget AISC 2015-2019 (undiluted) reducing costs which resulted in an AISCs of ~$1,300/oz ( orange line ) Realized AISC Current internal estimates for AISCs are approximately below $1,100/oz Budget AISC 2017-2021 ( green line ). The 2017 LOM has a weighted average AISC of $923 over LOM LOM AISC 2017 (2018-2022) ($1,050 over 2018-2022; blue line ). This is excluding Saramacca. 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 91

  84. Tonnes Mined Million Tonnes Mined - Rosebel Gold Mines N.V. 90 78.0 80 77.5 75.2 74.6 74.1 72.7 71.4 69.6 70 66.5 65.2 64.8 64.5 63.2 63.2 63.7 62.8 64.1 60 63.5 63.1 61.3 58.4 57.2 56.7 50 50.3 Budget 2013-2017 49.8 Budget 2015-2019 46.0 40 Realized Budget 2017-2021 30 LOM 2017 (2018-2022) 20 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 92

  85. Significant increase Mill throughput 16 Million Tonnes Milled 14 13.1 12.5 12.6 12.5 12.5 12.5 12.3 13.0 12 11.5 12.8 12.1 12.5 12.3 11.2 11.0 11.8 10.7 9.8 10 9.0 Budget 2013-2017 10.2 9.4 8.0 9.3 8.0 Budget 2015-2019 8.2 7.2 8 Realized With essentially the same Mill 6 Budget 2017-2021 configuration (3BM + 1SAG), Mill LOM 2017 (2018-2022) throughput has increased from 4 7.2MT @ 83% HR (B2013) to 9.4MT at 91% HR (LOM 2017) 2 100 % Hard Rock Milled 91 90 90 83 85 0 83 84 81 80 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 72 68 70 67 63 60 56 54 53 51 50 42 43 51 37 40 32 39 38 30 30 29 20 24 20 10 - 93 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022

  86. Gold produced koz Gold produced - Rosebel Gold Mines N.V. 381 378 402 348 328 354 318 342 308 311 290 294 317 316 284 289 302 285 279 279 276 236 242 233 259 259 Budget 2013-2017 (undiluted) LOM 2017 is excluding Saramacca. The production Budget 2015-2019 (undiluted) profile beyond 2019 will significantly improve once Realized Saramacca will be incorporated. Budget 2017-2021 (diluted) LOM 2017 (2018-2022) 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 94

  87. Continued Reduction Mine costs: 15% below 2013/2014 2013 - 2017 Mining Cost per tonne Mined by area $2.36 2.50 $2.34 2.50 Continued $2.15 reduction in $1.97 mining costs by $1.95 2.00 2.00 over $0.35/t from 40% 27% 16% $2.34/t to $1.97/t 25% 54% 1.50 1.50 Despite +$0.15/t 32% 25% increase due to 34% 31% 30% increase HR 1.00 1.00 from 17% to 50% 29% (HR costs are 20%/t higher) $0.35 0.50 $0.34 52% 0.50 50% 38% $0.24 30% $0.09 17% Despite +$0.15/t 0.00 - increase due to 2013A 2013A 2014A 2014A 2015A 2015A 2016A 2016A 2017A 2017A Soft Rock % 1.27 0.93 0.59 0.32 0.49 RC Drilling Trans Rock % 0.68 0.73 0.74 0.61 0.50 Hard Rock % 0.39 0.70 0.82 1.01 0.98 Approx. $0.30/t of Grade Control 0.02 0.05 0.18 0.19 0.18 Geology 0.02 0.02 0.03 0.03 0.03 reduction due to Engineering 0.06 0.07 0.06 0.05 0.04 lower fuel costs MIne Other 0.40 0.54 0.45 0.36 0.39 Mine Maintenance 0.63 0.59 0.58 0.56 0.56 Approx. $0.35/t Haul 0.65 0.55 0.39 0.32 0.36 improvement due Load 0.16 0.16 0.10 0.08 0.08 to cost control & Blasting 0.28 0.25 0.23 0.22 0.20 productivity Drilling 0.12 0.14 0.13 0.15 0.14 initiatives Productivity gain 0.09 0.24 0.34 0.35 Total $/ t Mined 2.34 2.36 2.15 1.95 1.97

