QNP Green Hydrogen to Ammonia Project QNP and Project Intro - Feb 2020 Text Text Commission 235 ktpa AN 2000 QNP facility near Moura, Queensland BHP 50/50 Glencore ownership 90 employees Ammonium nitrate products Prill


slide-1
SLIDE 1

QNP Green Hydrogen to Ammonia Project

QNP and Project Intro - Feb 2020

slide-2
SLIDE 2

Text

  • Text

Commission 2000 BHP Glencore 90 employees 235 ktpa AN

QNP facility near Moura, Queensland Ammonium nitrate products – “Prill” (left) & “Emulsion”

50/50

  • wnership

$25-35m local economy

slide-3
SLIDE 3

QNP - Location

  • Approximately 160km east of Gladstone
  • Southern end of the coal rich Bowen Basin

Mines Serviced by QNP

CUR URRAGH

slide-4
SLIDE 4

QNP Process – opportunity for additional hydrogen and ammonia production

Ammonia Nitric Acid Ammonium Nitrate Purchased ammonia Gas

QNP Production Process

Customers

slide-5
SLIDE 5

QNP Green Ammonia Project Concept

H2O Air

  • New plant - hybrid wind,

solar, battery (≈ 200 to 300MW)

  • Approximately 30MW at

80% capacity for electrolysis

  • 60GWh/yr for existing QNP

facility

  • New plant - electrolysis

producing 3500 t/year of hydrogen (H2)

  • New plant – liquid ammonia

(NH3) 20,000 t/year,

  • H2 storage to absorb

renewable variability & provide continuous feed to NH3 plant

  • Existing QNP ammonium nitrate (AN)

facility, output used for mining explosives within Queensland

  • Currently using NH3 from on site gas

steam reformation, which is at capacity – additional 20kT/y sourced from 3rd parties

  • Concept is to displace 3rd party supply

using new renewables/hydrogen/ammonia plant

New plant New plant Existing QNP Facility

5

Blue Chip Customers

slide-6
SLIDE 6

Expected Final Asset Ownership & Relationships

ASSET OWNERSHIP

PPA

MW/MWh

Supply of capacity & energy to both the new H2 and NH3 components, as well as to the existing QNP ammonia nitrate facility.

6

H2O Air Expertise

Electricity supply Commercials, operations, plant integration PM, engineering, delivery

slide-7
SLIDE 7
  • Blue Chip Australian owners
  • Experienced chemicals facility operator
  • Providing grid support services
  • Renewable energy supply
  • 20 ktpa Ammonia sensible scale up step
  • Established offtake and customers
  • 20 ktpa Ammonia sensible scale up step
slide-8
SLIDE 8

Green Hydrogen to Ammonia

Some knowledge from ARENA supported feasibility underway:

  • 1
  • 2
  • 3
  • 4
  • Interruptible loads

OEM inexperienced with dynamic

  • peration of large electrolysers
  • Significant early step to commercialisation

Scalability and learning to:

  • take the next step to decarbonise QNP supply

chain

  • Take the next step to scale renewables based

hydrogen export potentially via ammonia

  • Balancing risk and scale

Large green hydrogen project, small in relation to the opportunity - the right size to demonstrate scalability.

  • Learn as enablers emerge

Build capability in projects beyond studies. Potential enablers include:

  • Lower cost Renewables
  • Carbon pricing
  • Natural gas markets
  • Hydrogen markets
slide-9
SLIDE 9

Potential Business Case Levers

Initial Business Case Feasibility Engineering Network Costs Energy Costs Grant Funding Concessional Finance Tax Treatment Final Business Case NPV Business Case Lever

slide-10
SLIDE 10

Hydrogen Industry Development

End game:

  • New Renewables based hydrogen export industry
  • Decarbonise existing industries
  • Viable Business Case
  • Funding cost
  • Risk – proven commercial

application, established performance characteristics

  • Counterparty risk and

contractual arrangements

  • .
  • Electricity Cost
  • Operate plant to electricity

market signals

  • Unique operating and

contractual arrangements required

  • Transmission

Connecting the electricity generation to the market – what to transmit?

  • Capital Cost
  • Capital/operating trade-
  • ffs – renewables

intermittency/storage

  • Scale
  • R&D – technology,

manufacturing costs, response times.

slide-11
SLIDE 11

Project stages

11

Concept

  • Prepare initial ARENA

application

  • +-50% accuracy –

Class 1

FEED

  • +-10% accuracy –

Class 3

  • Finalise

renewables supply and financing

Feasibility

  • +-30 accuracy –

Class 2a

  • Financing and

renewables analysis

Delivery

  • Construction and

Installation

  • Commissioning

Aug 2019

  • ARENA -

Feasibility Study Funding approval

  • QNP Board

approval to proceed

Q1 2020

  • ARENA -Full

Project Funding approval sought

  • QNP Board

approval

Q4 2020

  • ARENA -Full

Project Funding confirmation

  • Board sanctions

– QNP and Neoen

Q4 2022 – Q1 2023

  • Commence
  • perations

6 months 8-15 months 24 months