30 years of gewi pile applications in canada
play

30 Years of GEWI-Pile Applications in Canada International Society - PowerPoint PPT Presentation

30 Years of GEWI-Pile Applications in Canada International Society of Micropiles Toronto, Sept 26 - 30, 2007 Prepared by Joe Li and Gary Kast 1 ISM Toronto, 2007 GEWI-Piles - Presentation Introduction Definition / System


  1. 30 Years of GEWI-Pile Applications in Canada International Society of Micropiles Toronto, Sept 26 - 30, 2007 Prepared by Joe Li and Gary Kast 1 ISM Toronto, 2007

  2. GEWI-Piles - Presentation • Introduction • Definition / System • Applications • Summary 2 ISM Toronto, 2007

  3. Introduction • Original micropiles or “root piles” by Dr. F. Lizzi - early 50’s • GEWI-Piles introduced to Western Canada in Mid 1970’s • The first GEWI-Pile project for an oil storage tank in a refinery, Calgary, 1974 • Winter Olympic Games in Mid 1980’s • Thousands of GEWI-Piles have been used 3 ISM Toronto, 2007

  4. Definition A GEWI-Pile (Threadbar Micropile ) is a small diameter, usually less than 300 mm, bored and grouted friction pile with centrically located threadbar(s) as the load carrying element, acting in tension and/or compression. 4 ISM Toronto, 2007

  5. GEWI-Pile System - Grout body encasing Threadbar provides corrosion protection for compression pile. - Double Corrosion Protection (DCP) system used for GEWI-Piles in tension. - Force transfered by friction into rock or soil. - Threadbar provides excellent bond transfer. - Continuous threads provide connection in pile cap. - Add permanent steel casing for additional capacity. - Special grouting techniques improve load carrying capacity. - DCP is an inexpensive corrosion protection system. (only a fraction of overall installation cost) 5 ISM Toronto, 2007

  6. GEWI-Pile Grouting Techniques Type A: Gravity fill techniques. Type B: Pressure grouting through casing. Type C: Type A + High-pressure Postgrouting. 6 ISM Toronto, 2007

  7. GEWI-Pile Applications – logistic advantages Solving logistic problems such as: 1) Difficult access to sites 2) Low headroom 3) Tight and congested work areas 4) Difficult soil conditions 7 ISM Toronto, 2007

  8. GEWI-Pile Applications – logistic advantages, continued.. 1) Access to sites – Along steep slopes (Rogers pass, BC, 1985) – Foundation in remote sites (Dew Lines, 1990) 8 ISM Toronto, 2007

  9. CP Rail Viaduct at Roger’s Pass, BC – 1985 9 ISM Toronto, 2007

  10. CP Rail Viaduct at Roger’s Pass, BC – 1985 Original Design 900ø steel pipe-piles 12 m deep, vertical Note the embankment required to support the temporary access road for heavy piling equipment 10 ISM Toronto, 2007

  11. CP Rail Viaduct at Roger’s Pass, BC – 1985 TYP. SPAN LENGTH = 30.0m Alternative Design (As-built) DYWIDAG GEWI-Piles 57ø gr. 517MPa tested to 1,020kN 140ø borehole 1,300 x 9 m deep at 20º Single Corrosion Protection Pressure grouted through casing 11 ISM Toronto, 2007

  12. GEWI-Pile pier foundations for Elevated Buildings, Dew Line, 1990 #14 Grade 413MPa Bar Working load 165kN Test load in tension 330kN GEWI-Pile for vertical piers Borehole 127mm Embedment length in rock 4 - 10m Cement Fondue grout Easy transport of materials & equipment 12 ISM Toronto, 2007

  13. GEWI-Piles Applications – logistic advantages, continued.. 2) Low headroom – Seismic Upgrading of existing Schools (Britannia School in Vancouver, 1993) – Underpinning for additons (Tiptop Tailors Building, Toronto, 2003) 13 ISM Toronto, 2007

  14. Seismic Upgrade of Britannia School in Vancouver, 1993 57Ø DYWIDAG GEWI-piles with Double Corrosion Protection (DCP) in aggressive soils. Pre-production Compression and Tension cyclic testing 14 ISM Toronto, 2007

  15. Seismic Upgrade of Britannia School in Vancouver, 1993 15 ISM Toronto, 2007

  16. Seismic Upgrade of Britannia School in Vancouver, 1993 16 ISM Toronto, 2007

  17. Seismic Upgrade of Britannia School in Vancouver, 1993 Tested GEWI-Piles ready to receive reinforcing steel and concrete 17 ISM Toronto, 2007

  18. Seismic Upgrade of Britannia School in Vancouver, 1993 Inclined Compression load testing of production GEWI-Piles 18 ISM Toronto, 2007

  19. Underpinning of Tiptop Tailors Building, Toronto, 2003 19 ISM Toronto, 2007

  20. Drilling of GEWI-Piles at Tiptop Tailors Building, Toronto, 2003 20 ISM Toronto, 2007

  21. Installation of GEWI-Pile at Tiptop Tailors Building, Toronto, 2003 21 ISM Toronto, 2007

  22. Testing of GEWI-Pile at Tiptop Tailors Building, Toronto, 2003 22 ISM Toronto, 2007

  23. GEWI-Piles Applications – logistic advantages, continued.. 3) Tight and congested work areas – Irving Tissue Plant, Toronto, 2003 – University of Toronto CBTC, 2006 23 ISM Toronto, 2007

  24. GEWI-Pile Foundation for Irving Tissue Plant, Toronto, 2003 24 ISM Toronto, 2007

  25. GEWI-Pile Foundation for Irving Tissue Plant, Toronto, 2003 25 ISM Toronto, 2007

  26. University of Toronto CBTC, 2006 GEWI-Pile (2 x 63mm DCP), Compression tested to 325 Tons 26 ISM Toronto, 2007

  27. University of Toronto CBTC, 2006 27 ISM Toronto, 2007

  28. University of Toronto CBTC, 2006 28 ISM Toronto, 2007

  29. University of Toronto CBTC, 2006 29 ISM Toronto, 2007

  30. University of Toronto CBTC, 2006 30 ISM Toronto, 2007

  31. University of Toronto CBTC, 2006 31 ISM Toronto, 2007

  32. University of Toronto CBTC, 2006 32 ISM Toronto, 2007

  33. GEWI-Piles Applications – logistic advantages, continued 4) Piles in difficult soil conditions: - Big Qualicum Bridge, BC, 1996 - Vancouver International Airport, BC, 1994 - 2006 33 ISM Toronto, 2007

  34. Big Qualicum Bridge, Vancouver Island, BC, 1996 57Ø DYWIDAG GEWI-piles with Double Corrosion Protection (DCP) in aggressive soils. Length 13.0m 34 ISM Toronto, 2007

  35. Big Qualicum Bridge, Vancouver Island, BC, 1996 Sand, silts, gravel mixture with cobbles & boulders Pw = 1,200 KN Tested to 2,200 KN 57Ø DYWIDAG DCP bar 230Ø x 13 m in compression 35 ISM Toronto, 2007

  36. Big Qualicum Bridge, Vancouver Island, BC, 1996 Soil profile on each side of Arch 36 ISM Toronto, 2007

  37. Big Qualicum Bridge, Vancouver Island, BC, 1996 Pre-production load test of 57 Ø GEWI-Piles in compression Theoretical ultimate capacity of 57 Ø Threadbar 1780 kN Failure occurred in compression, above ground, at 2200 kN 37 ISM Toronto, 2007

  38. Big Qualicum Bridge, Vancouver Island, BC, 1996 Applied Load in Compression (kN) -1.0 0 500 1000 1500 2000 2500 1600 kN 800 kN 2200 kN -3.0 Depth (m) -5.0 -7.0 -9.0 -11.0 38 ISM Toronto, 2007

  39. Vancouver International Airport Compression Testing of Post- -grouted GEWI grouted GEWI- -Piles using adjacent piles Piles using adjacent piles Compression Testing of Post as reaction. as reaction. 39 ISM Toronto, 2007

  40. Vancouver International Airport 40 ISM Toronto, 2007

  41. Summary • 30 years of proven performance. • Bar size: 50Ø -> 75Ø, yeild load: 1,000kN -> 3,000kN • GEWI-Piles (Micropiles) provide cost-effective solution under difficult logistical conditions. • Multiple bars & steel pipe combination provide high capacity micropiles (up to 500 tons). • High-pressure postgrouting increases soil/grout bond by up to 3 times versus gravity grouting. • Double corrosion protection provides a reliable corrosion protection for GEWI-piles to assure long service life. 41 ISM Toronto, 2007

  42. Thank-you! 42 ISM Toronto, 2007

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend