CURRENT CONFIGURATION AHU-01 Configuration - 60% FD CLASHES WITH UPDATED MONORAIL BEAM MONORAIL BEAM (8m) TITLE: AHU CONFIGURATION OPTIONS DATE: 12/12/18 DRAWN BY: DC OPTION NOT PREFERRED FROM AHU-01 Configuration - Rotate 90 deg


slide-1
SLIDE 1

AHU-01 Configuration - 60% FD

CURRENT CONFIGURATION CLASHES WITH UPDATED MONORAIL BEAM TITLE: AHU CONFIGURATION OPTIONS DATE: 12/12/18 DRAWN BY: DC

MONORAIL BEAM (8m)

slide-2
SLIDE 2

AHU-01 Configuration - Rotate 90 deg

OPTION NOT PREFERRED FROM EXCAVATION PERSPECTIVE

MONORAIL BEAM (8m)

slide-3
SLIDE 3

AHU-01 Configuration - Split Unit

OPTION NOT PREFERRED DUE TO SUPPLY DUCTS EXISTING ON BOTH SIDES OF MONORAIL CHALLENGE FOR FUTURE DUCT CONNECTION CROSSING MONORAIL BEAM

MONORAIL BEAM (8m)

slide-4
SLIDE 4

AHU-01 Configuration - Floor Level Horizontal

BSI PREFERRED OPTION AHU IS ACCESSED FROM LOW LEVEL AND SUPPLY DUCT IS ON NORTH SIDE OF CAVERN (FOR FUTURE CONNECTION) OPTION UNDER REVIEW FROM GEOTECH

MONORAIL BEAM (8m)

slide-5
SLIDE 5

AHU-01 Configuration - Floor Level Vertical

BSI PREFERRED OPTION AHU IS ACCESSED FROM LOW LEVEL AND SUPPLY DUCT IS ON NORTH SIDE OF CAVERN (FOR FUTURE CONNECTION) OPTION UNDER REVIEW FROM GEOTECH

MONORAIL BEAM (8m)