2 nd Street Improvement Project August 18, 2015 SFMTA Board of - - PowerPoint PPT Presentation

2 nd street improvement project
SMART_READER_LITE
LIVE PREVIEW

2 nd Street Improvement Project August 18, 2015 SFMTA Board of - - PowerPoint PPT Presentation

2 nd Street Improvement Project August 18, 2015 SFMTA Board of Directors Project Team Project Location Project Goals 1. Improve Safety & Accessibility 2. Promote Walking, Bicycling, and Transit 3. Reduce vehicles accessing I-80 from


slide-1
SLIDE 1

2nd Street Improvement Project

August 18, 2015 SFMTA Board of Directors

slide-2
SLIDE 2

Project Team

slide-3
SLIDE 3

Project Location

slide-4
SLIDE 4

Project Goals

  • 1. Improve Safety &

Accessibility

  • 2. Promote Walking,

Bicycling, and Transit

  • 3. Reduce vehicles accessing

I-80 from 2nd Street

  • 4. Rehabilitate and replace

sewer and pavement

slide-5
SLIDE 5

2nd Street Today

slide-6
SLIDE 6

6

Pedestrians Bicyclists

Vision Zero

slide-7
SLIDE 7

Community Involvement

  • 4 community meetings
  • Accessibility

Workshop

  • Door to door outreach

to businesses and residents

  • Intercept Survey
  • Presentations to Home

Owners Associations

slide-8
SLIDE 8

Project Elements

  • Repaving and Sewer Repair
  • Pedestrian Safety

Improvements

  • Bikeway Improvements
  • Transit Improvements
  • Public Realm Improvements
slide-9
SLIDE 9

9

Pedestrian Safety Improvements

  • High-visibility

Crosswalks

  • “Daylighting” near

intersections

  • Ramp Improvements
  • Additional Signal &

RRFB

slide-10
SLIDE 10

Bikeway Improvements

slide-11
SLIDE 11

11

Bikeway Improvements

slide-12
SLIDE 12

Transit Improvements

  • Transit Boarding Islands
  • Transit Signal Priority
  • Bus Stop Relocation
  • Right-turn lanes
  • Left-turn restrictions
slide-13
SLIDE 13

Public Realm Improvements

Pedestrian Scaled Street Lighting Bike Racks and Benches Market to Harrison Street Trees

slide-14
SLIDE 14

Parking and Driving

  • Deemphasize 2nd Street

as route to freeway

  • Floating parking
  • Prioritize commercial and

passenger loading

  • Coordination with

TransBay Terminal

14

slide-15
SLIDE 15

Education and Enforcement

15

  • Promote Safe and Proper

Use

– Outreach Materials – PCOs

  • Targeted Traffic

Enforcement

slide-16
SLIDE 16

Project Timeline

Planning: 2012-2013 Environmental Review:

– 2013- 2015 (complete)

Detailed Design:

– Winter 2015

Construction:

– Start (est) Fall 2016

slide-17
SLIDE 17

Early Implementation

  • Painted Safety Zones
  • High-Visibility

Crosswalks

  • Bikeway

Improvements

slide-18
SLIDE 18

Thank you!