Snap Lake Working Group De Beers update: North Pile, Paste and TDS - - PowerPoint PPT Presentation
Snap Lake Working Group De Beers update: North Pile, Paste and TDS - - PowerPoint PPT Presentation
MV2011L2-0004 Snap Lake Working Group De Beers update: North Pile, Paste and TDS Airstrip Emulsion Plant North Pile Disposal Facility Water Management Ammonium Nitrate Pond Storage Facility Former Construction Camp Fuel Storage
Airstrip Ammonium Nitrate Storage Facility Laydown Area Organics Pile North Pile Disposal Facility Camp Area Treated Water Discharge Warehouses and Workshops Intake Vent Raise Fuel Storage Facilities Emulsion Plant Water Management Pond Processing Facility Water Treatment Plant Mine Offices/Maintenance shops Former Construction Camp
Summary of Paste Research
Background
- Original Mine Design proposed the production of paste tailings
- Driver was to minimize environmental footprint
- It was envisaged that paste tailings would be used as follows:
- Placed underground as part of mine backfilling
- Placed at the tailings facility as part of an upstream construction approach.
- 50% Underground planned backfill
- Remainder placed in the North Pile (Processed Kimberlite containment facility)
Paste History
- Original paste plant not fully commissioned.
- Commissioning and paste project commenced 2010.
- Snap Lake Mine uses deep cone thickening.
- Significant early operational challenges were encountered.
- Only one other Diamond mine (of which we are aware) has successfully produced
Paste
- Kimberley Mines (South Africa) does not experience the harsh arctic environment
which presents its own challenges
5
Background and Initial Design of Snap Lake Paste System
6
Background 2001-2006
7
- 2001 AMEC engaged Mine Systems to undertake initial paste test work
- Large kimberlite particle size tended to break down during flow loop testing
- 2001-2005 Golder prepared the detailed design of the North Pile
- Snap Lake Mine carried out a review of the test work
- Golder contracted to review the paste backfill, and disposal system
Background 2007-2010
- Paste pipelines partially commissioned during initial project phase
- Pumping system was not fully constructed or commissioned
- Tailings deposition completed by pumping fine PK and trucking coarse and grits
- North Pile Starter Cell embankments constructed of coarse and grit PK
- Planned that upstream embankments would be constructed at the remaining
cells using full mix pk (paste)
- Paterson Cooke commissioned to audit the system
- Noted performance issues with deep cone thickening to produce sufficient density
to carry larger particle sizes without segregating
8
East Cell Perimeter Embankments
9
Background 2010-2011
10
Background 2010-2011
- Pipeline replaced with smaller diameter piping (200 mm to 150 mm) to increase
velocities
- Segregation of material occurring within the pipeline
11
Results and Conclusions
- Originally assumed that kimberlite would be disposed of via spigots at 2º inclined
beach
- Assumed that tailings would be of sufficient strength to allow for berm raises.
- Despite thickened nature of full paste mix with solids between 70—76% product
did not achieve required strengths
- Product has lows yields and does not stack due to lower than anticipated yield
stresses and rheology of the product
- Resulted in a change in pile construction to placement of coarse and grit
processed kimberlite
12
Advanced Stage Redesign
- 2012 addition of 1,500 m of piping to facilitate underground trials
- Engineer on site for three months to assist plant operators with performance
enhancements on trials
- Procedures were developed for operating the paste plant
- End of 2012 approval given for dedicated underground paste team
- Dedicated to constructing barricades and pipelines, monitoring pours etc.
13
Centrifuge Trial
- To improve paste densities, centifuge technology was trialed
- Intended to dewater material used in paste and improve control of solids
concentration in final product.
