30 Abby Road Resource Consent Application Hearing Presentation of Evidence related to Stormwater Dav David Arse Arseneau, P.Eng. Site conditions Site conditions Site conditions Existing overland flow path High point on 30 Abby Road overflow
SLIDE 2
SLIDE 3
Site conditions
SLIDE 4
Site conditions
High point on 30 Abby Road property ~ 93.52 m to 93.60 m (excluding existing
- verland flow path), yellow
arrows indicate flow direction Existing overland flow path
- verflow elevation ~93.33 m
Greyscale pixels indicate elevation (2018 PNCC DEM), lighter colour indicates higher elevation Low point on Abby Road that creates flooding
SLIDE 5
Site conditions
- Min. elevation of ground on 30 Abby
Road property ~ 93.52 m to 93.60 m (excluding existing overland flow path) Existing overland flow path to PNCC Reserve north of 30 Abby Road Existing overland flow path
- verflow elevation ~93.33
m Existing low point at northern terminus of Abby Road (on 30 Abby Road property) ~92.97 m
SLIDE 6
Site conditions
Existing overland flow path to PNCC Reserve north of 30 Abby Road Existing overland flow path
- verflow elevation ~93.33 m