ALW Airport Master Plan Update Planning Advisory Committee Meeting #4 November 2, 2016 Meeting Agenda 1. Study Progress 2. Review of PAC #3 3. Recommended Improvements 4. Implementation Plan 5. Next Steps Study Progress Airport Layout


slide-1
SLIDE 1

Planning Advisory Committee Meeting #4 November 2, 2016

ALW Airport Master Plan Update

slide-2
SLIDE 2

Meeting Agenda

  • 1. Study Progress
  • 2. Review of PAC #3
  • 3. Recommended Improvements
  • 4. Implementation Plan
  • 5. Next Steps
slide-3
SLIDE 3

Study Progress

  • What do we

have?

Inventory

  • What demand

do we expect?

Forecasts*

  • Can we meet

expected demand?

Facility Requirements

  • What do we

need to change to meet demand?

Alternatives

  • How do we pay

for these changes?

Capital Improvement Plan

  • What will these

changes look like?

Airport Layout Plan*

Stakeholder Coordination & Public Outreach * Denotes FAA-approved Element

PAC Public

slide-4
SLIDE 4

Review of PAC #3

  • Regional jet as future aircraft
  • Transition to single runway operation after

taxiway reconstruction project

  • Reconfigure passenger terminal
  • Develop GA facilities
  • Expand Airport maintenance and storage

Runway 2-20 Critical Aircraft (Future) Aircraft Design Characteristics: Aircraft Type: Regional Jet Transport FAA ARC/TDG: C-III; TDG 2 Approach Speed: ±138 Knots Wingspan: ±85' Length: ±103'9" Tailheight: 31.9' Maximum Weight: 82,700 Pounds Seating Configuration: 77 to 88 Passengers Cockpit to Main Gear (CMG) 42.0' Wheelbase 37.5' Main Gear Width (MGW) 17.0'

76 103’9” 85’ 85’138 Knots

slide-5
SLIDE 5

Facility Needs – Improvement Overview

Close Runway 7/25 Taxiway A Improvements Terminal Improvements GA Expansion SRE, O&M Expansion Parking Lot Expansion Property Acquisition

slide-6
SLIDE 6

Facility Needs – Taxiway System

  • New locations
  • Remove Runway

02 in-line

  • Resolve

geometry issues

  • New naming

system

slide-7
SLIDE 7

Facility Needs – SRE Building Expansion Options

  • Snow removal,
  • perations, and

maintenance in one location

  • Additional room for

snow removal equipment

slide-8
SLIDE 8

Facility Needs – New North GA Hangar Options

  • Reserved area for

GA development

  • Large ground lease

hangar parcel

  • Executive hangars
  • T-Hangars
slide-9
SLIDE 9
  • Phased expansion
  • Accommodate

greater flight frequency

  • Accommodate

larger aircraft

Facility Needs – Air Carrier Apron

slide-10
SLIDE 10

Facility Needs – Auto Parking

  • Phased expansion
  • Started in 2016
  • Capacity and level of

service to meet average day and peak-month demands.

slide-11
SLIDE 11

Passenger Terminal Option 1

slide-12
SLIDE 12

Passenger Terminal Option 2

slide-13
SLIDE 13

Facility Needs – New GA Terminal Building

  • Remove Building 117
  • Private

redevelopment

  • Potential to

accommodate other users

slide-14
SLIDE 14

Development Alternative 1 (Constrained)

slide-15
SLIDE 15

Development Alternative 2 (Unconstrained)

slide-16
SLIDE 16

ARFF Truck $700k Taxiway A $12m RPZ Property Ph. 1 $150k

2017-2018

slide-17
SLIDE 17

Close 7/25 $100k Parking Lot Ctd. $1.2m

2019-2022

GA Apron Rehab $1.4m SRE & Ops Building $1.7m

slide-18
SLIDE 18

Parking Lot Ctd. $500k Passenger Terminal $2.3m

2023-2027

GA Apron Rehab $4.4m Air Carrier Apron $2.4m RPZ Property Ph. 2 $1.3m

slide-19
SLIDE 19

Parking Lot, Signage, Road $500k

2027-2037

2/20 Rehab $4.4m Jet A Fuel Storage $300k GA Development $TBD Aviation Development $TBD Non-Aviation Development $TBD

slide-20
SLIDE 20

Next Steps

Final Public Open House Tonight FAA Forecast Approval Mid-November ALP Submittal November / December Project Closeout Spring 2017