WELCOME STATE HIGHWAY 53 Public Involvement Meeting February 23, - - PowerPoint PPT Presentation

welcome
SMART_READER_LITE
LIVE PREVIEW

WELCOME STATE HIGHWAY 53 Public Involvement Meeting February 23, - - PowerPoint PPT Presentation

WELCOME STATE HIGHWAY 53 Public Involvement Meeting February 23, 2016 Presented by: The Oklahoma Department of Transportation NewTran Solutions and White Engineering Associates, Inc. Team Introductions NewTran Solutions Transportation


slide-1
SLIDE 1

STATE HIGHWAY 53 Public Involvement Meeting

February 23, 2016

Presented by: The Oklahoma Department of Transportation NewTran Solutions and White Engineering Associates, Inc.

WELCOME

slide-2
SLIDE 2

Team Introductions

NewTran Solutions

Transportation Engineering Services

slide-3
SLIDE 3

Purpose of This Meeting

…is to inform the public and receive input regarding the Department's proposed improvements to SH-53 from Friendship Rd. (NS-278) to S. 5th St. in the City of Comanche.

Begin Project NS-278 End Project 5th St. Bridge A NS-278 NS-279 NS-280 NS-281

N NTS

SH-53 US-81 C

  • m

a n c h e Bridge B Bridge C & E (Ped.?) Bridge D & F (Ped.?) Stephens County Friendship Rd. Bowles Rd. Sears Rd.

slide-4
SLIDE 4

Project Development Process

Gather Information Develop Conceptual Alternatives Gain Public Input

Today

Identify Problems

slide-5
SLIDE 5

Purpose of The Project

  • Improve Roadway Safety and Multimodal Mobility
  • Upgrade Roadway Geometry and Intersection Sight-Distance to

current design standards.

  • Replace deteriorated sidewalk in Comanche.
  • Replace Deficient Bridges
  • Add Shoulders
  • Add Curb & Gutter in town
  • Mitigate high-frequency collision locations
  • Bowles Road (NS-280)
  • Sears Road (NS-281)
  • S. 8th Street
  • Improve safe ingress/egress at school
slide-6
SLIDE 6

Identify Problems & Gather Information

slide-7
SLIDE 7

Existing Conditions

  • Original roadway constructed in the 1926
  • Widened in 1965

80 ft. Right-of-Way (Typical) 18 ft. (Original Roadway) 80 ft. Right-of-Way (Typical) 24 ft. (Widened Roadway)

slide-8
SLIDE 8

Existing Conditions

  • Existing traffic (2012):

3,200 vehicles/day

  • Projected traffic

(2032): 4,500 vehicles/day

  • Percent truck traffic:

17%

  • Posted speed limit(s):

35MPH – 65MPH

slide-9
SLIDE 9

Existing Conditions

Obsolete roadway geometry provides inadequate sight-distance at NS-280 (Bowles Rd.)

slide-10
SLIDE 10

Existing Conditions

Dry Creek Bridge (60 ft. long by 30' wide steel beam bridge)

Includes overflow bridge

slide-11
SLIDE 11

Existing Conditions

Original bridge constructed in 1926 Widened in 1965

Dry Creek Bridge (60 ft. long by 30' wide steel beam bridge)

slide-12
SLIDE 12

Existing Conditions

Bridge near S. 7th Street in Comanche

Original bridge constructed in 1926 Reconstructed in 2008 using existing abutments 22 ft. long by 41 ft. wide steel beam bridge

No Pedestrian Protection Provided

slide-13
SLIDE 13

Existing Conditions

Bridge near S. 5th Street Bridge in Comanche

Original bridge constructed in 1926 24 ft. long by 30 ft. wide steel beam bridge

Pedestrian Protection Provided

slide-14
SLIDE 14

Existing Conditions

Roadway Culverts

slide-15
SLIDE 15

10-Year Collision History

  • Crash Types Reported

4 2 5 14 2 8 5 3 1

2 4 6 8 10 12 14 16 Rear-End (front-to-rear) Head-On (front-to-front) Right Angle Angle Turning Other Angle Fixed Object Animal Overturn/Rollover Other

slide-16
SLIDE 16

10-Year Collision History

Higher frequency collision locations (3 or more in 10 years)

6 collisions

3 collisions 4 collisions

  • S. 8th Street

30% of reported crashes at these three locations Primary collision type – Angle Turing (46%)

NS-280 NS-281

slide-17
SLIDE 17

Environmental Studies

Issues Considered

  • Relocation Impacts
  • Wetland & Stream Impacts
  • Floodplain Impacts
  • Farmland Impacts
  • Threatened & Endangered Species
  • Cultural & Archaeological Sites
  • Hazardous Waste Sites
  • Oil & Gas Sites
  • Noise Impacts
slide-18
SLIDE 18

Develop Conceptual Alternatives

slide-19
SLIDE 19

Conceptual Improvements

NS-278 NS-279 NS-280 NS-281

N

NTS US-81 Comanche

Section 1 (NS-278 – NS-281): Widen and resurface to a 40 ft.

  • pen section (two 12 ft. travel lanes and 8 ft. shoulders),

replace Dry Creek Bridge, alignment modification at NS-280 to improve sight distance and correct obsolete vertical curves. Section 2 (NS-281 – S. 5th St.) Widen and resurface to a 42 ft. curb & gutter section (two 12 ft. travel lanes, 8 ft. shoulders and 1 ft. gutters), correct skewed intersections and include dedicated turn lane at the school (evaluate use of 3-lane section)

Begin Project NS-278 End Project

  • S. 5th St.

Bridge D (Unnamed Creek) Widen Bridge F (Unnamed Creek) Pedestrian Bridge Bridge C (Unnamed Creek) Widen Bridge E (Unnamed Creek) Pedestrian Bridge Bridge B (Dry Creek Overflow) Replace with Culvert Bridge A (Dry Creek) Replace Alignment Mod.

slide-20
SLIDE 20

Section 1 Conceptual Improvements

Begin Project NS-278 End Project 5th St. NS-278 NS-279 NS-280 NS-281

N

NTS US-81 C

  • m

a n c h e

Section 1 Proposed roadway cross-section

slide-21
SLIDE 21

Section 1 Conceptual Improvements

slide-22
SLIDE 22

Section 2 Conceptual Improvements

Section 2 Proposed roadway cross-sections

slide-23
SLIDE 23

Section 2 Conceptual Improvements

slide-24
SLIDE 24

Section 2 Conceptual Improvements

Conceptual sidewalk improvements

Segment 1: Comanche

  • Dr. to school crosswalk

Segment 2: School crosswalk to S. 8th St. Segment 3: S. 8th

  • St. to S. 5th St.
slide-25
SLIDE 25

Section 2 Conceptual Improvements

Conceptual sidewalk improvement Segment 1: Comanche Dr. to school crosswalk

slide-26
SLIDE 26

Section 2 Conceptual Improvements

Conceptual sidewalk improvement Segment 2: School crosswalk to S. 8th Street

slide-27
SLIDE 27

Section 2 Conceptual Improvements

Conceptual sidewalk improvement Segment 3: S. 8th Street to S. 5th Street

  • S. 6th St.
  • S. 5th St.
  • S. 8th St.
  • S. 7th St.
slide-28
SLIDE 28

Right-of-Way

Section 1 (open roadway section):

  • Existing right-of-way – Approximately 80 ft.
  • Additional right-of-way required – Approximately 35 ft. either side)
  • Varies based on design constraints
  • Symmetrical widening (widened on both sides)
  • No relocations anticipated

Section 2 (curb & gutter roadway section):

  • Existing right-of-way – Approximately 80 ft.
  • Additional right-of-way required – Approximately 10 ft. either side
  • Varies based on design constraints
  • Symmetrical widening but widened to west near school
  • No relocations anticipated
slide-29
SLIDE 29

Conceptual Improvements At Intersections and Bridges

slide-30
SLIDE 30

Dry Creek Bridge Replacement

Construct Temporary Detour Replace existing 60 ft. long by 30 ft. wide Steel Beam Bridge with 120 ft. long 40 ft. wide Concrete Beam Bridge

NS-279

N

NTS

Replace existing double 10 ft. X 10 ft.

  • verflow bridge culvert with double

6 ft. X 6 ft. roadway culvert.

SH-53

slide-31
SLIDE 31

Dry Creek Bridge Replacement

slide-32
SLIDE 32

Dry Creek Bridge Replacement

slide-33
SLIDE 33

Alignment Modification at NS-280

Construct new alignment to North to correct vertical geometry and maintain traffic during construction

slide-34
SLIDE 34

Alignment Modification at NS-280

slide-35
SLIDE 35

Transition to Curb & Gutter at NS-281

slide-36
SLIDE 36

Texas Ave. Intersection

Texas Ave. SH-53

N NTS

slide-37
SLIDE 37
  • W. Oak Ave. & N. 10th St. Intersections
  • W. Oak Ave.
  • N. 10th St.
  • S. 10th St.
  • S. 8th St.
  • S. 10th St.

N NTS

  • N. 9th St.
slide-38
SLIDE 38
  • S. 8th St. to S. 5th St.
  • S. 6th St.
  • S. 5th St.
  • S. 8th St.
  • S. 7th St.
slide-39
SLIDE 39

Replace Bridge Near 5th Street

slide-40
SLIDE 40

Transition to Angle Parking (EOP)

  • S. 5th St.
  • S. 4th St.

N NTS

slide-41
SLIDE 41

Next Steps

Finalize Environmental Document Submit Comments by 3-8-2016 Select Preferred Design Right-of-Way Acquisition 2017 Gain Public Input

Today

Complete Detailed Design Utility Relocations 2017 Construction 2023

slide-42
SLIDE 42

Thank You!

Please Submit Your Comments by: March 8, 2016

  • Comments may be provided as follows:
  • Leave your comment form here tonight
  • Mail comment form to:

Oklahoma Department of Transportation Office of Public Involvement 200 NE 21st Street Oklahoma City, OK 73105

  • Fax comment form to (405) 521-6917
  • Email comments to: PUBLICMEETINGS@ODOT.ORG
  • Information is available at www.odot.org/publicmeetings