1 santa fe county project team
play

1 Santa Fe County Project Team Ed Moreno, County Commissioner Tony - PowerPoint PPT Presentation

1 Santa Fe County Project Team Ed Moreno, County Commissioner Tony Flores, Deputy County Manager Mike Kelley, P.E. Public Works Director Robert Martinez - Public Works Deputy Director Diego Gomez, P.E. Projects Engineer


  1. 1

  2. Santa Fe County Project Team  Ed Moreno, County Commissioner  Tony Flores, Deputy County Manager  Mike Kelley, P.E. – Public Works Director  Robert Martinez - Public Works Deputy Director  Diego Gomez, P.E. – Projects Engineer  Steven “Justin” Reese - Project Manager III  Terry Lease – Real Property Specialist  Penny Ellis Green – Growth Management Director  Vicki Lucero – Building & Development Manager 2

  3. Commissioner Ed Moreno 3

  4. Alignment/Corridor Study Phase A, B, C- Completed Phase A - Alternative Identification and Screening Phase B – Detailed Alternative Analysis Phase C – Environmental Documentation Phase D- Preliminary Design 4

  5. Phase A Alternate Identification and Screening A1 - Existing Conditions and Constraints A2 - Agency Coordination and Public Involvement A3 - Establish Purpose and Need A4 - Development of Study Alternative A-5 – Initial Screening of Alternatives 5

  6. Phase A Alternatives 6

  7. Phase B Detailed Alternative Analysis B1 - Detailed Evaluation of Alternatives B2 - Engineering Refinement of Preferred Alternative B3 – Alternative Analysis Report 7

  8. Phase B Preferred Alternatives NE Connector No Build 8

  9. 9

  10. Phase B Recommendations NE Connector SE PNM Utility Easement 10

  11. 11

  12. Phase C Environmental Documentation C1 - Prepare Resource Reports and Agency Consultation C2 – Prepare Environmental Documentation C3 – Final Environmental Certification C4 – Environmental Re-evaluation 12

  13. Phase C Clearance Map 13

  14. 14

  15. 15

  16. Conceptual Design 16

  17. Existing Easements and ROW 17

  18. Existing 124 Foot Easement Plat book 250 page 21 18

  19. Existing 124 Foot Easement Plat book 250 page 21 19

  20. Existing 124 Foot Easement Plat book 677 page 46 20

  21. Existing 68 Foot ROW Along College Drive Plat Book 778 page 49 21

  22. Existing 68 Foot ROW Along College Drive Plat Book 778 page 49 22

  23. Project Timeline  Engineering Design - Start December 2018  Engineering Design - Complete December 2019  Construction Start – March 2020  Construction Complete – October 2021  100% County Funded  2012 GOB and 2016 GOB 23

  24. Project Considerations  Environmental Commitments  Project Cost  Right of Way Required  Topography/ Drainage Structures Required  Traffic Flow/Connectivity  Intersection Improvements 24

  25. Prior Developer Commitments 25

  26. St. Francis South Santa Fe County Land Use Case S10-5364 Recorded 1/17/2017 Note 8. A revised an updated TIA reflecting current road conditions shall be submitted with the Preliminary design Plat/Development Plat for Phase 2 and shall include timing of improvements and complete road design for build-out of the development. Note 9. The road design for the right turn deceleration lane on rabbit road must be submitted with the Final Plat/Development Plan for Phase 26

  27. Elevation Multi Family Community CDRC Case #APP13-5382 and CRDC Case #V/DP 13-5381 Recorded 1/13/2016 Note 4. The Applicant shall construct College Drive, to CCDO standard, from its current terminus at Burnt Water to the western boundary to the future Southeast Connector right-of- way, Ordinance No. 2000-12, section 6.E.3.b Note 6. Construction may begin but Elevation is not permitted occupancy until the Southwest Connector is completed. 27

  28. Saleh Master Plan CRDC CASE # V/MP 14-5490 Recorded 10/22/2015 The design of a left turn lane and right turn deceleration lane on Richards Avenue shall be submitted with the Preliminary Development Plan application, as per article V, Section 7.2 28

  29. Questions And Answers 29

  30. Contact: Steven “Justin” Reese Santa Fe County (505) 986-6271 sjreese@santafecountynm.gov

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend