4 13 2009
play

4/13/2009 Presentation Outline Project Overview Chilled Beams - PDF document

4/13/2009 Presentation Outline Project Overview Chilled Beams & Commissioning Mechanical Breadth Parking Garage Waffle Slab Structural Breadth Curtain Wall Installation MAE Graduate Level Component Summary


  1. 4/13/2009 Presentation Outline • Project Overview • Chilled Beams & Commissioning – Mechanical Breadth • Parking Garage Waffle Slab – Structural Breadth • Curtain Wall Installation – MAE Graduate Level Component • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 1

  2. 4/13/2009 Presentation Outline History • Project Overview • Renovation of an existing building • Chilled Beams & Commissioning • Originally constructed in 1976 – Mechanical Breadth • Formerly occupied by the • Parking Garage Waffle Slab – Structural Breadth Department of Transportation • Curtain Wall Installation • Operated and leased by David – MAE Graduate Level Component Nassif Associates • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Location Location • Project Overview • Located a few blocks south of the • Chilled Beams & Commissioning National Mall and the United State – Mechanical Breadth Capital • Parking Garage Waffle Slab • Between 6 th and 7 th Street and D – Structural Breadth and E Street in SW DC • Curtain Wall Installation – MAE Graduate Level Component • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 2

  3. 4/13/2009 Project Team Presentation Outline Project Overview • Project Overview • Size: 1,500,000SF base building and Owner David Nassif Associates • Chilled Beams & Commissioning 6,000SF parking garage • Number of Stories: Three-level – Mechanical Breadth Lump Sum Lump Sum GMP underground parking garage, 10 • Parking Garage Waffle Slab Architect/MEP Engineer Owners Representative General Contractor stories, plus a Pent House SmithGroup, Inc. Kramer Consulting James G. Davis – Structural Breadth Construction Corp. • Curtain Wall Installation • Cost: $246 Million GMP Lump Sum Lump Sum Lump – MAE Graduate Level Component • Construction Dates: July 2007 – Sum Civil Engineer Structural Engineer Unit Subcontractors • Summary November 2009 Rate Wiles Mensch Corp. SK&A Not Listed • Questions and Acknowledgements • Security Rating: Level IV Abatement Subcontractor Aceco, Inc. • LEED Rating: Gold Project Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Architecture Overview • Project Overview • 4 separate, but integrated quadrants – Elevator • Chilled Beams & Commissioning – Stairways – Mechanical Breadth – Restrooms • Parking Garage Waffle Slab – Electrical and Communication Closets • One acre courtyard that is a private, – Structural Breadth secure green space • Curtain Wall Installation – Fountain, seating areas, sculpture, and 32 – MAE Graduate Level Component Honey Locus Shad Trees that are 11’-5” tall • Summary • Built-up roofing system and metal panels used to conceal the MEP equipment on the • Questions and Acknowledgements Pent House level Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 3

  4. 4/13/2009 Presentation Outline Chilled Beams • Project Overview • Finned chilled water heat exchanger • Chilled Beams & Commissioning utilizing cooling coils – Mechanical Breadth • Active chilled beams • Parking Garage Waffle Slab – About 7,000 units – Structural Breadth • Curtain Wall Installation – MAE Graduate Level Component • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Chilled Beams • Project Overview • Limited ceiling plenum • Chilled Beams & Commissioning • Goal: – Mechanical Breadth – 8’-4” ceiling height • Parking Garage Waffle Slab – Leaves 2’-0” to work with, including 1’-0” – Structural Breadth waffle slab • Curtain Wall Installation • TROX customized systems to only be – MAE Graduate Level Component 7.5” high and 2’ wide by 8’ long. • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 4

