1 puainako street widening second public information
play

1 PUAINAKO STREET WIDENING SECOND PUBLIC INFORMATION MEETING - PowerPoint PPT Presentation

1 PUAINAKO STREET WIDENING SECOND PUBLIC INFORMATION MEETING AUGUST 8, 2013 WAIAKEA INTERMEDIATE SCHOOL Purpose of This Meeting 2 Update the community on the status of the project and provide an overview of the progress since the first


  1. 1 PUAINAKO STREET WIDENING SECOND PUBLIC INFORMATION MEETING AUGUST 8, 2013 WAIAKEA INTERMEDIATE SCHOOL

  2. Purpose of This Meeting 2  Update the community on the status of the project and provide an overview of the progress since the first public meeting  Explain where we are now with the Environmental Impact Statement re-evaluation process and steps moving forward  Present the revisions made to the typical roadway sections along various portions of the alignment

  3. Purpose & Need For The Pro j ect 3  This area is identified as a corridor deficiency in the 1998 Hawaii Long Range Transportation Plan  Address congestion  Improve vehicle and pedestrian safety on existing Puainako Street  Improve arterial traffic flows by connecting the existing Puainako Street with Saddle Road  Create a direct route between East and West Hawaii

  4. Pro j ect History 4 1992 2004 2000 Contract to design both Upper Portion 1993 Federal EIS completed widening and extension and Record of Decision (Puainako Street State Environmental of existing Puainako Extension) Impact Statement signed – Selected Street initiated by Construction (EIS) completed Alignment 10 (Upper) County of Hawai‘i Complete and Alignment B (Lower) 2005 Due to procurement 2010 laws the County October 2012 2009 EIS Re- Design Contract for Public New Consultant Evaluation and Lower Portion was Informational hired under Roadway terminated and the Meeting #1 State Contract Design Initiated search for a new Consultant was initiated August 2013 Public Informational Meeting #2

  5. Project Location and Limits 5 Waiakea Begin Project Intermediate Waiakea Elementary End Project Phase 2 Phase 1 Project Length: Approximately 1.5 miles

  6. Existing Concerns 6 Naniakea St. Intersection (Looking Kinoole St. Intersection (Looking North) West/Mauka) Unsignalized intersections slow traffic flow  Sight distance  and create potential conflicts Intersection sight distance is not optimal  3 Intersections (North side) to Waiakea Schools at some locations.  More than 20 existing driveway connections Roadside obstructions present potential   concerns for motorists and pedestrians. 7 side streets (south side) from subdivisions 

  7. Existing Concerns 7 Pedestrian access  No raised sidewalks (only intermittent  asphalt curbing) No bike lanes  Many roadside utilities including  telephone poles and associated anchors are obstacles for pedestrians Traffic  Congestion at Kinoole and Kilauea  intersections during school drop off/pick up hours Increase in thru traffic due to Saddle Road  improvements

  8. Existing Concerns 8 Recent and Future  Developments near and along Puainako: Imiloa Astronomy Center  Expansion of University of  Hawai‘i - Hilo University Village – Phase 1  Pacific Basin Agricultural  Research Center New University of Hawaii  Saddle Road Community College Campus

  9. EIS Re-Evaluation 9 Initiated in 2010 to determine if the Final EIS and Record of Decision were adequate or if a Supplemental EIS would be needed for this project. The US Department of Transportation (USDOT) and the Federal Highway Administration (FHWA) require re- evaluation if “major steps to advance project” have not occurred within 3 years after issuance of EIS.

  10. MAP OF ALIGNMENTS CONSIDERED IN FEIS Portion Constructed In 2004 10

  11. EIS Re-Evaluation 11  Considerations Include Changes Since 2000: Project design  Project traffic  The physical, natural, and social environment  Legislative and regulatory requirements   Evaluation is specific to the Lower Portion since the Upper Portion was constructed in 2004.  Mitigation measures identified in Final EIS and Record of Decision must be followed in addition to those outlined in the Re-evaluation document.

  12. Proposed Alignment & Design Features 12  Improved segment will extend between Komohana St. and Kekela Street (just east of Kilauea).  Improvements:  Crosswalks  Intersection Upgrades  Traffic Signals  ADA provisions  Drainage enhancements  Improved sight distance  Noise barrier walls  Retaining walls  Lighting Upgrades  Buffer Zones

  13. Design Changes Since Previous Public Information Meeting 13  Revised Lane Width from 12’ to 11’  Increased Buffer Zone Between Properties and Travel Lanes  Potential Reduction in Noise  Retaining Wall Heights Reduced  Increased Area Available for Drainage Collection  Potential for Accommodating Utility Poles Outside of Sidewalk Areas

  14. DISPLAY DESCRIPTIONS 14  STATION 1 – PROJECT LOCATION AND ROADWAY PLAN VIEW EXHIBITS 3 RESIDENTIAL DISPLACEMENTS Existing homes that will be displaced with project.

