Agenda Introductions Brief intro. past hyd. dredging programs LPC - - PowerPoint PPT Presentation
Agenda Introductions Brief intro. past hyd. dredging programs LPC - - PowerPoint PPT Presentation
TOWN HALL MEETING Lake Summerset 2018 Dredge Program Update for Members Presented By Lake Planning Committee Agenda Introductions Brief intro. past hyd. dredging programs LPC Silt Accumulation Studies Engineering & Permitting
Agenda
- Introductions
- Brief intro. past hyd. dredging programs
- LPC Silt Accumulation Studies
- Engineering & Permitting process
- Funding for Dredge Program
- (3) Areas to be dredged & Equipment
- Hageman site for silt disposal
- What’s Next? Water Quality Improvement
- Q & A
LPC Membership
- Ken Malten (Co-Chairman) *
- Steve Harting (Co-Chairman) *
- Bob Page *
- Steve Marshall *
- Mark Metzler *
- Jeff Folkerts *
- Marty Beierwaltes
- Bill Keener
- Bill Pennock – (General Manager LSA)
* Degreed Engineers
L.S. Hydraulic Dredging Programs
- ~1977 Contracted to Beloit Pipeline & Dredge
~12 Years between dredge programs
- 1989 C&C Dredging & Const. – Lake Zurich, IL
3 Years between dredge programs
- 1992 Completed by LSA w/ Leased Equip. (Mud Cat)
26 Years between dredge programs
- 2018 Contracted to Frentress Lake Marine
- Permitting Completed
- Detention basin reconstruction contracted
LPC Siltation Studies
- LPC & LSA staff have worked to monitor silt levels
periodically, major projects listed below:
- 2009 - 2010 Full survey
- 2011 – Birch & Tamarack Bay
- 2015 – West End (50%) & Tamarack Bay (50%)
- 2107 – West End Full
- 2018 - Birch & Tamarack Bays sched. (weather permitting)
Notes: 2016 silt study cancelled due to poor ice / weather issues 2018 silt study planned for Tamarack & Birch bays
Siltation Studies (cont.)
- LPC staff (Mark Metzler) have adapted software
to model the lake bottom
- Lake depth
- Silt accumulation (over multiple studies)
- Calculation of silt volume (cubic yards)
- Analysis of data
Siltation Studies (cont.)
Siltation Studies (cont.)
Calibrated Silt Measurement Pole Data Collection Team 2015
Excerpt from 2017 Pole Data
Lot 38 to Lot 841
Siltation Studies (cont.)
Cross Section Lot 16 to Lot 223
Siltation Studies (cont.)
Cross Section Lot 9 to Lot 216
Siltation Studies (cont.)
Cross Section Lot 38 to 841
Analysis of Siltation Studies
Engineering & Permitting Process
- Greatly expanded requirements for permitting
- Engaged Fehr-Graham & Montgomery Assoc. to
complete engineering, applications & consulting
- LPC - detailed silt studies date back 2009
- IEPA & USACE* permits have been received
- The process to date has taken over two years
* USACE permit is being reissued
West End Proposed Dredge Area 2018
- Projected dredge area:
inlet* to the line between lots 2241 to 1423
- Projected Silt Removal
~15,000 cu. Yds.
- Silt study to be updated in
winter of 2018 (weather permitting)
2018 Proposed Dredge Area Tamarack Bay
* Dredge will proceed into inlet area as far as
equipment will allow
2018 Proposed Dredge Area Birch Bay
* Dredge will proceed into inlet area as far as
equipment will allow
- Projected dredge
area: inlet* to the line between lots 48 to 524
- Projected Silt Removal
~6,500 cu. Yds.
- Silt study to be
updated in winter of 2018 (weather permitting)
Hageman site for silt disposal
Hageman site for silt disposal
Dredge Discharge Pipe Route
Hageman site for silt disposal
Berm restoration (West End)
Dredge Discharge Into Basin (East End) Clear water decanting tower
Funding for Dredge Program
- No “Special Assessment” will be required to
fund the 2018 dredge program
- Funds have been set aside yearly thru member
dues going back to the 1970’s.
- We have been accumulating funds for the 2018
program since 1993.
- Some reallocation of funds is required between
reserve accounts.
2018 Dredging Contract Awarded
Frentress Lake Marine – E. Dubuque, IA
- Frentress awarded berm restoration contract for
Hagemann Spoils Site (work to start shortly)
- Dredge operations to commence early spring 2018, cont.
thru summer until completion
- A single booster pump (barge mounted) will be required
for Tamarack Bay. Location ~midway along pipeline
- Tent. operating schedule: (6) days / wk., (10) hrs./day
- Pipe discharge line will run along bottom of lake thru TX
culvert (not on peoples lawns)
- 60,000 cubic yards of material is targeted for removal
Frentress Lake Marine’s –
High Pressure Cutting Dredge
Operational Photo from Galena Territories 1000 HP Diesel Engine w/ acoustic dampening Walking Spuds for propulsion Cutting head (underwater) Lift Tower for cutter Operator’s Cab 10” dia. silt discharge pipe (off photo)
Frentress Lake Marine’s –
Ancillary Dredge Equipment
HDPE Discharge Pipe (heat welded in field) Cutter Head for Dredge
What’s Next? Water Quality Improvement!
Presented By Bob Page
PRIMARY WATERSHED PROJECT SCENARIOS Lake Maintenance & Water Mgt. Improvements
Upper Watershed Conservation Practices (BMP)
Sedimentation Basin
Lake Dredging
Watershed (farms)
Lake Mgt. Practices – “GOOD”
Conventional Dredging
Lake
Residuals 1290 Tons/Yr
2100 Cubic Yards
3010 Tons/Yr
5000 Cubic Yards
4300 Tons/Yr
7100 Cubic Yards
(Non-Recoverable)
70% 30% 100%
Lake Dredging
Watershed (Farms)
Lake Mgt. Practices – “BETTER”
Farm, Combination Sediment Basin & Dredging
Dredging Lake
Residuals 970 Tons/ Year
1600 Cu. Yds.
2255 Tons / Year
3725 Cu. Yds.
4300 Tons / Year
7100 Cu. Yds.
(Non-Recoverable)
25% 75% 100% 30% 70%
1075 Tons / Year
1775 Cu. Yds.
3225 Tons / Year
5325 Cu. Yds.
Combination Sediment Basin (Hagemann Site) Lake
Lake Mgt. Practices – “BEST”
Farms, BMP, Combination Sediment Basin & Dredging
Dredging Lake
Residuals 730 Tons/ Year
1200 Cu. Yds.
1700 Tons / Year
2800 Cu. Yds.
3225 Tons / Year
5300 Cu. Yds.
(Non-Recoverable)
25% 75% 75% 30% 70%
810 Tons / Year
1330 Cu. Yds.
2420 Tons / Year
3980 Cu. Yds.
Lake Watershed (Farms & BMP)
25%
Combination Sediment Basin (Hagemann Site)
1775 cu. yds. of silt never reach the lake and are trapped on the
Hagemann Property.
1775 cu. yds. are removed from the Hagemann Property by
mechanical means vs. dredging. Savings are (1775 cu yds) ($15.00) – (1775 cu yds) ($3.00) = $21,300
Non recoverable silt is diminished from 2100 cu yds to 1600 cu
yds, a reduction of 500 cu yds.
Water quality is improved because 1775 cu yds of nutrient rich
silt never reaches the lake and silt load is reduced by 900 cu
yds of non recoverable silt.
BOTTOM LINE
Dollar Saving & Water Quality Improvements Lake Mgt. Practices - “Good” to “Better”
3036 cu yds of silt never reach the lake and are trapped
- n the farms or in the off sight sedimentation basin.
1330 cu yds are removed from the sedimentation basin
mechanical vs dredging. Savings are (1330 cu yds) ($15/cu yd) – (1330 cu yds) ($3.00/cu yd) = $15,760
Non recoverable silt load to lake is reduced from 2100 cu
yds to 1200 cu yds, a saving of 900 cu yds.
Water quality is improved because 3030 cu yds of
nutrient rich silt never reaches the lake and non recoverable silt loading to the lake is reduced by 900 cu yds.
Lake Mgt. Practices - “Good” to “Best”
TH THAN ANK K YO YOU !! U !! Q & A Q & A
Bac Backup kup Sl Slid ides es Beg Begin in (fo (for r Q & Q & A) A)
Summary of USDA / NRCS Land Survey
- Avg. Annual Erosion and Sediment Controls for
Otter Creek Total Sediment (Mud) washed into L. S. 4300 Tons/Yr (4.4 Acre Ft or 1183 - 6yd dump trucks) Includes 1000 lbs of Fertilizer / Yr
Major Storm Event – June 17, 1996 8” – 10” Rainfall in 24 Hours
IEPA Dredge Permit – 2015-EA-59941
Army Corps of Eng. Dredge Permit – CEMVR – OD-P-2015-630
Frentress Lake Marine - Dredge Contract
Frentress Lake Marine – Berm Restoration Contract
Lake Summerset Algae Blooms June 2007
Lake Silt Monitoring
- On going monitoring of silt accumulation in the lake
(West End, Tamarack & Birch Bays). 2015 & 2016 data collection currently underway.
- Preliminary results from 2015 silt data completed
- Identified ~60,000 cubic yards of silt
- Data collection to be completed in winter 2016
- Final report issued in Spring 2016
Lake Planning Committee
Siltation Unchecked
Lake Planning Committee
- 4100 acres (6.4 sq. miles) total watershed
- 1600 acres owned or controlled by L.S.A.
- 2500 acres outside our control
- 2170 acres of this is our primary watershed
- 330 acres of this are small secondary watersheds
LAKE SUMMERSET WATER SUPPLY
Source: LPC Data
- Early 1960’s Boise Cascade surveyed land for lake
development (285 acre).
- Extensive water quality test by B.C. provides baseline
- Lake becomes operational in late 1960’s
- LSA conducted to stabilize secondary watersheds,
shorelines & stream banks within development
- LSA participates in IEPA Voluntary Lake Monitoring
Program (VLMP)
- VLMP allows LSA to compare itself with other IL lakes
(yardstick)
- LSA developed an E Coli Testing Program for swimmers
protection
LAKE SUMMERSET (HISTORICAL)
Mudcat Dredge
(Similar to unit in 1992 Prgm.)
Topographical Map of Lake Summerset & Surrounding Area
Legend
Primary Watershed (2200 acres) Secondary Watershed (1900 acres)
Lake Summerset Watershed
- 4100 acres (6.4 sq. miles) total watershed
- 1600 acres owned or controlled by L.S.A.
- 2500 acres outside our control
- 2170 acres of this is our primary watershed
- 330 acres of this are small secondary watersheds
LAKE SUMMERSET WATER SUPPLY
Source: LPC Data
- Primary watershed (normal annual performance)
- Delivers over 50% of rain as runoff water
- Delivers over 95% of all spring water
- Supplies 65% of the total flow to lake
- Smaller watersheds contribute 35% mostly runoff
- Total annual flow to lake 8500 acre ft.
Total flow is 25% spring and 75% runoff water
LAKE SUMMERSET WATER SUPPLY (CONT.)
Source: LPC Data
NOAA’s 24 Hr. Rain Frequency Events
Event Frequency - Years Rainfall - Inches