Your Input on VTAs 2019 New Transit Service Plan Feb 12, 2019 1 - - PowerPoint PPT Presentation

your input on vta s
SMART_READER_LITE
LIVE PREVIEW

Your Input on VTAs 2019 New Transit Service Plan Feb 12, 2019 1 - - PowerPoint PPT Presentation

Your Input on VTAs 2019 New Transit Service Plan Feb 12, 2019 1 Presenter and Facilitator Jay Tyree Cody Kraatz Senior Transportation Administrator of Planner Digital Communications 2 History and Why Were Here Today 2016 Draft


slide-1
SLIDE 1

Feb 12, 2019

Your Input on VTA’s 2019 New Transit Service Plan

1

slide-2
SLIDE 2

Presenter and Facilitator

2

Cody Kraatz Administrator of Digital Communications Jay Tyree Senior Transportation Planner

slide-3
SLIDE 3

2016 Draft Next Network + community engagement 2017 VTA Board adopts final Next Network plan …waiting for BART service to implement new network… 2018 VTA Ad Hoc Financial Stability Committee recommends service change Dec 2018 VTA Board directs staff to develop new service plan Jan 2019 VTA Board directs staff to conduct outreach on new plan January Community engagement February Community engagement

History and Why We’re Here Today

3

slide-4
SLIDE 4

VTA Board Direction for the 2019 New Transit Service Plan

4

Maintain today’s service level (no service increase) More ridership service & less coverage service Minimize cuts in South County

1 2 3

slide-5
SLIDE 5

5

current service

$360M / year

total cost

70/30

ridership/coverage

Next Network

$375M / year

total cost

83/17

ridership/coverage

Service Plan

$360M / year

total cost

90/10

ridership/coverage

Draft 2019 New Transit

slide-6
SLIDE 6

Two Types of Transit Routes

  • Ridership routes: service to areas with higher ridership
  • Coverage routes: service to areas with lower ridership

70%

RIDERSHIP

30%

COVERAGE

VTA SERVICE TODAY

slide-7
SLIDE 7

10,000 Points of Feedback From You Created this Plan

7

What we heard…  Service should be more frequent  Willing to walk to faster transit  Less coverage service  More ridership service

slide-8
SLIDE 8

8

  • What you like, what you don’t
  • Where you would add service
  • Where you would cut service

VTA staff role explain the proposal pass your feedback on to the VTA Board use your feedback to revise the plan

Feedback We’d Like from You

slide-9
SLIDE 9

Proposed Light Rail Service

9

Shortened (Baypointe – Santa Teresa) No change (Old Ironsides – Winchester) No change (Mountain View – Alum Rock) Replaced with bus route

slide-10
SLIDE 10

Bus Service Improvements (compared to Next Network)

10

Frequent Service to New Areas

26 68

More Frequent Service Between BART and Downtown San Jose

500

More Morning and Evening Trips on Popular Routes

522 23

slide-11
SLIDE 11

Bus Service Cuts (compared to Next Network)

11

Discontinue Entire Route

65 83

Fewer Trips in the Early Morning & Late Evening Reduce Weekend Service Frequency

27 44 20 21 22 31 40 44 47 52 53 56 57 59 61 63 71 77 27 47 59 72 73

slide-12
SLIDE 12

Bus Service Cuts (compared to Next Network)

12

Change Route Alignment

53 56

Discontinue Entire Express Bus Route

101 122 182 185

Discontinue Some Express Bus Trips

102 103 121 168

slide-13
SLIDE 13

Community Engagement

13

  • 6 community meetings + targeted meetings
  • Website for detailed information
  • Online video presentation
  • Printed materials on buses + trains
  • Email blasts, blog posts
slide-14
SLIDE 14

January Community engagement February Community engagement March Revise plan April Final plan to VTA committees May Final plan to VTA Board of Directors June July Implementation activities (scheduling, manufacturing signage, August preparing and printing passenger materials, operator training, etc.) September October New service ready for when BART opens

Next

14

slide-15
SLIDE 15

Q&A

15 Feedback we need from you

  • What you like + what you don’t
  • Where you would add service
  • Where you would cut service
slide-16
SLIDE 16

feedback deadline: February 28 newtransitplan.vta.org community.outreach@vta.org

detailed information • questions • submit additional feedback

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

18

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

24

slide-25
SLIDE 25

25

slide-26
SLIDE 26

COUNTY

RESIDENTS

NEAR FREQUENT TRANSIT

243,000 additional residents + 170,000 additional jobs near VTA’s Frequent Network

26

COUNTY

JOBS

NEAR FREQUENT TRANSIT current 42% Next Network 51% proposal 56% current 41% Next Network 57% proposal 59%

slide-27
SLIDE 27

27

Boardings per Hour of Current Bus Routes

2019 Plan Improvement 2019 Plan Reduction Next Network Revision

15 boardings/hour minimum standard

slide-28
SLIDE 28

28

Cost Per Boarding of Current Bus Riders

2019 Plan Improvement 2019 Plan Reduction Next Network Revision

slide-29
SLIDE 29

Ridership Impact

7-9%

higher ridership than current service

29

1%

lower ridership than Next Network plan

slide-30
SLIDE 30

Productivity for VTA Express Bus Routes

30

15

riders onboard each bus trip

42%

full (seats occupied)

6.3

boardings per hour

3%

farebox recovery

$33.09

cost per boarding

19.2 11% $8.33

VTA local bus