Actinide Behaviour during Severe Nuclear Accident Three Mile - - PowerPoint PPT Presentation

actinide behaviour during severe nuclear accident three
SMART_READER_LITE
LIVE PREVIEW

Actinide Behaviour during Severe Nuclear Accident Three Mile - - PowerPoint PPT Presentation

Actinide Behaviour during Severe Nuclear Accident Three Mile Island Andriy Sizov, PhD, Senior researcher/Technical Expert Institute for Safety Problems of NPPs/ENCO Joint ICTP-IAEA International School on 10 14 September 2018 1


slide-1
SLIDE 1

Actinide Behaviour during Severe Nuclear Accident – Three Mile Island

Andriy Sizov, PhD, Senior researcher/Technical Expert Institute for Safety Problems of NPPs/ENCO

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 1

slide-2
SLIDE 2

TMI

  • Middletown, Pennsylvania
  • May 1968 Three Mile Island (TMI) Unit 1

Construction began

  • November 1969 TMI Unit 2 Construction began
  • Unit 1 began operation in September 1974
  • Unit 2 started up in December 1978
  • Within 90 days, on March 28, 1979, a nuclear meltdown
  • ccurred in TMI 2
  • A non-nuclear failure led to a nuclear meltdown
  • Worst accident at a nuclear power plant in the

history of U.S. commercial power plants

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 2

slide-3
SLIDE 3

Location

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 3

slide-4
SLIDE 4

Three Mile Island NPP

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 4

slide-5
SLIDE 5

Reactor

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 5

slide-6
SLIDE 6

Sequence

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 6

slide-7
SLIDE 7

Sequence 2

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 7

slide-8
SLIDE 8

Sequence 3

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 8

slide-9
SLIDE 9

Sequence 4

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 9

slide-10
SLIDE 10

Sequence 5

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 10

slide-11
SLIDE 11

Sequence 6

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 11

slide-12
SLIDE 12

Sequence 7

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 12

slide-13
SLIDE 13

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 13

Actions

slide-14
SLIDE 14

Physical and Chemical processes during the accident

  • Phase 1 of the accident: LOCA (estimated duration 100 minutes)
  • Phase 2 of the accident: core heating with the RCS and high-

pressure SIS shut down (from 100 minutes to 174 minutes)

  • Phase 3 of the accident: partial reflooding of the core - formation of

a debris bed (between 174 and 180 minutes)

  • Phase 4 of the accident: heating of the debris bed – development of

the corium pool (between 180 and 200 minutes)

  • Phase 5 of the accident: total reflooding of the core - continued

development of the corium pool (between 200 and 224 minutes)

  • Phase 6 of the accident: movement of core materials towards the

reactor vessel’s lower plenum (between 224 and 226 minutes)

  • End of the accident: restoration of stable cooling (to 16 hours after

the start of the accident)

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 14

slide-15
SLIDE 15

Phase 1.

Phase 1 of the accident: LOCA (estimated duration 100 minutes). Assumed state of the core after lower crust formation.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 15

slide-16
SLIDE 16

Phase 2.

Phase 2 of the accident: core heating with the RCS and high- pressure SIS shut down (from 100 minutes to 174 minutes). Dose rate alarm. Relief valve is closed. Assumed state of the core 174 minutes after the start of the accident.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 16

slide-17
SLIDE 17

Phase 3.

Phase 3 of the accident: partial reflooding of the core (23 m3)- formation of a debris bed (between 174 and 180 minutes).

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 17

slide-18
SLIDE 18

Phase 4 and 5.

Phase 4 of the accident: heating of the debris bed – development of the corium pool (between 180 and 200 minutes). Reopening pressurizer relief valve. Emergency situation declared. Phase 5 of the accident: total reflooding of the core

  • continued development of

the corium pool (between 200 and 224 minutes) SIS is restarted.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 18

slide-19
SLIDE 19

Phase 6.

Phase 6 of the accident: movement of core materials towards the reactor vessel’s lower plenum (between 224 and 226 minutes). Crust rupture.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 19

slide-20
SLIDE 20

End state.

End of the accident: restoration of stable cooling (to 16 hours after the start of the accident). Hydrogen combustion occurred 9 hours 30 minutes after the start of the accident.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 20

slide-21
SLIDE 21

Decontamination and Defueling

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 21

slide-22
SLIDE 22

Why can it be dangerous? China syndrome

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 22

slide-23
SLIDE 23

Environmental/Public Health Consequences

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 23

  • No fatalities or injuries
  • Radiation exposure ~ 0.3 - 0.6 rem
  • No conclusive evidence for an increase in

cancer cases

  • Unit 2 not allowed to resume operation
  • Unit 1 not allowed to resume operations until 1985
  • General Public Utilities paid $82 million as compensation
  • Negative media coverage
  • Property values dropped
  • Mistrust of Nuclear Industry
  • Loss of income for surrounding farms
slide-24
SLIDE 24

Environmental/Public Health Consequences

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 24

slide-25
SLIDE 25

Consequences of the accident: comparison with Chornobyl and Fukushima

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 25

slide-26
SLIDE 26
  • New Regulations
  • Inherently Safer Design and Operation
  • Emphasis on Training and Transparency
  • Expect the Unexpected (PSA). More

severe accidents than a LOCA

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 26

Lessons Learned

slide-27
SLIDE 27

The PHEBUS FP programme

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 27

slide-28
SLIDE 28

References / Useful Links

  • Missouri University of Science and Technology

http://web.mst.edu/~dludlow/classes/ChE%20285%20S p12/Three%20Mile%20Island.pptx

  • Nuclear Power Reactor Core Melt Accidents. Current

State of Knowledge. IRSN 2015

  • Three Mile Island Nuclear Accident. March 28, 1979 at

Three Mile Island, Pennsylvania, USA. Failure Knowledge Database

  • Three Mile Island Accident of 1979 Knowledge

Management Digest. Overview. NUREG/KM-0001, Revision 1. Office of Nuclear Regulatory Research

  • Backgrounder on the Three Mile Island Accident

https://www.nrc.gov/reading-rm/doc-collections/fact- sheets/3mile-isle.html

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 28

slide-29
SLIDE 29

Thank you for your attention.

10 – 14 September 2018 Joint ICTP-IAEA International School on Nuclear Waste Actinide Immobilization 29