1 Santa Fe County Project Team Ed Moreno, County Commissioner Tony - - PowerPoint PPT Presentation

1 santa fe county project team
SMART_READER_LITE
LIVE PREVIEW

1 Santa Fe County Project Team Ed Moreno, County Commissioner Tony - - PowerPoint PPT Presentation

1 Santa Fe County Project Team Ed Moreno, County Commissioner Tony Flores, Deputy County Manager Mike Kelley, P.E. Public Works Director Robert Martinez - Public Works Deputy Director Diego Gomez, P.E. Projects Engineer


slide-1
SLIDE 1

1

slide-2
SLIDE 2

Santa Fe County Project Team

 Ed Moreno, County Commissioner  Tony Flores, Deputy County Manager  Mike Kelley, P.E. – Public Works Director  Robert Martinez - Public Works Deputy Director  Diego Gomez, P.E. – Projects Engineer  Steven “Justin” Reese - Project Manager III  Terry Lease – Real Property Specialist  Penny Ellis Green – Growth Management Director  Vicki Lucero – Building & Development Manager

2

slide-3
SLIDE 3

Commissioner Ed Moreno

3

slide-4
SLIDE 4

Alignment/Corridor Study

Phase A, B, C- Completed

Phase A - Alternative Identification and Screening Phase B – Detailed Alternative Analysis Phase C – Environmental Documentation Phase D- Preliminary Design

4

slide-5
SLIDE 5

Phase A

Alternate Identification and Screening

A1 - Existing Conditions and Constraints A2 - Agency Coordination and Public Involvement A3 - Establish Purpose and Need A4 - Development of Study Alternative A-5 – Initial Screening of Alternatives

5

slide-6
SLIDE 6

Phase A Alternatives

6

slide-7
SLIDE 7

Phase B

Detailed Alternative Analysis

B1 - Detailed Evaluation of Alternatives B2 - Engineering Refinement of Preferred Alternative B3 – Alternative Analysis Report

7

slide-8
SLIDE 8

Phase B Preferred Alternatives

NE Connector No Build

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10

Phase B Recommendations

NE Connector SE PNM Utility Easement

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

Phase C

Environmental Documentation

C1 - Prepare Resource Reports and Agency Consultation C2 – Prepare Environmental Documentation C3 – Final Environmental Certification C4 – Environmental Re-evaluation

12

slide-13
SLIDE 13

Phase C Clearance Map

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

Conceptual Design

16

slide-17
SLIDE 17

Existing Easements and ROW

17

slide-18
SLIDE 18

Existing 124 Foot Easement Plat book 250 page 21

18

slide-19
SLIDE 19

Existing 124 Foot Easement Plat book 250 page 21

19

slide-20
SLIDE 20

Existing 124 Foot Easement Plat book 677 page 46

20

slide-21
SLIDE 21

Existing 68 Foot ROW Along College Drive Plat Book 778 page 49

21

slide-22
SLIDE 22

Existing 68 Foot ROW Along College Drive Plat Book 778 page 49

22

slide-23
SLIDE 23

Project Timeline

Engineering Design - Start December 2018 Engineering Design - Complete December 2019 Construction Start – March 2020 Construction Complete – October 2021 100% County Funded 2012 GOB and 2016 GOB

23

slide-24
SLIDE 24

Project Considerations

Environmental Commitments Project Cost Right of Way Required Topography/ Drainage Structures Required Traffic Flow/Connectivity Intersection Improvements

24

slide-25
SLIDE 25

Prior Developer Commitments

25

slide-26
SLIDE 26
  • St. Francis South

Santa Fe County Land Use Case S10-5364 Recorded 1/17/2017

Note 8. A revised an updated TIA reflecting current road conditions shall be submitted with the Preliminary design Plat/Development Plat for Phase 2 and shall include timing of improvements and complete road design for build-out of the development. Note 9. The road design for the right turn deceleration lane on rabbit road must be submitted with the Final Plat/Development Plan for Phase

26

slide-27
SLIDE 27

Elevation Multi Family Community

CDRC Case #APP13-5382 and CRDC Case #V/DP 13-5381 Recorded 1/13/2016

Note 4. The Applicant shall construct College Drive, to CCDO standard, from its current terminus at Burnt Water to the western boundary to the future Southeast Connector right-of- way, Ordinance No. 2000-12, section 6.E.3.b Note 6. Construction may begin but Elevation is not permitted

  • ccupancy until the Southwest Connector is completed.

27

slide-28
SLIDE 28

Saleh Master Plan

CRDC CASE # V/MP 14-5490 Recorded 10/22/2015 The design of a left turn lane and right turn deceleration lane

  • n Richards Avenue shall be submitted with the Preliminary

Development Plan application, as per article V, Section 7.2

28

slide-29
SLIDE 29

Questions And Answers

29

slide-30
SLIDE 30

Contact: Steven “Justin” Reese Santa Fe County (505) 986-6271 sjreese@santafecountynm.gov