Alternatives Presentation PROJECT LOCATION TH 22, Br 30 Meeting - - PowerPoint PPT Presentation

alternatives presentation project location
SMART_READER_LITE
LIVE PREVIEW

Alternatives Presentation PROJECT LOCATION TH 22, Br 30 Meeting - - PowerPoint PPT Presentation

Huntington BRO 1445(35) Bridge 30 on TH 22 (Camels Hump Road) Over Brush Brook Alternatives Presentation PROJECT LOCATION TH 22, Br 30 Meeting Outline Purpose of the Meeting Structures Section Re-organization Existing bridge


slide-1
SLIDE 1

Huntington BRO 1445(35) Bridge 30 on TH 22 (Camels Hump Road) Over Brush Brook Alternatives Presentation

slide-2
SLIDE 2

PROJECT LOCATION

TH 22, Br 30

slide-3
SLIDE 3

Meeting Outline

  • Purpose of the Meeting
  • Structures Section Re-organization
  • Existing bridge deficiencies
  • Alternatives considered
  • Summary and recommendation
slide-4
SLIDE 4

Purpose of Meeting

  • Present the alternatives that we have considered
  • Explain the constraints to the project
  • Help you understand our approach to the project
  • Provide you with the chance to ask questions.
  • Provide you with the chance to voice concerns
  • Build consensus for the recommended alternative
slide-5
SLIDE 5

Accelerated Bridge Program

  • Began in January 2012
  • Bridges are deteriorating faster than we can fix them
  • Accelerated Bridge Construction (ABC) is key
  • Impacts to property and resources is minimized
  • Standard details repeated on many projects
  • Shift from individual projects to programmatic approach
  • Accelerated Project Delivery
  • Goal of 2 year design phase for ABP (5 years

conventional)

  • Goal of 25% of projects into Accelerated Bridge Program
slide-6
SLIDE 6

Project Initiation & Innovation Team

  • Part of re-organization in January 2012
  • Currently team of 5
  • All projects will begin in the PIIT
  • Very efficient process
  • Look for innovative solutions whenever possible
  • Involved until Project Scope is defined
  • Hand off to PM to continue Project Design phase
slide-7
SLIDE 7

Phases of Development

Project Definition Project Design Construction Project Funded Project Defined Contract Award

Identify resources & constraints Evaluate alternatives Public Participation Build Consensus

  • Quantify areas of

impact

  • Environmental

permits

  • Develop plans,

estimate and specifications

slide-8
SLIDE 8

Project Background

  • Priority 25 in the Town Highway Bridge Program
  • The structure is owned and maintained by the Town
  • TH 22 (Camels Hump Road) is a Class 3 Town Highway
  • Existing bridge is a single-span rolled beam bridge with a

timber deck

  • Span of 27 feet and width of 12.5 feet
  • The structure was built in 1925 (87 years old)
  • Bridge is structurally deficient and has a Federal

sufficiency rating of 18.9 (out of 100) -

slide-9
SLIDE 9

Project Background (Cont)

  • Traffic Data

TRAFFIC DATA 2015 2035 AADT 270 290 DHV 55 60 ADTT 10 15 %T 4.7 5.3

slide-10
SLIDE 10

Description of Terms Used

Beams (Superstructure) Deck Abutment (Substructure) Bridge Rail

slide-11
SLIDE 11

EXISTING BRIDGE DEFICIENCIES

Deficiencies

  • The bridge width is substandard
  • The bridge does not have adequate hydraulic capacity and has scour issues
  • The bridge and approach rails do not meet the current standard

Inspection Report Information (Based on a scale of 9) Deck Rating 4 Poor Superstructure Rating 7 Good Substructure Rating 5 Fair Channel Rating 6 Satisfactory

slide-12
SLIDE 12

Bridge Width and Railing Issues

slide-13
SLIDE 13

North Abutment - Upstream

slide-14
SLIDE 14

North Abutment - Downstream

slide-15
SLIDE 15

South Abutment

slide-16
SLIDE 16

Existing Site Conditions

  • Bridge Width (Face-Face Rail) = 12.5’
  • Design Speed Limit = 20 mph (Posted speed)
  • Posted for 16,000 weight limit (timber deck)
slide-17
SLIDE 17

Layout Showing Constraints

slide-18
SLIDE 18

Alternatives

  • 1. Replace deck and rehabilitate superstructure and

substructure

  • 2. Superstructure replacement and rehabilitate substructure
  • 3. Full replacement (phased construction)
slide-19
SLIDE 19

Alternative 1 – Rehabilitate

  • New timber deck (same width)
  • Address scour at abutments
  • Minor improvements to roadway (guardrail, etc)
  • Extends life approximately 15 years
  • Still need temporary bridge to maintain traffic
  • Other substandard features will not be addressed-
slide-20
SLIDE 20

Alternative 2 – Superstructure Replacement

  • Concrete superstructure replacement (same width)
  • Address scour at abutments
  • Minor improvements to roadway (guardrail, etc)
  • Extends life approximately 30 years
  • Still need temporary bridge to maintain traffic
  • Other substandard features will not be addressed
slide-21
SLIDE 21

Alternative 3 – Full Replacement

  • Completely new bridge
  • Width would meet required standards
  • Alignment improved slightly (flatter curves)
  • Longer span to address hydraulic issues
  • Long term (80 year) solution
  • Use phase construction to maintain traffic-
slide-22
SLIDE 22

Alternative 3 – Typical Section

slide-23
SLIDE 23

Alternative 3 – Layout

slide-24
SLIDE 24

Alternative 3 – Phasing

slide-25
SLIDE 25

Alternatives Matrix

Alt 1 Alt 2 Alt 3 Rehabilitation Rehabilitation w/ Super Replacement Full Replacement Temporary Bridge $65,000 $65,000 $0 Construction w/ CE and Contingencies $293,000 $463,000 $639,000 Preliminary Engineering $41,000 $65,000 $114,000 Right of Way $40,000 $40,000 $50,000

Total Cost $374,000 $568,000 $803,000

Town Share

$18,700 (5%) $28,400 (5%) $80,300 (10%)

Design Life (years) 15 30 80 Project Development Duration 3 years 3 years 3 years Construction Duration 6 months 6 months 6-8 months

slide-26
SLIDE 26

Conclusion and Recommendation

  • Recommend Alternative 3 – Full bridge replacement
  • Long term (80 year) solution
  • Addresses all sub-standard features-
slide-27
SLIDE 27

Questions