- Final product removed some untrafines , but showed good flow characteristics and
produced a cake with a density of 1.8 t/m³
- Subsequent testing completed demonstrated that rheology had changed since
initial testing commenced
- Variations in the kimberlite dyke and safety concerns required certified
engineered barricades be designed
14
2013 Updated Hydraulic Analysis and Mechanical Design- Underground
- First paste pour occurred in February 2013
- Ended early due to pressure causing concern over damaging the system
- Trials continued throughout the year
- Various percentages of cement were added to improve yield stresses (up to 2%)
- Progress improved with the addition of a dedicated crew
- Pressure testing later determined that the mechanical supports for the pipeline
needed to be redesigned
15
Technical Challenges
- Production of stable paste suitable for underground operation and tailings facility
is not possible for all ore types:
- Rheology of the ore not consistent producing low strength paste
- Variability of ore type, hence gradation, physical properties, and fluid characteristics.
- The tendency for kimberlite particles to break down in a pipe and flowing stream.
16
Layout of the Orebody and Underground Mine Workings
- Geometry of the orebody and layout of development make it a challenge to
achieve 50% backfill
- Shallow dipping dyke at 10-15º
- Modified room and pillar mining system
- Positive gradient of ore stopes
- Density Difference between intact rock and paste backfill
- Based on this, it is projected that less than 30% of processed kimberlite will be
deposited underground
17
Future of Paste Backfill
- Alternatives are currently being assessed
- Although only a small volume of backfill has successfully been placed, future work
will build upon successes to date
- 2014 work will include:
- Underground booster pump station design and
- Expanding under ground reticulation system
- Second centrifuge
18
Conclusion
- De Beers Snap Lake Mine has demonstrated that paste backfill can be placed in the
underground mine workings
- Paste tailings have been deposited in to the “North Pile” although the beach angles and
paste strength are lower than required to successfully be used for upstream embankment construction
- The Snap Lake Mine operator bench strength has increased
- Stope layouts and overall underground mine geometry and mining methods will make
attaining the required underground placement rates highly unlikely
- Continued testing and research in the future will be done on the rheology of the kimberlite
in order to ensure the safe and efficient underground deposition
19
Questions?
North Pile Update
North Pile Footprint
22
North Pile Current Status
- Deposition of PK slurry into the Starter cell commenced in the second half of 2007.
- Design and construction of the East Cell commenced in 2010
- First deposition into the East Cell was in 2012.
- The Starter cell has undergone three phased raises in the height since the original design.
- Cone penetration tests (CPT) were undertaken in the Starter Cell in the fourth quarter of
- 2013. Results indicate that further upstream increase in embankment height of the Starter
cell is at present not geotechnically feasible.
- DBCI expects production rates to increase above name plate rates over life of mine.
23
Estimated Dates for capacity to be met: Starter and East Cells
24
Present Situation and Future Requirements
- Currently in West Cell Design Phase
- The following conservative design assumptions and facts have been included for
the design of the North Pile extension:
- Waste host rock, and PK will be deposited on surface. Currently, it is estimated that
less than 30 % PK in the form of paste will be deposited underground for the remainder of the life of mine.
- Paste technology and paste strengths will not meet the requirements of the original
envisaged North Pile design requirements.
- Upstream heightening of the Starter cell embankments will not be geotechnically
- feasible. Although downstream options are feasible
25
West Cell Options
- To ensure that production operations are not disrupted the North Pile extension
needs to be constructed by the end of 2015.
- Several options are currently being considered to increase the North Pile capacity
for life of mine.
- Raising the height of the current Starter and East Cells by changing angle of
embankment slopes from 3:1 slope to 2:1 to facilitate a downstream embankment or
- Expanding the current North Pile footprint; or
- A combination of both.
26
High Level Timelines for West Cell Construction
- Geotechnical drilling and trenching
Completed 2013
- Detailed design and layouts
Ongoing
- Submission of design package to MVLWB for approval
Aug 2014
- Commence quarrying and excavation of water catchment structures
Q4 2014
- Construction of West Cell structure
2015
- Deposition into West cell
Q1 2016
- Conceptual studies into North Pile expansion
Ongoing
- Expansion designs and communication to regulators
2016/ 2017
27
Permitted Footprint
28
Draft Layout West Cell – Phase I
29
Conceptual Layout West Cell – Phase II
30
W1 W2 W3 W4
West Cell Footprint Options
31
Starter Cell Conceptual Expansions
32
East Cell Conceptual Expansions
33
Closure Conceptual
34
Questions?
Chloride Discussion
Objective
- Provide summary of chloride exceedence event April-May 2014
- Summarize management actions since November 2013
- Summarize planned management actions for future
- Effects on the environment
02-17b Chloride SNP Reportable Results Max Grab Limit: 620 mg/L Average Monthly Limit: 310 mg/L Date Grab (mg/L) AML (mg/L) 24-Mar-14 262 294 30-Mar-14 369 306 5-Apr-14 310 306 11-Apr-14 316 305 17-Apr-14 314 306 23-Apr-14 309 313 29-Apr-14 307 321 05-May-14 307 311 11-May-14 282 306 17-May-14 296 303
Sources of Chloride in Mine Effluent
- Chloride is a component of high TDS connate water released during
mining
- TDS of connate water is on average 5,000 mg/L
- Groundwater comprises ~ 10% of water managed underground
Connate Groundwater Recharge Structures
Sources of Chloride in Mine Effluent
- Connate water is not separated from other “dirty” water in the mine
workings
- Current practice to manage connate water is to dilute with recharge
water that enters mine workings from Snap Lake
- ~ 42,000 m3 effluent discharged to Snap Lake daily: 99% originates
from underground
Generalized Water Balance – Snap Lake Mine
Surface Water WMP & WTP
- North Pile Seepage
- Runoff
< 1% Fresh Water
- Potable
- Fire Suppression
< 1% U/G Mine Water
- Clear Water
- Dirty Water, including Connate
Water
99 %
- Recycled Water
- Treated Water
Effluent Discharge to Snap Lake
Management Actions to Date
- Source monitoring and update of groundwater models
- Increased groundwater monitoring has identified areas of potential
higher groundwater inflows
- Grouting trials for both full and selective source control
- Grouting to reduce loading from high TDS areas is technically
possible, but not practical
- Limited underground segregation of high TDS water
- Detailed studies to support appropriate and protective effluent
quality criteria per licence requirements
Management Actions – Current and Future
- Chloride is measured “end-of-pipe”; sample is sent to accredited lab
- In-line chloride meter has been installed and currently being
calibrated
- In-line conductivity is used to estimate chloride in effluent, and is
used as an internal management tool – recorded every 2 hours
- When upward trend is detected, some water can be held
underground.
- Approximately 4,000 m3 high TDS water is currently being held
underground in designated mine headings and sumps
- The temporary storage of water in mine headings renders makes
headings inaccessible
2 level
sumps
4x
Reactor/thickener /filters 15 sumps I
5
drainages
16x
15 sumps I 2
drainages
14x 6sumps/ 3
drainages
6x
MSS
Pump Station Trash Screens Smain sumps
2
sumps I
1
drainage 2x 11 sumps I
4
drainages lOx
1
sump I
1
drainage
lx
2
sumps I
1
drainage 2x
A B , C
Ramp Sumps
17x
Management Actions – Current and Future
- Engineering studies and pilot testing of options to remove TDS are
currently underway.
- Summary of investigations into treatment are summarized in IR#3-
1 of EA1314-02. Results of current pilot studies are expected to be known Q3-4 2014.
- Based on proven technologies
- Site-specific water quality objectives that are protective of the
environment have been proposed
Effects of Exceedance
- Results of site-specific toxicity studies undertaken as a
requirement of the water licence show that April-May exceedance will not cause harm to the environment
- Water remains safe to drink
- Review of proposed, higher effluent limits for chloride and TDS are