  5. 4/13/2009 Energy Cost Comparison Presentation Outline Energy Usage • Project Overview (according to SmithGroup's Research) (according to SmithGroup's Research) $3.00 • Chilled Beams & Commissioning 2.6% $2.67 4.1% 0.5% 10.2% $2.50 – Mechanical Breadth Lighting - Conditioned - 10.2% 2.3% 4.7% $/sq ft per year Lighting - Uncondititioned - 4.1% 1.1% 4.1% $1.93 • Parking Garage Waffle Slab Space Heating - 25.5% $2.00 Savings - 19.6% 4.9% $1.50 – Structural Breadth Space Cooling - 12.7% 1.4% $1.50 Pumps - 6.4% • Curtain Wall Installation Cooling Tower - 1.4% 6.4% $1.00 Fans - AHU - 4.9% – MAE Graduate Level Component 25.5% Fans - Misc. - 1.1% $0.50 • Summary Fans - Parking Garage - 2.3% Service Water Heating - 0.5% 12.7% Office Equipment - 4.7% • Questions and Acknowledgements $0.00 Savings Elevator & Escalators - 2.6% Typical Building in ASHRAE Constitution Misc. Equipment - 4.1% Washington DC 90.12004 Center 19.6% Baseline (1,504,000 sq ft) Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Multi-Service Beams • Project Overview • Services built into them for “just-in-time” arrival • Chilled Beams & Commissioning – Lighting fixtures and control circuits – Mechanical Breadth • Direct and/or indirect • Parking Garage Waffle Slab – Public address speakers – Structural Breadth – Occupancy sensors • Curtain Wall Installation – Fire and smoke sensors and alarms – MAE Graduate Level Component – Passive infra-red detectors • Summary – Acoustic insulation – Sprinklers • Questions and Acknowledgements – Fresh air supply – Cooling and heating Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 5

  6. 4/13/2009 Presentation Outline Advantages • Project Overview • Shorter construction periods • Chilled Beams & Commissioning • Clear reduction of interfaces – Mechanical Breadth • Less maintenance and operating costs • Parking Garage Waffle Slab • Energy savings – Structural Breadth • Curtain Wall Installation • Maximum flexibility of configuration and technology – MAE Graduate Level Component • Summary • Customized exterior frames • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Cost Comparison Schedule Comparison • Project Overview • Active Chilled Beams • Active Chilled Beams • Chilled Beams & Commissioning – $150/LF to $200/LF – About 20 minutes to install one unit – Mechanical Breadth • Multi-Service Chilled Beams • Multi-Service Chilled Beams • Parking Garage Waffle Slab – $350/LF to $500/LF – About 25 minutes to install one unit – Structural Breadth • Curtain Wall Installation – MAE Graduate Level Component • Summary • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 6

  7. 4/13/2009 Commissioning Presentation Outline Commissioning • Project Overview • LEED Gold rating • ComIT • Chilled Beams & Commissioning – Energy & Atmosphere LEED points • Program used to track deficiency items, – Mechanical Breadth • Four phases: post information such as schedules, • Parking Garage Waffle Slab – Phase 1 - Hot Water System submittals, and start-up forms – Structural Breadth – Phase 2 - CHW/CW & North AHU system • Curtain Wall Installation – Phase 3 - SW AHU System, Fuel Oil System, Emergency Power System, and Power – MAE Graduate Level Component Monitoring System • Summary – Phase 4 - SE AHU System, FA System, BMS • Questions and Acknowledgements System, and conclude with Endurance Period Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 Presentation Outline Commissioning • Project Overview • Interview of several industry members: • Chilled Beams & Commissioning – “Identify the commissioning needs and – Mechanical Breadth program requirements early in the design • Parking Garage Waffle Slab stage so all team members can understand and set their strategies to meet the project – Structural Breadth goals” • Curtain Wall Installation – “Make sure all parties know what is required – MAE Graduate Level Component for commissioning as soon in the project as • Summary possible (Communications is key)” • Questions and Acknowledgements Natalie Bryner Constitution Center Construction Management Option 400 7th Street SE, Washington, DC 20024 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend