2017 LGA 191/192 & 195 Pipeline Safety Conference
Presented by: Wallace Jones Director, Gas Pipeline Safety Division Alabama Public Service Commission
2017 LGA 191/192 & 195 Pipeline Safety Conference Presented by: - - PowerPoint PPT Presentation
2017 LGA 191/192 & 195 Pipeline Safety Conference Presented by: Wallace Jones Director, Gas Pipeline Safety Division Alabama Public Service Commission Issu Issues tha that GPS/PSC GPS/PSC St Staf aff ar are ha havi ving ng wi with Pip
Presented by: Wallace Jones Director, Gas Pipeline Safety Division Alabama Public Service Commission
What’s wrong with this picture?
How do we fix this?
We get the spare tire out right?
Solution: Inspect your spare every time you service your vehicle
What about this one?
Wh What at do do we we do do no now? w?
game?
Refer to your O&M and Emergency Plan
REVIEWED and UPDATED by the
15 months, but at least once each calendar year. Also Submit to APSC
Must be kept at locations where
activities are conducted.
How do we know these Manuals aren’t being Reviewed, Revised or Followed?
their inspector
allows
Items that are late or not submitted at all
Especially if Media is Involved
At Atmospheric Corr Corrosi
192.481 192.481
Atmospheric Corrosion continued 192.481
Then the frequency of inspection is: At least once every 3 calendar years, but with intervals not exceeding 39 months
Then the frequency of inspection is: At least once each calendar year, but with intervals not exceeding 15 months
At Atmospheric Corr Corrosi
nued 192.481 192.481
attention to pipe at soil‐to‐air interfaces, under thermal insulation, under disbonded coatings, at pipe supports, in splash zones, at deck penetrations, and in spans over water.
inspection, the operator must provide protection against the corrosion as required by Sec. 192.479.
Cathodic Protection
Cathodic Protection
including pipe, valves, and other appurtenance attached to pipe, compressor units, metering stations, regulator stations, delivery stations, holders, and fabricated assemblies. that is under cathodic protection must be tested at least once each calendar year, but with intervals not exceeding 15 months, to determine whether the cathodic protection meets the requirements
sections of mains or transmission line a pipeline, other than a gathering line, that: (1) Transports gas from a gathering line or storage facility to a gas distribution center, storage facility, or large volume customer that is not down‐stream from a gas distribution center; (2)
field., not in excess of 100 feet (30 meters See Customer meter, Meter set assembly. (Guide definition)), or separately protected service line a distribution line that transports gas from a common source of supply to an individual customer, to two adjacent or adjoining residential or small commercial customers, or to multiple residential or small commercial customers served through a meter header or manifold., these pipelines may be surveyed on a sampling basis. At least 10 percent of these protected structures, distributed over the entire system must be surveyed each calendar year, with a different 10 percent checked each subsequent year, so that the entire system is tested in each 10‐year period.
Cathodic Protection Mapping
maps to show the location of cathodically protected piping, cathodic protection facilities, galvanic anodes, and neighboring structures bonded to the cathodic protection
number of anodes, installed in a stated manner or spacing, need not show specific distances to each buried anode.
Cathodic Protection Deficiencies
correct any deficiencies indicated by the monitoring.
REVIEW REVIEW Wh What at ar are som some Issues Issues we we ar are ha having ving wi with Oper Operator
actually reviewing or updating the programs
consideration prior to their next inspection
not it’s reportable (especially when the media is present)
Issues continued
2. Does the Emergency Plan meet the following requirements
a. Has the plan been reviewed and updated at intervals not exceeding 15 months but at least
§192.605(a). 1. Does the Plan provide for receiving, identifying, and classifying notices of events which require immediate response?
2. Has the Operator established and maintained adequate means of communication with appropriate fire, police, and other public officials?
b. Have responsible supervisors been trained and furnished the 13 parts of this part? When was the most current training? Ref. 192.615(b). c. Has Operator established and maintained liaison with appropriate public officials? Ref. 192.615(c).
Some Programs Operators are using to address the Appropriate Stakeholders
APACT (Alabama Pipeline Awareness Cooperative Training ‐
Conducted by Alabama 811 and sponsored by local operators)
Paradigm CGA (Common Ground Alliance) Other
35. Does the Operator's Public Awareness Program meet the requirements of §192.616? a. Has the Operator evaluated the PAP for effectiveness as described in RP1162? b. Did the operator deliver messages to the following stakeholders: 1. Affected Public? 2. Emergency Officials? 3. Local Public Officials? 4. Excavators? 5. Municipalities, Schools Districts, Businesses, and Residents?
Coordinated with first responders and city school board Held emergency drill based on report of natural gas leak Had all students evacuated and accounted for in 8 minutes Prior Planning: Mapping of all gas in area of schools Staging areas for students and staff designated away from gas lines Staging areas for first responders designated to limit traffic and allow access for emergency vehicles
For additional information, contact Brent Wilson Roanoke Utilities Board (334) 863‐4055 (6)
Gash in pipe about to be covered up
Tracer wire wrapped around pipe
Dragging pipe on asphalt/rocks
Additional Construction Issues Lack of certification for plastic fusion Lack of procedures on job site Lack of qualified inspector on job site Dirty/non‐functioning tools being used for fusion Not checking temperature with a pyrometer ‐ relying on temperature gauge on fusion iron