ALW Airport Master Plan Update Planning Advisory Committee Meeting #4 November 2, 2016 Meeting Agenda 1. Study Progress 2. Review of PAC #3 3. Recommended Improvements 4. Implementation Plan 5. Next Steps Study Progress Airport Layout


  1. ALW Airport Master Plan Update Planning Advisory Committee Meeting #4 November 2, 2016

  2. Meeting Agenda 1. Study Progress 2. Review of PAC #3 3. Recommended Improvements 4. Implementation Plan 5. Next Steps

  3. Study Progress Airport Layout Alternatives • How do we pay Forecasts* Plan* • What do we • Can we meet for these have? expected • What demand • What do we changes? • What will these demand? do we expect? need to change changes look to meet like? Capital demand? Facility Improvement Inventory Requirements Plan Stakeholder Coordination & Public Outreach * Denotes FAA-approved Element PAC Public

  4. Review of PAC #3 Runway 2-20 Critical Aircraft (Future)  Regional jet as future aircraft  Transition to single runway operation after taxiway reconstruction project  Reconfigure passenger terminal Aircraft Design Characteristics:  Develop GA facilities Aircraft Type: Regional Jet Transport FAA ARC/TDG: C-III; TDG 2 85’138 Knots Approach Speed: ±138 Knots  Expand Airport maintenance and storage 85’ Wingspan: ±85' 103’9” Length: ±103'9" Tailheight: 31.9' Maximum Weight: 82,700 Pounds Seating Configuration: 76 77 to 88 Passengers Cockpit to Main Gear (CMG) 42.0' Wheelbase 37.5' Main Gear Width (MGW) 17.0'

  5. SRE, O&M Parking Lot Facility Needs – Improvement Overview Expansion Expansion Taxiway A Terminal Property GA Expansion Improvements Improvements Acquisition Close Runway 7/25

  6. Facility Needs – Taxiway System  New locations  Remove Runway 02 in-line  Resolve geometry issues  New naming system

  7. Facility Needs – SRE Building Expansion Options  Snow removal, operations, and maintenance in one location  Additional room for snow removal equipment

  8. Facility Needs – New North GA Hangar Options  Reserved area for GA development  Large ground lease hangar parcel  Executive hangars  T-Hangars

  9. Facility Needs – Air Carrier Apron  Phased expansion  Accommodate greater flight frequency  Accommodate larger aircraft

  10. Facility Needs – Auto Parking  Phased expansion  Started in 2016  Capacity and level of service to meet average day and peak-month demands.

  11. Passenger Terminal Option 1

  12. Passenger Terminal Option 2

  13. Facility Needs – New GA Terminal Building  Remove Building 117  Private redevelopment  Potential to accommodate other users

  14. Development Alternative 1 (Constrained)

  15. Development Alternative 2 (Unconstrained)

  16. 2017-2018 ARFF Truck $700k RPZ Property Ph. 1 $150k Taxiway A $12m

  17. 2019-2022 Parking Lot Ctd. $1.2m GA Apron Rehab $1.4m SRE & Ops Building $1.7m Close 7/25 $100k

  18. 2023-2027 Parking Lot Ctd. $500k GA Apron Rehab $4.4m Passenger Terminal RPZ Property Ph. 2 Air Carrier Apron $2.3m $1.3m $2.4m

  19. 2027-2037 Parking Lot, Signage, Road $500k 2/20 Rehab $4.4m GA Development Jet A Fuel Storage $TBD $300k Aviation Development $TBD Non-Aviation Development $TBD

  20. Next Steps Final Public Open House Tonight FAA Forecast Approval Mid-November ALP Submittal November / December Project Closeout Spring 2017

  21. Questions and Comments Thank you!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.