Alternatives Presentation PROJECT LOCATION Meeting Outline Purpose - - PowerPoint PPT Presentation

alternatives presentation project location meeting outline
SMART_READER_LITE
LIVE PREVIEW

Alternatives Presentation PROJECT LOCATION Meeting Outline Purpose - - PowerPoint PPT Presentation

Barton Village BHF 0286(5) Bridge 20 on VT Route 16 (TH 2) Over Crystal Lake Outlet Alternatives Presentation PROJECT LOCATION Meeting Outline Purpose of the Meeting Structures Section Re-organization Existing bridge deficiencies


slide-1
SLIDE 1

Barton Village BHF 0286(5) Bridge 20 on VT Route 16 (TH 2) Over Crystal Lake Outlet Alternatives Presentation

slide-2
SLIDE 2

PROJECT LOCATION

slide-3
SLIDE 3

Meeting Outline

  • Purpose of the Meeting
  • Structures Section Re-organization
  • Existing bridge deficiencies
  • Alternatives considered
  • Summary and recommendation
slide-4
SLIDE 4

Purpose of Meeting

  • Present the alternatives that we have considered
  • Explain the constraints to the project
  • Help you understand our approach to the project
  • Provide you with the chance to ask questions
  • Provide you with the chance to voice concerns
  • Build consensus for the recommended alternative-
slide-5
SLIDE 5

Accelerated Bridge Program

  • Began in January 2012
  • Bridges are deteriorating faster than we can fix them
  • Accelerated Bridge Construction (ABC) is key
  • Impacts to property and resources is minimized
  • Standard details repeated on many projects
  • Shift from individual projects to programmatic approach
  • Accelerated Project Delivery
  • Goal of 2 year design phase for ABP (5 years

conventional)

  • Goal of 25% of projects into Accelerated Bridge Program
slide-6
SLIDE 6

Project Initiation & Innovation Team

  • Part of re-organization in January 2012
  • Currently team of 5
  • All projects will begin in the PIIT
  • Very efficient process
  • Look for innovative solutions whenever possible
  • Involved until Project Scope is defined
  • Hand off to PM to continue Project Design phase
slide-7
SLIDE 7

Phases of Development

Project Definition Project Design Construction Project Funded Project Defined Contract Award

Identify resources & constraints Evaluate alternatives Public Participation Build Consensus

  • Quantify areas of

impact

  • Environmental

permits

  • Develop plans,

estimate and specifications

slide-8
SLIDE 8

Description of Terms Used

Beams (Superstructure) Deck Abutment (Substructure) Bridge Rail

slide-9
SLIDE 9

Project Background

  • Priority 22 in the Town Highway Bridge Program
  • The structure is owned and maintained by the Town
  • VT Rte 16 (TH 2) is a Class 1 Town Highway
  • Existing bridge is a two-span granite slab bridge
  • Two spans of 9 feet (24’ overall) and width of 30 feet
  • The age of the structure is unknown
  • Bridge is structurally deficient and has a Federal

sufficiency rating of 67.6 (out of 100) -

slide-10
SLIDE 10

Project Background (Cont)

  • Traffic Data

TRAFFIC DATA 2015 2035 ADT 4,100 4,300 DHV 540 560 ADTT 340 500 %T 6.5 9.3

slide-11
SLIDE 11

EXISTING BRIDGE DEFICIENCIES

Deficiencies

  • The granite slabs are in fair condition and have an unknown capacity
  • The bridge does not have adequate hydraulic capacity
  • The bridge rail is substandard

Inspection Report Information (Based on a scale of 9) Deck Rating 5 Fair Superstructure Rating 5 Fair Substructure Rating 5 Fair

slide-12
SLIDE 12

Bridge Looking North

slide-13
SLIDE 13

Bridge Looking South

slide-14
SLIDE 14

Looking North Along Approach

slide-15
SLIDE 15

Looking South along Downstream Fascia

slide-16
SLIDE 16

Looking Upstream

slide-17
SLIDE 17

Existing Site Conditions

  • Bridge Width (Face-Face Rail) = 30.9’
  • Design Speed Limit = 30 mph (Posted speed)
  • No Postings for Weight Restriction
  • Overhead Utilities present along eastern fascia
slide-18
SLIDE 18

Layout Showing Constraints

  • Right of Way (4 rods)
  • Historic properties (not bridge)
  • Overhead Utilities
slide-19
SLIDE 19

Alternatives

  • 1. Superstructure replacement
  • 2. Full replacement

Note that other alternatives considered in the Scoping Report are not shown in this presentation

slide-20
SLIDE 20

Bridge Typical Same for Both Alternatives

slide-21
SLIDE 21

Superstructure Replacement

  • Replace superstructure
  • Remove pier but leave abutments to retain fill
  • 30’ wide rail to rail
  • Superstructure set on “sleeper slabs” behind abutments
  • Maintain existing centerline of bridge
  • Maintain approximate vertical grade of bridge
  • Projected 30 year design life
  • Minor hydraulic improvement
slide-22
SLIDE 22

Superstructure Replacement - Layout

slide-23
SLIDE 23

Superstructure Replacement - Profile

slide-24
SLIDE 24

Full Bridge Replacement

  • Complete Bridge replacement
  • 43’ span w/ substructure on steel H piles
  • 30’ width between face of rail
  • Maintain existing centerline of bridge
  • Maintain approximate vertical grade of bridge
  • Long term (80 year) solution
slide-25
SLIDE 25

Full Replacement - Layout

slide-26
SLIDE 26

Full Replacement - Profile

slide-27
SLIDE 27

Methods to Maintain Traffic

Temporary Bridge

  • One-way would only be possible
  • Traffic congestion due to traffic lights
  • Environmental & Property Impacts
  • High cost

Phased Construction

  • Traffic congestion due to traffic lights
  • Much longer construction phase
  • Safety concerns

Short-term bridge closure with detour

  • Recommended method to be discussed further
slide-28
SLIDE 28

ABC with Bridge Closure Option

  • Bridge 20 to be closed for 28 days (maximum)
  • Allow 24/7 construction during bridge closure
  • Contract incentives/dis-incentives to encourage contractor
  • Community would have input on time of closure (between

June 1 and September 1)

  • State will be responsible for detour route
  • Public Outreach to provide advance notice for planning
  • Local share will be cut in half (10% reduced to 5%)-
slide-29
SLIDE 29

Proposed Detour Route

A-B Thru Route = 0.4 miles A-B Detour Route = 0.8 miles Added Miles = 0.4 miles End-End = 1.2 miles

slide-30
SLIDE 30

Accelerated Bridge Construction Examples

  • We have been using ABC methods to build bridges since

2007 on approximately 20 projects.

  • The following slides show some examples of past projects
slide-31
SLIDE 31

Accelerated Bridge Construction

Driven steel piles with precast concrete cap for abutment

slide-32
SLIDE 32

Accelerated Bridge Construction

The first of three Precast Concrete Caps being placed

slide-33
SLIDE 33

Accelerated Bridge Construction

Precast concrete Abutment in place and ready for Superstructure

slide-34
SLIDE 34

Accelerated Bridge Construction

Precast Concrete NEXT Beam lifted into place

slide-35
SLIDE 35

Accelerated Bridge Construction

The second NEXT Beam being placed

slide-36
SLIDE 36

Accelerated Bridge Construction

Three NEXT Beams in place with the final unit ready

slide-37
SLIDE 37

Accelerated Bridge Construction

Precast Bridge Unit (PBU) delivered to site

slide-38
SLIDE 38

Accelerated Bridge Construction

Precast Bridge Unit (PBU) lifted onto abutments

slide-39
SLIDE 39

Accelerated Bridge Construction

Precast Bridge Units (PBUs) connected together

slide-40
SLIDE 40

Alternatives Matrix Note

  • The “Do Nothing” and several rehabilitation alternatives

were considered in the Scoping Report that are not shown in the following matrix. Refer to the Scoping Report for that information.

  • Since the proposed detour route crosses bridge 58 which

has load restrictions, we assume that these projects will be coordinated as the development process advances. Funding for the design of Bridge 58 is planned in the very near future.

slide-41
SLIDE 41

Alternatives Matrix

  • Super. Replacement w/

Short term closure Full Replacement w/ Short term closure

Construction w/ CE and Contingencies

$691,831 $1,309,014

Preliminary Engineering

$159,653 $201,387

Right of Way

$0 $0

Total Cost

$851,485 $1,510,400

Town Share

$42,574 (5%) $75,520 (5%)

Design Life (years)

30 80

Project Development Duration

3 years 3 years

Construction Duration

2 months 6 months

Closure Duration

2 weeks 4 weeks

slide-42
SLIDE 42

Conclusion and Recommendation

  • Full Bridge Replacement using ABC & short-term closure
  • Long term (80 year) fix
  • Addresses most sub-standard features
  • Improved hydraulic performance
  • Project Development time minimized
  • Minimal mobility impacts
  • Minimal impact to environmental resources
  • Minimal impact to adjacent property owners
  • Takes advantage of reduced local share for closure--
slide-43
SLIDE 43

Questions