  88. Continued Reduction Mill costs: 15% below 2013 2013 - 2017 Milling Cost per tonne Mined by area (excl. Power) Continued $5.13 reduction in $4.93 $4.95 5.00 $4.73 mining costs by $4.40 over $0.50/t 25% 16% 7% since 2014 42% 4.00 38% (2014 is used as reference as 50% 3.00 Ball Mill 3 was 51% 45% only installed 33% mid 2013) 34% 2.00 Despite $0.50/t $0.84 increase due to 1.00 44% 33% 30% 29% $0.37 increase HR 24% $0.11 (HR costs are - 50%/t higher) 2013A 2013A 2014A 2014A 2015A 2015A 2016A 2016A 2017A 2017A Soft Rock % mix 2.16 1.85 1.25 0.76 0.29 Trans Rock % mix 1.72 1.63 2.20 2.39 2.20 About $0.15/t of Hard Rock % mix 1.24 1.45 1.49 1.57 1.93 reduction like for Other Milling Cost 0.51 0.48 0.46 0.44 0.45 like cost base General Maintenance 0.40 0.43 0.42 0.35 0.33 Laboratory & Metallurgy 0.19 0.20 0.24 0.24 0.13 Approx. $0.85/t Instrumentation & Electrical 0.08 0.08 0.10 0.08 0.07 improvement Power Distribution 0.08 0.09 0.10 0.09 0.10 due to cost Tailings System 0.16 0.12 0.11 0.08 0.07 control and Reagents 1.85 1.72 1.73 1.71 1.62 productivity Thickening & Carbon regen. 0.15 0.14 0.12 0.09 0.14 initiatives Leaching and CIP 0.12 0.15 0.16 0.11 0.09 Grinding & Gravity 1.37 1.30 1.32 1.26 1.22 Crushing & Ore storage 0.20 0.19 0.19 0.24 0.17 Total $ / Ton Milled 5.13 4.93 4.95 4.73 4.40 Productivity Gain since 2014 0.11 0.37 0.84

  89. Workforce Rationalization Rosebel Employees Tonnes mined (M) Number of Employees 1,400 70 64.1 64 63.5 63.1 61.3 57.2 1,200 60 53.1 1,000 50 990 983 973 937 800 40 825 691 600 30 675 492 487 469 459 460 458 426 400 20 200 10 74 74 70 65 50 43 43 0 0 2011A 2012A 2013A 2014A 2015A 2016A 2017F Hourly Staff Expat Tonnes Mined 97

  90. Mine Production 80.0 4.0 70.0 3.5 64.1 63.5 61.8 61.4 57.2 60.0 3.0 Mine production Mtpa 50.0 2.5 40.0 2.0 31.5 30.0 1.5 20.0 1.0 10.0 0.5 0.0 - 2012A 2013A 2014A 2015A 2016A 2017A-6M Soft rock (Mtpa) 24.9 33.3 21.9 23.9 10.4 7.7 Trans rock (Mtpa) 22.3 17.8 20.1 21.8 32.4 8.2 Hard rock (Mtpa) 9.9 10.2 19.8 17.8 21.3 15.6 Total mined (Mtpa) 57.2 61.4 61.8 63.5 64.1 31.5 Strip Ratio 3.1 3.6 3.6 3.5 3.4 3.4 Mining Unit Cost ($/t mined) 2.12 2.33 2.36 2.15 1.95 1.97 98

  91. Mill Production 16.0 8.0 13.1 14.0 7.0 12.8 12.6 12.3 12.3 12.1 12.0 6.0 10.0 5.0 8.0 4.0 6.3 Kt 6.0 3.0 4.0 2.0 2.0 1.0 0.0 0.0 2011A 2012A 2013A 2014 2015A 2016A 2017A-6M Soft Rock 3.8 3.9 5.2 4.9 3.1 2.0 2.3 Transitional Rock 6.5 6.3 4.1 4.3 5.5 6.4 0.9 Hardrock 1.7 2.6 3.0 3.8 3.7 4.2 2.1 Total Processed 12.1 12.8 12.3 13.1 12.3 12.6 6.3 Milling Costs ($/t) 3.97 4.31 5.29 4.93 4.95 4.73 4.40 Power Costs ($/t) 2.62 3.05 1.85 2.52 2.01 1.90 2.15 G&A Costs ($/t) 2.51 2.82 3.34 2.43 2.43 1.82 1.85 99

  92. Operating Cost Trend 350 300 278 273 252 252 250 227 227 200 $ M 150 116 100 50 0 2011A 2012A 2013A 2014A 2015A 2016A 2017A-6M G&A Cost 32.3 36.1 41.3 31.7 29.9 22.9 11.8 Power Cost 35.9 39.1 22.8 32.9 24.7 24.0 13.7 Milling Cost 51.2 55.2 65.3 64.4 60.8 59.5 28.0 Mining Cost 107.1 121.4 143.3 148.9 136.7 125.2 62.3 Total Operating Cost 227 252 273 278 252 227 116 100

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend