26 th street project
play

26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT - PowerPoint PPT Presentation

Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT 1 FINAL PRESENTATION | APRIL 13, 2010 Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL


  1. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT 1 FINAL PRESENTATION | APRIL 13, 2010

  2. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline I. Project Overview II. Introduction to Analyses III. Analysis I: Short Interval Production Scheduling IV. Analysis II: MEP Coordination V. Analysis III: Green Roof Design � � Structural Breadth Structural Breadth � Mechanical Breadth VI. Lessons Learned VII. Acknowledgements VIII. Questions 2

  3. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Project Overview Project Overview I. Project Overview � Location � 4763 Old Dominion Drive II. Introduction to Analyses � Arlington, VA III. Analysis I: Short Interval Production Scheduling � Owner IV. Analysis II: MEP Coordination � Marymount University y g V. Analysis III: Green Roof Design � Catholic University � Catholic University � Structural Breadth � 3,600 Students. � Mechanical Breadth � Project Goals VI. Lessons Learned � Expand Academic Spaces VII. Acknowledgements � Expand Student Housing VIII.Questions � Expand Parking Capacity 3

  4. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Project Overview Project Overview I. Project Overview � Occupancy Type � Residential, Business, Storage/Garage & Assembly II. Introduction to Analyses � Size III. Analysis I: Short Interval Production Scheduling � 267,000 Square Feet IV. Analysis II: MEP Coordination � Number of Stories y g V. Analysis III: Green Roof Design � (4) Below Grade Parking (3) Above Grade + Penthouse � (4) Below Grade Parking, (3) Above Grade + Penthouse � Structural Breadth � Construction Dates � Mechanical Breadth � April 2009 – September 2010 VI. Lessons Learned � Building Cost VII. Acknowledgements � $42 Million VIII.Questions � Delivery Method 4 � Design‐Bid‐Build w/ CM Agent

  5. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Project Overview Project Overview I. Project Overview � Residential Facility II. Introduction to Analyses � 62 Units Housing 239 Students � 77,000 Square Feet III. Analysis I: Short Interval Production Scheduling � Academic Facility IV. Analysis II: MEP Coordination � 52,000 Square Feet V. Analysis III: Green Roof Design y g � Laboratories Classrooms Offices � Laboratories, Classrooms, Offices � Structural Breadth � Below Grade Parking Garage � Mechanical Breadth � 138,000 Square Feet VI. Lessons Learned VII. Acknowledgements VIII.Questions 5

  6. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Project Team Project Team PROJECT TEAM I. Project Overview Owner: Marymount University II. Introduction to Analyses Owner's Representative/CM: Stranix Associates III. Analysis I: Short Interval Production Scheduling General Contractor: James G. Davis Construction Corp. Architect: Davis, Carter, Scott LTD. IV. Analysis II: MEP Coordination Structural Engineer: Structura, Inc. V. Analysis III: Green Roof Design y g MEP Engineer: GHT Limited � Structural Breadth Civil Engineer: VIKA Landscape Architect: Lewis Scully Gionet � Mechanical Breadth LEED Consultant: Sustainable Design Consulting VI. Lessons Learned Cast ‐ In Place Concrete Subcontractor: Brothers Concrete Construction, Inc. VII. Acknowledgements Pre ‐ Cast Concrete Subcontractor: Arban & Carosi Mechanical/Plumbing Subcontractor: Tyler Mechanical Contracting, Inc. VIII.Questions Electrical Subcontractor: Power Design, Inc. 6

  7. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Introduction to Analyses Introduction to Analyses I. Project Overview � Analysis I: Short Interval Production Scheduling II. Introduction to Analyses � Analysis II: MEP Coordination Techniques III. Analysis I: Short Interval Production Scheduling � Analysis III: Green Roof Design IV. Analysis II: MEP Coordination V. Analysis III: Green Roof Design y g � Structural Breadth � Mechanical Breadth VI. Lessons Learned VII. Acknowledgements VIII.Questions 7

  8. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Analysis I: Short Interval Production Scheduling Analysis I: Short Interval Production Scheduling I. Project Overview � Problem Statement: II. Introduction to Analyses � The repetitive nature of the activities involved with this phase of the project provides an opportunity to attempt to bring the efficiencies of III. Analysis I: Short Interval Production Scheduling the “manufacturing process” to the construction industry. IV. Analysis II: MEP Coordination V. Analysis III: Green Roof Design y g � Goal: � Structural Breadth � This type of work will allow the workforce to maximize their � Mechanical Breadth productivity, without sacrificing quality. In turn, this will create a VI. Lessons Learned schedule that is more predictable, easier to track, and easier to VII. Acknowledgements communicate. VIII.Questions 8

  9. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Current Project Schedule Current Project Schedule I. Project Overview � February 2010 – September 2010 II. Introduction to Analyses � 26 Week Duration � Dependent upon the Building Dry Milestone III. Analysis I: Short Interval Production Scheduling � February 19, 2010 IV. Analysis II: MEP Coordination � Involves all Interior Finish Activities for the Residential Facility V. Analysis III: Green Roof Design y g � Structural Breadth � Mechanical Breadth VI. Lessons Learned VII. Acknowledgements VIII.Questions 9

  10. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Current Project Schedule Current Project Schedule I. Project Overview � February 2010 – September 2010 II. Introduction to Analyses � 26 Week Duration � Dependent upon the Building Dry Milestone III. Analysis I: Short Interval Production Scheduling � February 19, 2010 IV. Analysis II: MEP Coordination � Involves all Interior Finish Activities for the Residential Facility V. Analysis III: Green Roof Design y g � Structural Breadth � Mechanical Breadth VI. Lessons Learned VII. Acknowledgements VIII.Questions 10

  11. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Building Zones Level Zones Occupancy G3 5 26 Presentation Outline Presentation Outline Development of a SIP Schedule Development of a SIP Schedule G2 G2 7 7 36 36 G1 7 36 L1 9 42 L2 12 53 I. Project Overview � Break the Building down into Zones/Sections L3 12 53 Totals 52 246 II. Introduction to Analyses � 52 Zones, In Total � 1 Zone ~ 900 Square Feet III. Analysis I: Short Interval Production Scheduling IV. Analysis II: MEP Coordination V. Analysis III: Green Roof Design y g � Structural Breadth � Mechanical Breadth VI. Lessons Learned VII. Acknowledgements VIII.Questions 11

  12. Marymount University 26 TH STREET PROJECT BENJAMIN J. MAHONEY | CONSTRUCTION MANAGEMENT FINAL PRESENTATION | APRIL 13, 2010 Presentation Outline Presentation Outline Development of a SIP Schedule Development of a SIP Schedule Number Number Number Number Color Color Color Color Critical Activity Critical Activity Critical Activity Critical Activity 1 1 Frame Metal Studs Frame Metal Studs 2 2 Rough ‐ In MEP Rough ‐ In MEP I. Project Overview � Break the Building down into Zones/Sections 3 3 Preform In Wall QC Preform In Wall QC II. Introduction to Analyses � 52 Zones, In Total 4 4 Hang/Tape/Finish GWB Hang/Tape/Finish GWB � 1 Zone ~ 900 Square Feet III. Analysis I: Short Interval Production Scheduling 5 5 Prime Walls Prime Walls � Determine the Sequence of the Critical Path IV. Analysis II: MEP Coordination 6 6 Point ‐ Up Drywall Point ‐ Up Drywall V. Analysis III: Green Roof Design y g 7 7 Paint Final Coat Paint Final Coat � Structural Breadth 8 8 Install Ceramic Tile Install Ceramic Tile � Mechanical Breadth 9 9 Install Plumbing Fixtures Install Plumbing Fixtures VI. Lessons Learned 10 10 Install Millwork & Countertops Install Millwork & Countertops VII. Acknowledgements 11 11 Install VCT & Carpet Install VCT & Carpet VIII.Questions 12

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend