ISO Confidential
2018 ISO LCR Study Criteria, Methodology, and Assumptions
Catalin Micsa Senior Advisor Regional Transmission Engineer Stakeholder Web Conference October 31, 2016
2018 ISO LCR Study Criteria, Methodology, and Assumptions Catalin - - PowerPoint PPT Presentation
2018 ISO LCR Study Criteria, Methodology, and Assumptions Catalin Micsa Senior Advisor Regional Transmission Engineer Stakeholder Web Conference October 31, 2016 ISO Confidential Agenda Introductions General Resource Adequacy (RA)
ISO Confidential
Catalin Micsa Senior Advisor Regional Transmission Engineer Stakeholder Web Conference October 31, 2016
ISO Confidential 2
ISO Confidential 3
ISO Confidential
ISO Confidential 5
ISO Confidential 6
ISO Confidential 7
ISO Confidential 8
Total RA Requirements Imports Minimum Local Resources MW Any other resources within the CAISO control area not needed as Minimum Local Resources 115-117% Of System Peak Load
ISO Confidential 9
First N-1
Loading Within A/R (normal) Loading Within A/R (emergency)
Manual adjust per NERC P6 in order to support the Loss of the next element.
“LCR Category B or P1&3”
Second trip
A or P0 C3 or P6 (N-1-1) B or P1&3 (N-1)
Planned and Controlled Load Shedding Allowed
Loading Within A/R (emergency)
“LCR Category C or P6&7”
Load Shedding Not Allowed
C5 or P7 (N-2) A or P0 (N-0)
Loading Within A/R (emergency) Loading within A/R (normal) as well as making sure the system can support the loss of the most stringent next single element or credible double and be within post-contingency A/R (emergency).
ISO Confidential 10
ISO Confidential 11
ISO Confidential
ISO Confidential 13
ISO Confidential 14
LCR Area - L.A. Basin
Lugo Substation
GEN GEN GEN LOAD LOAD
path rating
push back to relieve overload & balance load
South of Lugo Limits Limit LCR Path Rating 6,400 MW 10,589 MW Thermal Rating 13,848 MVA ?
South of Lugo Path
ISO Confidential 15
ISO Confidential
ISO Confidential 17
ISO Confidential 18
ISO Confidential 19
Deliverability of generator outside the LCR area is enforced under normal A or P0 (N-0), single B or P1 (N-1), and common mode C5 or P7 (N-2) contingencies. For C3 or P3&P6 (N-1-1), immediately after the first contingency any unit (subject to maximum MW number) can be decremented as part of the manual adjustment.
GEN
LCR AREA
deliverable level such as 100%
GEN GEN GEN
to relieve overload & balance load
LOAD LOAD
deliverable unit and increase import from another line into LCR area to relieve overload
ISO Confidential 20
LCR AREA
dispatched at deliverable level
GEN GEN GEN
to relieve overload & balance load
LOAD LOAD
ISO import and increase flows from another line into LCR area to relieve
Deliverability of generator outside the LCR area is enforced under normal A or P0 (N-0), single B or P1 (N-1), and common mode C5 or P7 (N-2) contingencies. For C3 or P3&P6 (N-1-1), immediately after the first contingency any import (subject to maximum MW number) can be decremented as part of the manual adjustment.
ISO Confidential 21
ISO Confidential 22
ISO Confidential 23
ISO Confidential
ISO Confidential 25
ISO Confidential 26
ISO Confidential 27
ISO Confidential 28
ISO Confidential
ISO Confidential 30
ISO Confidential
ISO Confidential 32
ISO Confidential
ISO Confidential 34
ISO Confidential 35
ISO Confidential 36
ISO Confidential
ISO Confidential 38
ISO Confidential
ISO Confidential 40