ABCOURT MINES INC.
BARVUE MINE SILVER-ZINC PROJECT
(July, 2017)
Planned 1750 t/d mill Project
1
ABCOURT MINES INC. BARVUE MINE SILVER-ZINC PROJECT (July, 2017) - - PowerPoint PPT Presentation
ABCOURT MINES INC. BARVUE MINE SILVER-ZINC PROJECT (July, 2017) Planned 1750 t/d mill Project 1 A BCOURT M INES Inc. TSXV : ABI FORWARD LOOKING STATEMENTS Except for statements of historical facts, some statements contained in this Power
(July, 2017)
1
Except for statements of historical facts, some statements contained in this Power Point presentation, constitute forward looking statements, including, without limitation, anticipated developments in the Company’s operations in future periods and other events or conditions that may occur in the future. These statements are about the future and are inherently uncertain and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors. Management believes that the expectations reflected in those statements are reasonable but no assurance can be given that these expectations will prove to be correct. It is recommended not to place undue reliance on forward-looking statements as the plans, intentions or expectations upon which they are based might not occur.
TSXV: ABI
2
TSXV: ABI
3
CAPITAL STRUCTURE
and also in Berlin (AML-BE) and Frankfurt (AML-FF)
commercial production, the net profit was $1.73M
net loss of $1.9M was incurred. A profit of $186,000 was made in the 3rd quarter.
TSXv: ABI / Pink Sheets: ABMBF
Officers:
Canada for over 50 years, both with major and junior mining companies. Proven track record of cost efficient mining operation management.
development and management.
worldwide experience.
Directors: Renaud Hinse, mining engineer, CEO François Mestrallet, business man André de Guise, mining engineer with several years of mine management experience Marc Filion, Ph. D, M.B.A., P. Eng. geology Normand Hinse, B. adm., business man Jean-Guy Courtois, retired business man Legal counsel: Me Julie Godard, Rouyn-Noranda, Qc Auditors: Dallaire & Lapointe, Rouyn-Noranda, Qc
4
TSXv: ABI
5
1- Barvue 2- Vendome 3- Jonpol 4- Elder-Tagami 5- Aldermac
(ROUYN-NORANDA / VAL-D’OR AREA)
TSXv: ABI / Pink Sheets: ABMBF
6
BARVUE MINE
6- Vezza (claims) 7- Géant Dormant mine 8- Discovery - Flordin
(AMOS – MATAGAMI AREA)
TSXv: ABI / Pink Sheets: ABMBF
7
8 .
TSXv: ABI
8
Barvue mine’s production : 8.87 M oz Ag and 198,850 st Zn in concentrate from open pit (1952-57) and 2.67 M oz Ag and 34,850 st Zn in concentrate from underground (1985-90) . Historical picture of Barvue mine (1952-1957)
TSXv: ABI / Pink Sheets: ABMBF
9
8 .
TSXv: ABI
10
Barvue Property
are evaluated at
equipment)
Barvue Property
11
TSXv: ABI / Pink Sheets: ABMBF
RESERVES AND RESOURCES HIGHLIGHTS
1985-1990: 2.67 M oz Ag and 34,850 st Zn in concentrate from Barvue U/G mine
6,515,863 t @58.32 g/t Ag & 3.33%/t Zn
503,106 t @95.35 g/t Ag & 3.44%/t Zn
1,505,687 t @ 120.53 g/t Ag & 2.98%/t Zn
(14,400,000 ounces of silver & 545,000,000 pounds of zinc)
2,041,150 t @ 114.32 g/t Ag & 2.89%/t Zn
zinc)
Barvue Property
12
TSXv: ABI / Pink Sheets: ABMBF
SERVES (incl. dilution)
2010 & 2011 drilling at 150 – 180 m depth has upgraded and expended these resources.
2006 Proven / Probable : 6,823,532 tonnes @ 57.76 g/t Ag and 3.11% Zn ( 95 % Proven, 78 % Open pit, 5.7 % Ave. Dilution )
2010 & 2011 drilling at 150 – 180 m depth has upgraded and expended these
Partly
13
TSXv: ABI / Pink Sheets: ABMBF
Barvue Property
14
TSXv: ABI / Pink Sheets: ABMBF
615,000 t/yr
up to 80% of the silver and producing a 56-57% Zn concentrate for sale
financing
property
been issued for water treatment facilities and the dewatering of the mine
Barvue Property
15
TSXv: ABI / Pink Sheets: ABMBF
Summary of project CAPEX
(all in Canadian dollars x 1,000)
2007 estimate CAN$
Mine equipment & preproduction stripping, etc 19,812 Process plant (EPCM & contingencies included) 44,275 Infrastructure 1,862 Owner’s cost (including warehouse inventory) 1,930 Pre-production capital 67,879 Working capital 3,376 Total: 71,255 Less value of equipment on site 11,255 Net cost 60,000 Subsequent 10 year on-going capital expenditures (open pit & underground development) 24,420
Barvue Property
16
TSXv: ABI / Pink Sheets: ABMBF
(all in Canadian dollar, 2007 estimate)
Life-of-mine operating costs in M$ Unit costs / tonne
Mining1 98.6 15.30 Processing 87.42 13.46 G & A 14.30 2.22 Royalties 1.16 0.18 Total 201.48 31.16
