1
play

1 Presentation Outline Presentation Outline Project Background - PDF document

Hilton Baltimore Hilton Baltimore Convention Center Hotel Convention Center Hotel Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Faculty Advisor: Dr. Bahnfleth Bahnfleth Faculty Advisor: Dr. 1 Presentation Outline Presentation


  1. Hilton Baltimore Hilton Baltimore Convention Center Hotel Convention Center Hotel Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Faculty Advisor: Dr. Bahnfleth Bahnfleth Faculty Advisor: Dr. 1

  2. Presentation Outline Presentation Outline • Project Background • Existing Mechanical System • Design Objective • Mechanical Design Alternatives • Energy Analysis • First Costs • Life-Cycle Cost Analysis • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Project Background Project Background • Project Background • Project Cost: $250 Million • Existing Mechanical System • Groundbreaking: February • Design Objective 2006 • Mechanical Design Alternatives • Completion: August 2008 • Energy Analysis • Owner: Hilton Hotels • First Costs • Adjacent to Oriole Park at • Life-Cycle Cost Analysis Camden Yards and the Baltimore Convention Center • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 2

  3. Project Background Project Background • Project Background • Existing Mechanical System • Design Objective Guest Room Towers West Podium East Podium • Mechanical Design Alternatives • Three Levels • Levels 4 through 21 • Three Levels • Energy Analysis • Restaurant, Starbucks, Junior • 758 Guest Rooms, Service • Main Lobby, Grand Ballroom, Lounge, Meeting Areas Ballroom, Meeting Rooms • First Costs Rooms, Hotel Management • Life-Cycle Cost Analysis • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Existing Mechanical System Existing Mechanical System • Project Background Cooling • Existing Mechanical System • Comfort Link District Chilled Water System • Design Objective • (2) Plate and Frame Heat Exchangers • Mechanical Design Alternatives 1,000 tons each • Energy Analysis District Side – 37 F to 54 F • First Costs Building Side – 42 F to 56 F • Life-Cycle Cost Analysis • Two pumping zones with (2) pumps each • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 3

  4. Existing Mechanical System Existing Mechanical System • Project Background Heating • Existing Mechanical System • Trigen District Steam System • Design Objective 150 psi steam from Trigen • Mechanical Design Alternatives 50 psi steam after pressure reducing valve • Energy Analysis • (2) Shell and Tube Heat Exchangers • First Costs 810 gpm each • Life-Cycle Cost Analysis Entering Water Temp – 140 F • Electrical Breadth Leaving Water Temp – 180 F • Final Recommendation • Kitchens served by steam directly Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Existing Mechanical System Existing Mechanical System • Project Background Air Handling PAC 1 PAC 1 2% 2% • Existing Mechanical System • (8) Air Handling Units AHU 8 AHU 8 2% 2% • Design Objective AHU 1 AHUs 1-7 – VAV units with economizers AHU 7 AHU 1 AHU 7 20% 17% 20% 17% • Mechanical Design Alternatives AHU 8 – CAV unit with economizer • Energy Analysis AHU 6 AHU 6 • (4) Makeup Air Units AHU 2 11% AHU 2 11% 15% 15% • First Costs AHU 5 AHU 5 MAUs 1-2 – Serve Guest Room Towers 7% 7% AHU 3 AHU 4 AHU 3 • Life-Cycle Cost Analysis AHU 4 MAUs 3-4 – Serve Kitchen Spaces 16% 11% 16% 11% • Electrical Breadth System Area Breakdown System Area Breakdown • (1) Pool Air Conditioner • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 4

  5. Design Objective Design Objective • Project Background Chiller Plant Optimization Study • Existing Mechanical System • Consider numerous chiller plant design alternatives in order to quantitatively prove which alternative is • Design Objective the most cost-effective. • Mechanical Design Alternatives • A Life-Cycle Cost Analysis, based on first and yearly • Energy Analysis operating costs, will be the basis of the optimization. • First Costs • Life-Cycle Cost Analysis Lowest Life-Cycle Cost = Most Cost-Effective System • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Mechanical Design Alternatives Mechanical Design Alternatives • Project Background Option 1: District System with Backpressure • Existing Mechanical System Steam Turbine • Design Objective • Replaces Pressure Reducing Valve with a Backpressure Steam Turbine • Mechanical Design Alternatives • Energy Analysis • First Costs • Life-Cycle Cost Analysis • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 5

  6. Mechanical Design Alternatives Mechanical Design Alternatives • Project Background Option 2: On Site Centrifugal Chilling • Existing Mechanical System • Replaces Comfort Link District Chilled Water System • Design Objective with (2) 950 ton centrifugal chillers • Mechanical Design Alternatives • (2) condenser water pumps along with two-celled cooling tower added • Energy Analysis • Primary / Secondary pumping arrangement • First Costs • (2) primary pumps added • Life-Cycle Cost Analysis • All secondary pumps remain • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Mechanical Design Alternatives Mechanical Design Alternatives • Project Background Option 3: On Site Absorption Chilling • Existing Mechanical System • Replaces Comfort Link District Chilled Water System • Design Objective with (2) 950 ton double-effect absorption chillers • Mechanical Design Alternatives • Chillers utilize steam at 100 psi • Energy Analysis • (2) condenser water pumps along with two-celled cooling tower added • First Costs • Primary / Secondary pumping arrangement • Life-Cycle Cost Analysis • (2) primary pumps added • Electrical Breadth • All secondary pumps remain • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 6

  7. Mechanical Design Alternatives Mechanical Design Alternatives • Project Background Option 4: On Site Absorption Chilling with • Existing Mechanical System Backpressure Steam Turbine • Design Objective • Identical to previous design alternative, but with Backpressure Steam Turbine added • Mechanical Design Alternatives • Extraction type Backpressure Steam Turbine required, • Energy Analysis allowing for 2 separate outlet steam pressures • First Costs • Life-Cycle Cost Analysis • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel Hilton Baltimore Convention Center Hotel Energy Analysis Energy Analysis • Project Background • Existing Mechanical System In order to calculate the yearly operating costs of • Design Objective all the systems, two factors must be known… • Mechanical Design Alternatives • Cost of energy (Utility Rates) • Energy Analysis • Amount of energy (Hourly energy usage data) • First Costs • Life-Cycle Cost Analysis • Electrical Breadth • Final Recommendation Andrew Rhodes Andrew Rhodes Hilton Baltimore Convention Center Hotel Spring 2007 Spring 2007 Hilton Baltimore Convention Center Hotel 7

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend