addition renovation phase 2 re bid results
play

Addition & Renovation Phase 2, Re-Bid Results BASE BIDS BP - PowerPoint PPT Presentation

Addition & Renovation Phase 2, Re-Bid Results BASE BIDS BP Description Name Budget Bid Amount MBE WBE 05a Demolition Broeren Russo Builders, Inc. $ 194,017 $ 307,900 05b Carpentry Broeren Russo Builders,Inc. $ 244,375 $ 400,000


  1. Addition & Renovation

  2. Phase 2, Re-Bid Results BASE BIDS BP Description Name Budget Bid Amount MBE WBE 05a Demolition Broeren Russo Builders, Inc. $ 194,017 $ 307,900 05b Carpentry Broeren Russo Builders,Inc. $ 244,375 $ 400,000 05c Furnish, Doors, Frames, & Hardware S&S Builders Hardware Co. $ 155,800 $ 79,500 05d Framing, Drywall, Ceilings & Treatments Broeren Russo Builders $ 494,561 $ 828,000 05e Painting Bedrock Painting, Inc. $ 127,472 $ 100,000 05f Flooring Mr. David's Flooring Int. LLC $ 313,728 $ 305,471 05g Architectural Woodwork Stevens Industries, Inc. $ 113,215 $ 159,800 30% 06a Roofing at New Addition Advanced Commercial Roofing $ 173,827 $ 152,625 32% 06b Roofing at Existing School Advanced Commercial Roofing $ 30,034 $ 71,975 13% TOTALS $ 1,847,029 $ 2,405,271 0.0% 4.4%

  3. Guaranteed Maximum Price Amendment Phase 2 Re-bid, Total Guaranteed Maximum Price $ 2,737,858

  4. Revised Project Budget Revised Total Project Budget $ 12,097,041 Requested Budget Increase $ 997,041

  5. SOUTH SIDE ELEMENTARY SCHOOL ADDITION & RENOVATION PROJECT SCHEDULE

  6. Primary Entrance Barrier-free Doors

  7. Primary Entrance Barrier-free Doors

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.