xfel cost and uncertainties risk analysis
play

XFEL Cost and Uncertainties/risk Analysis R. Brinkmann, DESY ILC - PowerPoint PPT Presentation

XFEL Cost and Uncertainties/risk Analysis R. Brinkmann, DESY ILC workshop, Snowmass, August 2005 R. Brinkmann, DESY European XFEL costing Introductory remarks Construction cost estimate is based on the XFEL design described in the Oct


  1. XFEL Cost and Uncertainties/risk Analysis R. Brinkmann, DESY ILC workshop, Snowmass, August 2005 R. Brinkmann, DESY European XFEL costing

  2. Introductory remarks • Construction cost estimate is based on the XFEL design described in the Oct 2002 supplement to the TESLA TDR; prices have been adjusted to the year 2005 (escalating with 1.5%/year from the original year 2000 basis) • An update of the cost estimate is ongoing, will be completed by ~end 2005 as part of a new TDR (taking into account design changes, different site, more detailed analysis of some of the sub- systems, etc.) • Personnel costs are estimated on the basis of salaries at DESY (year 2005), including an overhead to cover basic central services and administration (different from 2002 TDR supplement) R. Brinkmann, DESY European XFEL costing

  3. Project time schedule 2004 2006 2012/13 2014/15 preparation construction beam operation SASE1 project start SASE2+3, 2009: LCLS start spont. rad operation (SLAC) • Assumes final project approval & funding at European level in ~mid 2006 • Site approval (“PFV”) and preparations for placing orders for civil construction before official project start R. Brinkmann, DESY European XFEL costing

  4. Estimated total project cost 793M€, year 2005 basis, not including project preparation and escalation over construction period Investment & Personnel distribution 30 25 % of total cost 20 personnel/% 15 invest/% 10 5 0 c s n r l e i a y e o r v n s p u i t c i b o o t l c u h & & 1 u s p 0 r r t e & c t n t s c l i o u a s a c r d f 6 2 n n 4 0 0 u 0 i 5 3 0 0 The way the cost distribution is presented here reflects the present work package structure of the XFEL project group R. Brinkmann, DESY European XFEL costing

  5. Focus on this WPG in the following R. Brinkmann, DESY European XFEL costing

  6. Accelerator schematic layout beam lines Beam distr. Main linac 0.4 km Beam energy 20 GeV Collimation acc gradient 22.9 MV/m Diagnostics Bunch spacing 200 ns 10…20GeV (-->25GeV) beam current 5 mA power � beam p. klystron 3.8 MW incl. 10% + 15% overhead 4.8 MW 4.6 ⋅ 10 6 1.7 km matched Q ext RF pulse 1.37 ms 120 modules LINAC Beam pulse 0.65 ms 30 RF stations # bunches p. pulse 3250 Rep. rate 10 Hz 2 GeV Av. Beam power 650 kW BC-II BC-I 0.5GeV Injector R. Brinkmann, DESY European XFEL costing

  7. Input for cost estimate • TDR2001: industrial studies for production of ~20,000 cavities, treatment, and assembly of modules • Oct 2002: update of studies for smaller # of components • Application of scaling rules (cost/component vs. # components) for single components (e.g. tuners, RF couplers) • Overall consistency check: cost per module factor ~1.7 higher for XFEL linac than for TESLA linac • In contrast to TDR2001, no large reduction factor assumed for RF system components (e.g. need ~40 instead of ~600 klystrons – manufacturer wouldn’t set up new large-scale production facility) • Counter check with present prices and experience from other projects where possible (TTF, HERA) R. Brinkmann, DESY European XFEL costing

  8. Method for personnel cost estimate • For each work package, the amount of required laboratory personnel for the construction phase was estimated (FTEs) • A matrix map was created between the DESY M-division technical groups and the work packages (how much of the work per WP would be done by which M-group) • From the known salary structure in each M-group thus the salary structure for the WPs was derived (this procedure was simplified by defining small number of salary classes, in the final representation just two: “scientific” and “technical”) • Different costs per FTE in the different WPs are the result – on average (all WPs) this figure is 77k€/FTE (2005) including overhead R. Brinkmann, DESY European XFEL costing