1 Supplies include maintenance and repairs by the suppliers for open pit equipment.
Barvue Property
17
TSXv: ABI / Pink Sheets: ABMBF
(Source: World Bank – in $/t)
Average price 2017 – 2025 = US$1,04 / lb August 11, 2017 = US$1.31 / lbs
Barvue Property
18
TSXv: ABI / Pink Sheets: ABMBF August 2017
Barvue Property
19
TSXv: ABI / Pink Sheets: ABMBF
(with distance to Barvue’s future mill site)
Barvue Property
20
TSXv: ABI / Pink Sheets: ABMBF
Measured & Indicated: 712,222 tonnes, 0.63 % Cu, 7.50 % Zn, 1.23 g/t Au, 60.11 g/t Ag Inferred: 305,769 tonnes, 0.49 % Cu, 4.30 % Zn 0.99 g/t Au, 36.77 g/t Ag
63,000 short tons, 0.19 oz/t Au
Barvue Property
21
TSXv: ABI / Pink Sheets: ABMBF
Upper: 20,000 st @ 4 % Zn and 8 oz/st Ag Jay: 26,000 st @ 3.5 % Cu and 1 oz/st Ag Main West: 1,946,000 st @ 1.04 % Cu and 0.02 oz/st Ag Lower: 815,000 st @ 1.25 % Cu, 3,21 % Zn and 3.55 oz/st Ag
Barvue Property
22
TSXv: ABI / Pink Sheets: ABMBF
~ 2,000,000 st @ 1.78 % Cu, 0.2 oz/t Ag and 0.02 oz/t Au
1,781,000 st @ 1.56% Cu, 4.01% Zn, 0.89 oz/t Ag, 0.014 oz/t Au Excellent copper-zinc values over outstanding widths in 2008 drilling:
Hole From To Length (meters) % Cu % Zn g/t Ag g/t Au AL08-11 256.03 279.50 23.47 1.22 5.06 26.30 0.216 AL08-12 305.00 311.00 6.00 0.37 6.34 11.30 0.028 327.50 367.80 40.30 1.16 5.42 35.88 0.460 AL08-13 269.75 301.43 27.05 1.09 3.15 16.70 0.030 AL08-14 354.08 393.76 39.68 1.94 3.58 28.80 0.579 AL08-17 254.63 259.00 4.37 0.54 8.99 22.70 0.025 265.50 272.08 6.58 0.90 18.94 34.10 0.044 AL08-18 255.26 264.09 8.83 0.49 7.20 22.70 0.126 294.35 296.03 1.68 3.52 0.04 41.20 0.168 AL08-20 318.58 323.68 5.10 2.31 13.03 63.90 0.390 AL08-21 227.20 234.70 7.50 1.86 1.06 29.00 0.230
Revised May 6, 2008
Barvue Property
23
TSXv: ABI / Pink Sheets: ABMBF
Note: When the 2007 Feasibility Study was done in 2007, the price of the shares reached $0.85. From 2008 to 2017, the project was dormant.
TSXv: ABI
24
The mine is equiped with functional buildings and all
underground equipment with a 2,600-ft shaft (793 m) and 16 levels. 95 employees
TSXv: ABI
25
and other Gold Properties with the Regional Geology
Amos DISCOVERY FLORENCE CAMERON SHEAR FLORDIN LAFLAMME DORMEX HARRICANA VEZZA Matagami Senneterre Chibougamau
26
Renaud Hinse President, Director and CEO Abcourt Mines Inc. 506 des Falaises St. Mont-St-Hilaire, Québec J3H 5R7 Tel.: 1-819-768-2857 rhinse@abcourt.com TSXv: ABI
Renaud Hinse President, Director and CEO Abcourt Mines Inc. 506 des Falaises St. Mont-St-Hilaire, Québec J3H 5R7 Tel.: 1-819-768-2857 rhinse@abcourt.com
27