NUC-001-1 Reliability Standard Update April 8, 2008 Keith ONeal - - PowerPoint PPT Presentation

nuc 001 1 reliability standard update
SMART_READER_LITE
LIVE PREVIEW

NUC-001-1 Reliability Standard Update April 8, 2008 Keith ONeal - - PowerPoint PPT Presentation

NUC-001-1 Reliability Standard Update April 8, 2008 Keith ONeal Office of Electric Reliability Overview Introduction FERCs role in establishing mandatory Reliability Standards Processing Reliability Standard filings at


slide-1
SLIDE 1

NUC-001-1 Reliability Standard Update

April 8, 2008 Keith O’Neal Office of Electric Reliability

slide-2
SLIDE 2

2

Overview

  • Introduction
  • FERC’s role in establishing

mandatory Reliability Standards

  • Processing Reliability Standard

filings at FERC

  • RM08-3 Update
slide-3
SLIDE 3

3

FERC’s Role

  • Approve the standard as mandatory
  • Remand the standard back to the

ERO

  • Approve the standard as

mandatory, and direct changes to the ERO on the standard

  • Standards must be just,

reasonable, not unduly discriminatory and in the public interest

slide-4
SLIDE 4

4

Processing Reliability Standard Filings

  • Commission has processed most

Reliability Standard filings to-date by a rulemaking, but can also process them through a FERC order

  • Typically 30 days allow ed for

comments

  • Commission may modify direction

from NOPR in final rule

  • Rehearing requests allow ed 30 days

after final rule issued

slide-5
SLIDE 5

5

RM08-3 Update

  • Public comments w ill be due 30

days from publication in the Federal Register

  • Final rule issued after all

comments are considered

  • Not final until the rehearing

process is completed