A12 Chelmsford to A120 widening
Third round of forums 25 November – 7 December 2016
A12 Chelmsford to A120 widening Third round of forums 25 November 7 - - PowerPoint PPT Presentation
A12 Chelmsford to A120 widening Third round of forums 25 November 7 December 2016 The Project team : Shah Hussain Project Manager (Highways England) Patrick de Feu Project Manager (Jacobs) David Orr-Ewing Principal Engagement
Third round of forums 25 November – 7 December 2016
Shah Hussain– Project Manager (Highways England) Patrick de Feu – Project Manager (Jacobs) David Orr-Ewing – Principal Engagement Manager (Jacobs) Jennifer Goddard – Business Manager (Highways England) Philippa Garden – Engagement Lead (Jacobs)
5
6
identify issues & objectives create long list
achieve
'shortlist
select options for consultation
Avalon’s issues:
motorway
businesses are finding cost of transport are affecting their growth.
years 8 How?
local policies and priorities
This work produces.
engagement with statutory bodies.
previously commissioned route
landowner and farmer put forward a route last year
from the council and government organisations were engaged to generate route options
9
10
11
look at options to identify the best ‘route’ in each avoiding ‘environmental showstoppers’
feasible better performing options
What to look at…
Apply the Treasury’s Case Model 1. Strategic case 2. Economic case 3. Management case 4. Financial case 5. Commercial case Review original objectives and enhance and apply 12
13
sifting is detailed in an Options Appraisal Report.
14
Analyse the responses received and then undertake any additional technical work required Report the feedback received to the decision maker Should decision maker believe there is a compelling case for the scheme and a suitable option, a preferred route would be announced Further engagement with communities, land owners and stakeholders as the preferred route is developed and more technical work takes place, including environmental A statutory public consultation on the Preferred Route Further technical work and engagement, then submit an application for a Development Consent Order (Planning Application) Consent Order decision received If successful, construction would begin
identify issues & objectives create long list
achieve
'shortlist
select options for consultation
Issues Congestion Safety Resilience Reliability Substandard junctions Poor provision for non-motorised users Objectives Improving user satisfaction Making the network safer Supporting the smooth flow of traffic Encouraging economic growth Delivering better environmental
Helping cyclists, walkers and other vulnerable road users of the network
Using existing reports, technical workshops and objectives, a long list of options was created:
22
Analyse the responses received and then undertake any additional technical work required Report the feedback received to the decision maker Should decision maker believe there is a compelling case for the scheme and a suitable option, a preferred route would be announced Further engagement with communities, land owners and stakeholders as the preferred route is developed and more technical work takes place, including environmental A statutory public consultation on the Preferred Route Further technical work and engagement, then submit an application for a Development Consent Order (Planning Application) Consent Order decision received If successful, construction would begin
Identify problems and
an area Data Collection Development
model Development of future traffic growth models Scheme
assessment
Stage 1 Options identification Stage 0 Outline Strategy Current position
Between April and June 2016 we commissioned a large number of traffic surveys across the area. Other data sources used include:
journey time and traffic flow
A120 study
destination data
destination and journey time data
Colchester Chelmsford Witham Braintree
Up to 90,000 vehicles per day (two-way) Over 4,000 vehicles in each direction at the busiest locations
Existing flows are over 85% Capacity Existing flows are under 85% Capacity Existing flows are over 100% Capacity
J22
Junction 19 - 25 Free flow journey time - 15 mins Typical peak journey time - up to 25 mins
J19 J20a J20b J21 J23 J24 J25
Witham Hatfield Peverel Chelmsford
A120
Kelvedon
A130 B1019 B1018 B1024
We are currently developing a new traffic model using the 2016 traffic data using computer software. The model reflects typical weekday ‘peak hour’ conditions. The model will allow us to study how traffic moves across the area, not just on the A12, but a much wider area. Forecast models allow us to see how traffic might change in the future on the A12 and on local roads (with and without the implementation of scheme
A12 A12 Witham
Colchester Braintree Chelmsford Brentwood
The scheme will lead to significant improvements in traffic conditions throughout the wider area and not just on the scheme itself. We study this by developing a traffic growth ‘forecast’ model which tells us about traffic conditions in the future. Traffic modelling allows us to assess a number of different impacts and benefits across the entire study area including (but not limited to):
These benefits can be turned into a monetary value then used to provide a “Benefit to Cost Ratio” (BCR) and subsequently estimate the Value for Money of the scheme. Any scheme must demonstrate Value for Money.
Email: A12chelmsfordA120wide@highwaysengland.co.uk Website: www.highways.gov.uk/A12chelmsfordA120widening