  15. DISPLAY DESCRIPTIONS 15 STATION 2 – Section 106 Information 

  16. DISPLAY DESCRIPTIONS  STATION 3 – Roadway typical sections incorporating revisions since last Public Information meeting 16

  17. DISPLAY DESCRIPTIONS 17 STATION 4: Access Routes to and from Affected Areas 

  18. Potential Impacts to Property Owners Due to Widening and/or Realignment 18  Some property frontages adjacent to the roadway improvements will be impacted  Partial loss of existing parking areas for businesses, schools, and churches along the existing Puainako St.  3 homes might be affected.  The back of 32 lots adjacent to the realignment may be impacted  Noise levels may increase along corridor for properties where improvements move traffic lanes closer to homes/ businesses  Access to Puainako Street will be altered for property owners adjacent to the realigned roadway.

  19. Proposed Mitigation to Decrease Impacts 19 Potential Impacts During Construction: Land Issues: Traffic (Mitigation: construction of section in  front of Waiakea schools shall be Construct retaining walls (4’ - 10’) to  scheduled for summer vacation as much as reduce the size and number of possible) easements and acquisitions Noise (Mitigation: contractor to apply for  noise permit which may include mitigation Optimize vertical alignment to limit  measures, such as restriction of equipment impacts to property owner access to type during restricted hours) Puainako St. Utilities (Mitigation: construction schedule  to minimize length of time utility customers are inconvenienced) Provide noise barriers where justified  Dust (Mitigation: wind screens, watering of *Noise barriers are different than  active work areas, etc.) retaining walls in that their purpose is to decrease noise levels and not retain Sediment pollution (Mitigation: time certain  construction activities during periods of soil. minimal rainfall)

  20. Section 106 Consultation 20  Requires the federal agencies to take into account the effects of undertakings on historic properties through consultation with parties with an interest in the effected historic properties.  Recognizes Native Hawaiian Organizations (NHOs) and requires consultation with NHOs that attach religious and cultural significance to historic properties that may be affected by the undertaking  Goals  Identify historic properties potentially affected by an undertaking  Assess the effects  Seek ways to AVOID, MINIMIZE or MITIGATE any adverse effects on historic properties

  21. Section 106 Update 21  A Memorandum of Agreement (MOA) was completed in 2000. It included the following stipulations on existing historic sites:  State Sites (50-10-35) 1814, 18915, and 18917 to be PRESERVED IN PLACE and protected during construction with TEMPORARY FENCING.  No further data recovery necessary for State Sites (50-10-35) 18911, 18912, 18916, 18919, 18921, 18922, 18923, and 20681.  MOA signatories include FHWA, HDOT, SHPD, COH-DPW and HHF

  22. Historic Properties: All Plantation Era Alignment A- Not Selected as Preferred Alignment to Avoid 22 Archaeological Resources to be Preserved in Place (18914, 18915, 18917) Waiakea Elementary & 18915 Intermediate 18922 18914 18917 Schools 18918 18913 18923 Site Description Mitigation Proposed/Performed 20681 18919 18911 11 Features: Agricultural Rock Piles, terraces, mounds Data Recovery Completed 18912 18911 18916 18912 Mound Data Recovery Completed Alignment B – 18913 Linear Mound in Poor Shape - No Longer Significant None Upper Segment Alignment B – 18914 8 Features: terraces, mounds, platforms, modified outcrops Avoid – Preserve Above Komohana 18915 9 Features: Enclosure, Railroad Bed, Mounds, Platforms Avoid – Preserve Lower Segment to 18916 Platform and Wall Data Recovery Completed Already be Constructed in 18917 Two Mounds and Linear Rock Pile Avoid – Preserve Constructed and Current Project 18918 Three modified Pahoehoe Outcrops and a Mound Data Recovery Completed Mitigated 18919 36 Features: Mounds, Wall Segments, Platforms, modified Outcrops Data Recovery Completed 18922 Modified Outcrop No Further Work Needed 18923 Modified Outcrop No Further Work Needed 20681 16 Features: mounds, modified Outcrops, walls, Data Recovery Completed

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend