An Inside Look at Electric Reliability
2018 Electric Reliability Report
Stockton, California December 13, 2019
An Inside Look at Electric Reliability 2018 Electric Reliability - - PowerPoint PPT Presentation
An Inside Look at Electric Reliability 2018 Electric Reliability Report Stockton, California December 13, 2019 Delivering Safe and Reliable Electric Service Steven Calvert P.E. Senior Manager, Electric System Reliability Agenda Safety and
Stockton, California December 13, 2019
Together, Building a Better California
Momentary Outage Sustained Outage
An outage of 5 minutes or An outage greater than 5 less in duration. minutes in duration.
Planned Outage Major Event
Outages which are customer A set of outages which occurred during
a specific time and location and which where the company has combined, exceeds historically expected provided notice to the customer.
day (as defined in IEEE 1366-2012)
Average cumulative minutes of sustained power Average number of sustained power interruptions interruptions during the year during the year Average duration of each sustained power Average number of momentary power interruptions interruptions during the year during the year *AIDI – Average cumulative minutes of sustained *AIFI – Average number of sustained power power interruptions during the year on a specific interruptions during the year on a specific circuit. circuit.
11
12
What is PG&E’s system-wide reliability story?
impacted by severe storms and wildfires
experience outages since 2009 - SAIDI
How will PG&E’s reliability improve?
hardening investments
158.0 157.2 141.7 131.0 116.1 108.4 95.9 108.9 113.4 126.3 0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 180.0 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIDI: Planned & Unplanned Outages (Excludes Major Event Days)
1.173 1.207 1.097 1.130 1.070 0.966 0.871 1.021 0.958 1.079 0.000 0.200 0.400 0.600 0.800 1.000 1.200 1.400 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
SAIFI: Planned & Unplanned Outages (Excludes Major Event Days)
134.7 130.3 129.3 115.9 108.5 112.2 110.1 106.7 118.3 117.0 0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
CAIDI: Planned & Unplanned Outages (Excludes Major Event Days)
158.0 157.2 141.7 131.0 116.1 108.4 95.9 108.9 113.4 126.3
75.0 85.0 95.0 105.0 115.0 125.0 135.0 145.0 155.0 165.0 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018
(Incl. Planned Outages and Excl. MEDs and ISO Outages)
(Includes Planned Outages, Excludes Major Event Days and ISO Outages)
13
Chart 104: Division Reliability - AIDI Indices Chart 123: Division Reliability - AIFI Indices
Chart 142: Division Reliability - MAIFI Indices Chart 161: Division Reliability - CAIDI Indices
14
15
PG&E’s poorly performing electric circuits in 2018, by the amount of time the average PG&E customer experienced a sustained outage (an outage that lasts more than five minutes). Table 62: AIDI Worst Performing Circuit for 2018
16
PG&E’s poorly performing electric circuits in 2017, by the number of times the average PG&E customer experienced a sustained outage (an outage that lasts more than five minutes). Note that no Sacramento circuits met this criteria. Table 61: AIFI Worst Performing Circuit for 2018
System Map Stockton Division Area Map
Completed 2018 Identified as a poor performing circuit in 2014, significant work including the installation of new protection devices and resolving reliability issues identified through detailed circuit inspections. A 25+% improvement in reliability circuit performance was recorded in 2018.
Number of customers on the circuit:
Completed 2016, 2017 & 2018 44 TripSavers (TS) were installed in Stockton Division. This new technology protection device replaced traditional fuses and had the functionality to “test” back in after an intermittent fault. This would reduce the number of sustained outages for customers beyond new TS.
Number of customers: about 10,000
Planned for 2020-21 This project will replace bare wire with insulated conductor, increase strength requirements for poles, install system automation/protection equipment, and convert overhead (OH) equipment to underground (UG) in targeted locations. This would minimize the risk of an asset failure that could result in a fire ignition.
Number of customers on the circuit:
Planned for 2019-20 This program will install various switching and protection devices equipped with Supervisory Control and Data Acquisition (SCADA) technology. This would minimize the customer disruption impacts of a Public Power Shut Off (PSPS) event.
Number of customers: about 30,000