A Complete Electrical Distributor Since 1919 Celebrating 90 Years of - - PowerPoint PPT Presentation

a complete electrical distributor since 1919
SMART_READER_LITE
LIVE PREVIEW

A Complete Electrical Distributor Since 1919 Celebrating 90 Years of - - PowerPoint PPT Presentation

To be a global business leader and build shareholder value through our commitment to provide the best service and value to the Electrical Industry and to the communities we serve. A Complete Electrical Distributor Since 1919 Celebrating 90


slide-1
SLIDE 1

A Complete Electrical Distributor Since 1919

Celebrating 90 Years of Service “To be a global business leader and build shareholder value through our commitment to provide the best service and value to the Electrical Industry and to the communities we serve.”

slide-2
SLIDE 2

Solar System and Component Descriptions

  • We designed the system to be showcase to

promote our offering and abilities with solar for our entry in the renewable market.

  • This project was intended to be a learning

vehicle for the Renewable Group.

slide-3
SLIDE 3

Solar System and Component Descriptions

  • 47.2 KW solar array
  • Consists of 189-250w panels
  • Installed in the fall of 2012
  • System is a Net Metering configuration
  • Covers about a 1/3 of the power for our

85,000 sq ft facility

slide-4
SLIDE 4
slide-5
SLIDE 5

Mounting system

  • Our mounting system is an Arista non-invasive system by

Cooper Industries. (No penatrations in the roof)

  • The quantity of pavers was calculated by weight as

required to prevent the system from lifting under 100 mph plus winds.

  • We required 15 pallets (2250 concrete pavers), each

paver weighing 21 lbs.

  • Our roofing contractor required us to install an additional

90 mm of membrane in the area of the solar system to protect the original 35 mm membrane. This was to maintain our warranty.

slide-6
SLIDE 6
slide-7
SLIDE 7

Solar Panels

  • We used Jinko Solar JMK250M 250 watt panels.
  • The system configures as 9 arrays.
  • Each array consists of 7 strings in parallel.
  • Each string consists of 3 panels wired together in
  • series. 3 panels in series is rated at 8.70 amps

and 112.8 vdc.

  • The 7 strings per array put out 60.9 amps at the

112.8 vdc. Each of the arrays is tied to an inverter.

slide-8
SLIDE 8

Combiner Box

  • The combiner boxes are manufactured by

Mersen.

  • These boxes were custom designed for us as

we have also incorporated a shunt trip which will become a code item in the future.

  • The shunt gives firemen entering the building

the ability to shut down the system.

  • The combiner box “combines” the 7 strings.
slide-9
SLIDE 9
slide-10
SLIDE 10

Inverter

  • The inverter we chose is manufactured by

Sustainable Energy Technologies.

  • The inverter converts the dc current and

voltage to ac current and voltage, in our case 1 phase 208vac.

  • These inverters are rated for cold weather

(-40 deg C) so are mounted on the roof at the

  • arrays. This minimizes losses in the system.
slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

Max Monthly Efficiency (All Inverters, DC/AC Conversion): February 2017 to June 2017 Max Monthly Efficiency (All Strings): February 2017 to June 2017

slide-15
SLIDE 15
slide-16
SLIDE 16

Key Points

Overall cost for Material was roughly $300,000.00 Cost overruns for structural upgrades $50,000.00 Modifications to roof membrane $50,000.00

slide-17
SLIDE 17

Key Points

Since installation we have done zero maintenance With the 30 degree angle on the panels, they are more or less self cleaning

slide-18
SLIDE 18

Key Points

At roughly .09/kwh we would generate about $6,142.00/year in revenue. That is roughly 68,230 KWH per year. The approx payback would be 50 plus years. With todays price for material and install it would be roughly a 10 year payback in comparison. This gives you a good snap shot on how the market has come down in just 7 short years.

slide-19
SLIDE 19

Summary

The solar project was a learning experience. It gave us a working knowledge from design through installation. And importantly, we are able to review real data, not just theoretical production potential. With everything learned, in future installations problems would be mitigated.

slide-20
SLIDE 20

Thank You