PROJECT NO. T-841017.83 SE Adams Street - SE 37 th Street to SE 33 rd - - PowerPoint PPT Presentation

project no t 841017 83
SMART_READER_LITE
LIVE PREVIEW

PROJECT NO. T-841017.83 SE Adams Street - SE 37 th Street to SE 33 rd - - PowerPoint PPT Presentation

PROJECT NO. T-841017.83 SE Adams Street - SE 37 th Street to SE 33 rd Street Project Contacts City of Topeka Engineering Division Project Manager - Robert Bidwell, PE 368-3824 Community Information Manager - David Bevens 368-1642


slide-1
SLIDE 1

PROJECT NO. T-841017.83

SE Adams Street - SE 37th Street to SE 33rd Street

slide-2
SLIDE 2

Project Contacts

City of Topeka – Engineering Division Project Manager - Robert Bidwell, PE – 368-3824 Community Information Manager - David Bevens – 368-1642 Consulting Engineer Finney & Turnipseed Transportation & Civil Engineering, L.L.C. Project Manager - Craig Mattox, PE, PLS – 235-2394 Project Engineer – Tim Reed, PE – 235-2394

slide-3
SLIDE 3

Project Scope of Work

  • Replace existing 8”+ concrete pavement and curb &

gutter with new 10” Concrete Pavement and curb & gutter

  • n an aggregate base including driveways (to the

sidewalk) and sidewalk ramps at the intersections.

  • Replace deteriorated storm sewer inlets and inlet tops.
  • Replace existing corrugated metal storm sewer pipes with

reinforced concrete pipe.

slide-4
SLIDE 4

Project Phasing

  • Road to be closed to thru traffic. Thru traffic will be

carried on signed detour.

  • Properties abutting Adams between SE 37st to SE 33rd

will be carried to side streets on existing pavement or one lane access roads to side streets. Once new pavement is in place, residents will park on the new pavement until the pavement and driveways in front of their properties is constructed.

slide-5
SLIDE 5

Project Detour Route

slide-6
SLIDE 6

Project Bus Detour Route Tentative

  • Regular route to 29th & Adams (temporary bus stop)
  • West on 29th to Freemont
  • South on Freemont to Golf Park
  • East on Golf Park to Colfax (Avondale-temporary bus stop)
  • East on Golf Park to Adams
  • North back onto normal route
slide-7
SLIDE 7

During Construction

  • Properties that abut Adams Street will have temporary

mailboxes relocated to a central location as per the Post

  • Master. Permanent mailboxes will be reinstalled after

completion of the work.

  • Trash containers will be pick up weekly by the Contractor

and taken to a location for disposal by the trash hauling

  • companies. Make sure the cans are out when they are usually

to be picked up.

  • If there is a problem or concern, seek out the Contractor’s

superintendent or the project inspector first.

slide-8
SLIDE 8

Project Schedule

The current schedule for the project is;

  • Late February 2019 – Let project
  • Late March 2019 – Start work
  • October 2019 – Project to be complete
slide-9
SLIDE 9

THANK YOU FOR COMING TODAY! QUESTIONS ?