  9. Approach to cost uncertainty/risk analysis • Detailed analysis for the entire project is in progress; methodology is described here for the largest (~27% of total cost) XFEL Work Package group (WPG01, linac) • Statistical analysis of cost probability distribution using a set of uncertainty categories for the cost items in the WPs (named “standard” categories in the following) • Determination of maximum risk with “conservative” (or rather: pessimistic) uncertainty assumptions: – Present prices for components/sub-systems (low number, partially prototypes!) have been collected where available – Upper limit for cost risk defined by assuming that only half of the cost reduction from present price to price used for the XFEL cost evaluation can be achieved R. Brinkmann, DESY European XFEL costing

  10. Standard cost uncertainty categories Category definition lower/upper range C1 good experience and present price for this component/sub-system are -10% / +10% available, no cost scaling for large quantities has been applied C2 experience and present price for similar components/sub-systems are -20% / +20% available, no or only minor scaling to large quantities has been applied C3 present price is available, significant (>25%) cost scaling to large quantities -10% / +20% has been applied C4 present price is available, price from industrial study is used which results -10% / +20% in significant (>25%) cost reduction for production of large quantities C5 present price not available, price from industrial study is used -10% / +20% C6 Required technology pushes state-of-the art, significant R&D still required -10% / +50% P1 personnel requirements well known due to present experience or with -10% / +10% similar systems in previous large scale projects P2 personnel requirements less certain or relatively large fraction of R&D -20% / +20% included in this WP Furthermore, raw material cost uncertainties (volatility of metal and currency markets) have been added where appropriate (e.g. Niobium sheets & parts) R. Brinkmann, DESY European XFEL costing

  11. Result of analysis with standard categories Cost probability distribution for XFEL WP group 1 (linac), standard uncertainty categories 250000 240000 230000 Cost / kEUR 220000 evaluated cost 210000 200000 190000 0 20 40 60 80 100 Probability / % R. Brinkmann, DESY European XFEL costing

  12. Result of maximum risk analysis Cost probability distribution for XFEL WP group 1 (linac), conservative analysis (get only 1/2 of price reduction w.r.t. present price) 250000 240000 w. 10% risk budget 230000 cost / kEUR 220000 210000 evaluated cost 200000 190000 0 20 40 60 80 100 probability / % R. Brinkmann, DESY European XFEL costing

  13. R. Brinkmann, DESY % variation -40 -20 20 40 60 80 0 modulator mod. power assumed uncertainties in percent for cost items WPG01 klystron auxiliaries Max risk analysis cont’d pulse tanks/oil safety cabling Kl+Mod (linac), max risk scenario driver amp complete cryostat cabling, Niobium treatment personnel personnel personnel personnel personnel European XFEL costing personnel personnel % up % down

  14. Risk of delays due to problems at manufacturers (or participating institutes) • E.g. over-commitment (or as extreme case, bankruptcy) at manufacturer can cause delay of project construction • Delay can to some extend be minimized by re-scheduling installation, testing or technical commissioning • The resulting cost risk is determined by multiplying the delay with the personnel cost per unit time • Resulting cost risk for a delay of 6 months is approximately 2% (~15M€) of the total project cost R. Brinkmann, DESY European XFEL costing

  15. Conclusions regarding risk analysis • Methodology will be applied to all Work Package groups – overall picture not expected to drastically change • Adjust the estimated cost by ~+1…2% to match the probability distribution at 50% (instead of ~35%) • Risk budget of about 10% of total project cost appears reasonable • This analysis of uncertainties does not include cost modifications due to changes in the detailed design of the facility or additional R&D items identified by STI – final cost update will be prepared as part of the TDR R. Brinkmann, DESY European XFEL costing

  16. Operation cost distribution of XFEL operating cost (total 83 MEUR/year 2005 basis) 25 20 Million Euro 15 10 5 0 D d p y s h h c a t n s & t c x i e e c o i a e R b h i r m / r r r t l r t e u e s e c / t f n y l e v a e e l n l o w K r n E / o n n d , s m e o d r s e t a u n r p i l i e a e p H M R. Brinkmann, DESY European XFEL costing

  17. Operation cost cont’d • Estimated personnel is 265 FTEs for accelerator & infrastructure, 166 FTEs for photon beam lines & exp. area (salary classes derived similarly as for construction phase) • Electricity cost assumes 14MW/5,500h + 3.4MW/full year at 8c/kWh • Maintenance/repair, refurbishment and R&D are assumed with ~2% of initial investment each • Additional overhead introduced to cover expenses for user service, guest scientists, student programme, etc. R. Brinkmann, DESY European XFEL costing

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend