SLIDE 10 2018-19 School Readiness: Update for RPS School Boar 2018-19 School Readiness: Update for RPS School Board d
10
Final Operations Update
Richmond Public Schools | September 4, 2018
In addition to emergency maintenance (fixing/repairing chillers and ACs, addressing leaks, etc.,) we have completed:
Locks – Upgraded security measures at Francis and Henderson.
ee removal emoval – Removed downed trees from Swansboro, Broad Rock, Munford, Cary, Green, and Fisher.
Bathr hrooms
- oms – Replaced 200 paper towel dispensers, 150 toilet paper dispensers, 150 soap dispensers, 260 faucets,
170 sinks, 20 stall doors, 200 stall locks, 3 toilets/urinals, and 100 ceiling tiles. Painted 41 bathrooms. This work will continue into the school year as we continue to make improvements in our bathrooms.
arious Structural Projects:
- jects:
- Replaced all windows (100) and doors (21) at Overby-Sheppard.
- Completed the Fairfield Court and Westover Hills roof projects.
- Installed two modular units at William Fox and assembled/delivered furniture for the units.
- Completed the Huguenot gym project.
- Replaced 40 window AC units in schools.
- Replaced over 400 ballasts to improve lighting in schools.